Kevlinx BRU01

Neder-Over-Heembeek, Brussels, Belgium

Reviewed 28 Sept 20268 sources
Watch this site

Watch Kevlinx BRU01

Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.

Fields marked * are required.

Checking enquiry availability…

Request details

Register your interest in monitoring this record. Alerts are not active yet. Site Watch will cost €150 per site per month excluding VAT after any included trial.

Optional. Public information only. Do not include confidential or non-public information.

Project brief

Operating first phases on citydev’s Galilei land under a long-term lease. Technical delivery now has a site-specific Elia route, cooling supplier and carrier relationship.

Read overview
Next check

Check the signed demand allocation and the scope behind BESIX’s 40 MVA rating.

Open the full check

Overview

Operating first phases on citydev’s Galilei land under a long-term lease. Technical delivery now has a site-specific Elia route, cooling supplier and carrier relationship.

Developer / applicant
Kevlinx Data Centers
Owner
citydev.brussels (land; long-term lease to Kevlinx)
Operator
Kevlinx Data Centers

Planning and delivery status

Kevlinx announced ready-for-service status on 9 January 2026. BESIX separately confirms phase1A/1B handover on 2 December 2025.

Stage source: 9 Jan 2026

Project intelligence. This record does not establish that the land or facility is available to acquire.

POWER STUDY

Power

What the power evidence establishes

The site-specific connection scope has not been established for this record.

Power classDNo qualifying rung

No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.

The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.

Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.

Read the rules and verification levels
01

Capacity ladder and evidence

Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.

01

Applied

Unknown

Not established from the public records reviewed.

What applied mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the applied connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the applied connection evidence cover?
Verification
Unknown
02

Offered

Unknown

Not established from the public records reviewed.

What offered mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the offered connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the offered connection evidence cover?
Verification
Unknown
03

Accepted / contracted

Unknown

Not established from the public records reviewed.

What accepted or contracted mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the accepted connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the accepted connection evidence cover?
Verification
Unknown
04

Energised

Unknown

Not established from the public records reviewed.

What energised mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the energised connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the energised connection evidence cover?
Verification
Unknown
Connection point and load boundaries
Network operator
Unknown

Not established from the public records reviewed.

Which TSO or DSO is responsible for this demand connection?
Connection point
Unknown

Not established from the public records reviewed.

What is the operator-confirmed connection substation or circuit?
Voltage
Unknown

Not established from the public records reviewed.

What voltage level is specified for the demand connection?
Straight-line distance
Unknown

Not established from the public records reviewed.

What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Published route length
Unknown

Not established from the public records reviewed.

What grid route length is published, and for which circuit?

IT load

Unknown

Not established from the public records reviewed.

What is the published IT load in MW?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the IT load in MW stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the IT load in MW cover?

Facility load

Unknown

Not established from the public records reviewed.

What is the published facility load in MW?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the facility load in MW stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the facility load in MW cover?

Import capacity

Unknown

Not established from the public records reviewed.

What is the published import capacity in MVA?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the import capacity in MVA stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the import capacity in MVA cover?

These are different electrical quantities. No power factor, PUE or available import is assumed from an IT-load statement.

Connection agreement and conditions
Agreement type
Unknown

Not established from the public records reviewed.

What connection agreement type and current status are documented?
Phased capacity
Unknown

Not established from the public records reviewed.

Does the agreement impose phased import-capacity limits?
Flexibility obligations
Unknown

Not established from the public records reviewed.

What flexibility or curtailment obligations apply?
On-site generation obligations
Unknown

Not established from the public records reviewed.

What on-site generation obligations apply?
Securities posted
Unknown

Not established from the public records reviewed.

What securities are required, posted and still valid?
Longstop dates
Unknown

Not established from the public records reviewed.

What connection longstop or milestone dates apply?
02

Conflicts and scope comparisons

No conflicting pair is recorded. This does not establish that all public statements have been reconciled.

03

Belgium grid context

Network publications frame the claim. They do not allocate capacity to this site.

No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.

04

Derived energisation window

Earliest plausible yearUnknown
Latest plausible yearUnknown

The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.

Rule

Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.

No observed inputs establish this result.

Dependencies driving the range

  • Connection-dependent reinforcement scope and completion dates: unknown.
  • Grid-works planning status and programme: unknown.
  • Applicable connection-policy conditions and programme: unknown.

What the earliest case requires

  • Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
  • Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
  • Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.

Missing inputs leave the range open

  • A dated, document-verified import-MVA rung for the assessed scope.
  • An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
  • Connection-dependent reinforcement scope and completion dates
  • Grid-works planning status and programme
  • Applicable connection-policy conditions and programme
05

Indicative HV and connection capex

Unknown

Rule and scope

Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.

No observed inputs establish this result.

Published connection works scope
Unknown

Not established from the public records reviewed.

What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Scope completeness
Unknown

Not established from the public records reviewed.

Is the published connection scope complete enough to match every component to a sourced benchmark?

Scope questions

  • Obtain a published complete connection scope with voltage, configuration and measured quantities.
  • Establish that every necessary connection-work component is included in the published scope.
  • Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
06

Alternatives and policy exposure

Behind-the-meter generation

Unknown

Not established from the public records reviewed.

What behind-the-meter generation is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require behind-the-meter generation?

Battery storage

Unknown

Not established from the public records reviewed.

What battery storage is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require battery storage?

Private wire

Unknown

Not established from the public records reviewed.

What a private wire is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require a private wire?

Gas

Unknown

Not established from the public records reviewed.

What gas supply or generation is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require gas supply or generation?

Connection claim against current policy

Unknown

Not established from the public records reviewed.

Does the published connection claim meet the policy applicable to its application date, location and agreement status?
07

Open questions for a Reality Check

Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.

60 questions to resolve
  1. Which TSO or DSO is responsible for this demand connection?

    Not established from the public records reviewed.

  2. What is the operator-confirmed connection substation or circuit?

    Not established from the public records reviewed.

  3. What voltage level is specified for the demand connection?

    Not established from the public records reviewed.

  4. What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?

    Not established from the public records reviewed.

  5. What grid route length is published, and for which circuit?

    Not established from the public records reviewed.

  6. What applied mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  7. What is the effective date of the applied connection evidence?

    Not established from the public records reviewed.

  8. Which buildings or phases does the applied connection evidence cover?

    Not established from the public records reviewed.

  9. What evidence level can be supported for capacityLadder.applied?

    Verification has not been established.

  10. What offered mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  11. What is the effective date of the offered connection evidence?

    Not established from the public records reviewed.

  12. Which buildings or phases does the offered connection evidence cover?

    Not established from the public records reviewed.

  13. What evidence level can be supported for capacityLadder.offered?

    Verification has not been established.

  14. What accepted or contracted mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  15. What is the effective date of the accepted connection evidence?

    Not established from the public records reviewed.

  16. Which buildings or phases does the accepted connection evidence cover?

    Not established from the public records reviewed.

  17. What evidence level can be supported for capacityLadder.accepted?

    Verification has not been established.

  18. What energised mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  19. What is the effective date of the energised connection evidence?

    Not established from the public records reviewed.

  20. Which buildings or phases does the energised connection evidence cover?

    Not established from the public records reviewed.

  21. What evidence level can be supported for capacityLadder.energised?

    Verification has not been established.

  22. What connection agreement type and current status are documented?

    Not established from the public records reviewed.

  23. Does the agreement impose phased import-capacity limits?

    Not established from the public records reviewed.

  24. What flexibility or curtailment obligations apply?

    Not established from the public records reviewed.

  25. What on-site generation obligations apply?

    Not established from the public records reviewed.

  26. What securities are required, posted and still valid?

    Not established from the public records reviewed.

  27. What connection longstop or milestone dates apply?

    Not established from the public records reviewed.

  28. What is the published IT load in MW?

    Not established from the public records reviewed.

  29. On what electrical basis is the IT load in MW stated?

    Not established from the public records reviewed.

  30. Which phase or campus does the IT load in MW cover?

    Not established from the public records reviewed.

  31. What is the published facility load in MW?

    Not established from the public records reviewed.

  32. On what electrical basis is the facility load in MW stated?

    Not established from the public records reviewed.

  33. Which phase or campus does the facility load in MW cover?

    Not established from the public records reviewed.

  34. What is the published import capacity in MVA?

    Not established from the public records reviewed.

  35. On what electrical basis is the import capacity in MVA stated?

    Not established from the public records reviewed.

  36. Which phase or campus does the import capacity in MVA cover?

    Not established from the public records reviewed.

  37. What operator-published connection-to-energisation duration applies to this site and connection stage?

    An application-to-offer processing target is not an energisation duration.

  38. Which reinforcements does the connection depend on, and what dates are published?

    Not established from the public records reviewed.

  39. Which grid works require planning, and what is their current consent status and dated programme?

    Not established from the public records reviewed.

  40. Which connection-policy conditions apply, and when could they be satisfied?

    Not established from the public records reviewed.

  41. What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?

    Not established from the public records reviewed.

  42. Is the published connection scope complete enough to match every component to a sourced benchmark?

    Not established from the public records reviewed.

  43. What behind-the-meter generation is evidenced, and at what scope?

    Not established from the public records reviewed.

  44. Does the applicable planning or connection policy require behind-the-meter generation?

    Not established from the public records reviewed.

  45. What battery storage is evidenced, and at what scope?

    Not established from the public records reviewed.

  46. Does the applicable planning or connection policy require battery storage?

    Not established from the public records reviewed.

  47. What a private wire is evidenced, and at what scope?

    Not established from the public records reviewed.

  48. Does the applicable planning or connection policy require a private wire?

    Not established from the public records reviewed.

  49. What gas supply or generation is evidenced, and at what scope?

    Not established from the public records reviewed.

  50. Does the applicable planning or connection policy require gas supply or generation?

    Not established from the public records reviewed.

  51. Does the published connection claim meet the policy applicable to its application date, location and agreement status?

    Not established from the public records reviewed.

  52. Which checked country-grid sources and location-specific constraints apply to this connection?

    No country-context relationship has been established for this record.

  53. Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.

    Connection-cost scope question.

  54. Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.

    This missing input leaves an energisation bound unknown.

  55. Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.

    This missing input leaves an energisation bound unknown.

  56. Resolve the energisation input: Connection-dependent reinforcement scope and completion dates

    This missing input leaves an energisation bound unknown.

  57. Resolve the energisation input: Grid-works planning status and programme

    This missing input leaves an energisation bound unknown.

  58. Resolve the energisation input: Applicable connection-policy conditions and programme

    This missing input leaves an energisation bound unknown.

  59. Obtain a published complete connection scope with voltage, configuration and measured quantities.

    This scope or reference gap prevents a complete indicative connection capex band.

  60. Establish that every necessary connection-work component is included in the published scope.

    This scope or reference gap prevents a complete indicative connection capex band.

Use these questions to scope a Power Reality Check.

Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.

Request a Reality Check
Earlier capacity notes and source context
40 MVAProject capacity

BESIX-published facility rating for the phase1A/1B project. Operator separately distinguishes 16MW IT powered shell and 4MW fitted IT at launch; 40MVA is not spare capacity.

Published claimCapacity source
Import rights and connection evidence

Equans identifies a direct connection to Elia’s Buda substation about 2 km away and an 11 kV UPS installation. Connection and UPS details do not establish spare import rights.

IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.

Planning & utilities

8 of 10 categories contain evidence. Each status applies to its specific claim.

Planning & decisions

Partial evidence

OpenPermits records KevlinX Belgium’s original class 1B environmental permit 04/IPE/1715193 (municipal A709/2019; mixed A387/2019) at Avenue Antoon van Oss 27–29 as granted on 19 November 2019, with listed validity to 6 February 2035. The indexed later urban case 04/PU/2014327 is a separate alteration application; its retrieved snapshot has no decision date. Full-page retrieval was blocked, so current phase-2 status is not resolved.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Retrieve the live decisions for 04/PU/2014327 and linked 04/IPE/2028807 and their conditions, reconciling later reported 2026 grants with the older indexed application state.

Grid & import rights

Partial evidence

Equans identifies a direct connection to Elia’s Buda substation about 2 km away and an 11 kV UPS installation. Connection and UPS details do not establish spare import rights.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Check the signed demand allocation and the scope behind BESIX’s 40 MVA rating.

Fibre & dark fibre

Partial evidence

Kevlinx names Colt as a BRU01 connectivity partner. Carrier presence is evidenced, but physical route separation and site-entry details are not.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Verify independent routes and dark-fibre availability for the site.

Ownership & development control

Partial evidence

The joint operator/citydev statement identifies a long-term lease on citydev’s Galilei site. Lease duration, assignment terms and title encumbrances were not disclosed.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Verify the landholding entity and executed lease restrictions.

Land, footprint & access

Partial evidence

The land statement describes a 2.5 ha Galilei holding; Colt’s partnership article uses 24,000 m² for the campus. The boundaries behind these figures remain unreconciled.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Match lease, campus and building perimeters before calculating developable area.

Flood, ground & environment

Partial evidence

BESIX includes decontamination in its civil/structural/architectural scope. This is contractor evidence of remediation work, not an environmental closure certificate.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Find the remediation acceptance, residual restrictions and operating environmental permit.

Water, cooling & heat

Partial evidence

Equans describes completed phase-1 indirect-air cooling. OpenPermits separately records refusal on 27 March 2026 of 04/IPEEXT/2022812, concerning phase-2 cooling-network changes and regularisation of undeclared cooling installations. This historic refusal does not establish a current campus prohibition: a subsequent environmental case 04/IPE/2028807 is linked, but its operative decision was not retrieved.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Read the refusal reasons and subsequent 04/IPE/2028807 decision; distinguish authorised phase-1 cooling from the revised phase-2 scope and water obligations.

Programme & delivery

Partial evidence

BESIX dates phase 1A/1B handover to 2 December 2025; the operator announced service in January 2026. Equans reports tested technical systems ready for service.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Reconcile commissioned fitted IT with powered-shell capacity and future fit-out milestones.

Not assessed

Land-use zoningDemand & location fit
Evidence still needed
  • Land-use zoning

    The site boundary has not been matched to the current adopted zoning map and data-centre use policy.

  • Demand & location fit

    Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.

Project team

Appointments are limited to the project, phase and scope supported by each source.

Main contractor

Specialists & vendors

Technical design and installation, including electrical distribution, medium-voltage UPS, cooling and fire systems; customer IT excluded.

Appointment source

Unlisted roles have no project-specific appointment recorded.

Sources

Publication dates are shown where known. Review dates do not establish approval or commissioning.

  1. Kevlinx: BRU01 livekevlinx.com · 9 Jan 2026
  2. BESIX: phase1A/1B handover and project scopebesix.com · 13 Jan 2026
  3. Kevlinx/citydev: land ownership and long-term leasekevlinx.com · 6 Nov 2025
  4. Equans: BRU01 technical systems completedequans.be · 29 Jan 2026
  5. Kevlinx and Colt: BRU01 connectivity partnershipkevlinx.com · Publication date unstated
  6. OpenPermits: KevlinX Belgium original environmental permit 04/IPE/1715193openpermits.brussels · 19 Nov 2019
  7. OpenPermits: KevlinX cooling-extension refusal 04/IPEEXT/2022812openpermits.brussels · 27 Mar 2026
  8. OpenPermits: BRU01 alterations case 04/PU/2014327 and linked case historyopenpermits.brussels · Publication date unstated

Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.