Skip to content
Menu

Data centres

European projects, capacity and delivery teams.

Explore land research
Map viewBrowse Europe

173 projects160 with viability evidence

Thames Valley Park Data Centre

Earley, Reading·United Kingdom

Developer Mapeley / FH Trustees Limited and FH Trustees 2 Limited as applicants

In planningStage source 28 Sept 2026
Published capacity72 MW ITPublished claim
Proposed full-campus IT design capacity stated by the project team. The planning energy material separately describes approximately 110 MW peak facility demand; neither figure is commissioned load, secured grid import or available customer capacity.

Proposed full-campus IT design capacity stated by the project team. The planning energy material separately describes approximately 110 MW peak facility demand; neither figure is commissioned load, secured grid import or available customer capacity.

Capacity source

110 MW facility · Peak facility demand
Approximate completed-site peak demand reported from the submitted Energy Strategy, including cooling and electrical plant; not IT load or secured import.
Published claim

1.8 MW import · Existing site grid supply
Existing supply described for the administration building during the initial fuel-cell phase; not evidence of supply to the proposed data halls.
Published claim

60 MVA · Later SSEN connection
Applicant Utilities Statement scope reported as secured but dependent on transmission reinforcement and targeted from 2037. It does not cover the stated 110 MW facility peak and is not an achieved energisation.
Published claim

49.9 MW unspecified · Proposed on-site fuel-cell plant
Utilities Statement plant rating for proposed natural-gas solid-oxide fuel cells. The Energy Strategy separately gives about 42.5 MW initial effective supply; generation plant is not grid import capacity.
Published claim

10/10 evidence categories5 sources·5 team entries

Echelon DUB10 — Clondalkin campus

Clondalkin, Dublin·Ireland

Developer Echelon Data Centres

OperatingStage source 17 Sept 2026
Published capacity>90 MW ITPublished claim
Published campus design exceeds 90 MW IT; this is not verified commissioned load or utility import.

Published campus design exceeds 90 MW IT; this is not verified commissioned load or utility import.

1/10 evidence categories11 sources·17 team entries

AVAIO Orion / Mayo Data Hub — Killala

Killala, County Mayo·Ireland

Developer Mayo Data Hub Limited / AVAIO Digital

Permission refusedStage source 15 Sept 2026
Published capacity40 MW ITPublished claim
Proposed IT load in submitted EIAR and ACP assessment; refused scheme, not delivered or contracted capacity.

Proposed IT load in submitted EIAR and ACP assessment; refused scheme, not delivered or contracted capacity.

50 MW facility · Average facility electricity demand
Approximate average electrical requirement in EIAR; not a maximum-import agreement or connection offer.
Published claim

8/10 evidence categories11 sources·9 team entries

Echelon DUB20 — Arklow

Arklow, County Wicklow·Ireland

Developer Echelon Data Centres

Under constructionStage source 15 Sept 2026
Published capacity90 MW ITPublished claim
Initial campus IT target confirmed by Echelon; not commissioned capacity or a published utility-import MVA.

Initial campus IT target confirmed by Echelon; not commissioned capacity or a published utility-import MVA.

2/10 evidence categories9 sources·10 team entries

CRA Prague Gateway DC

Jíloviště, Prague region·Czechia

Developer CRA Prague Gateway DC a.s. / České Radiokomunikace

Under constructionStage source 7 Sept 2026
Published capacity4 MW ITPublished claim
Initial phase-one IT module in Cordiant's 2026 results; full campus design is 17.3 MW IT. These are development capacities, not operational MW.

Initial phase-one IT module in Cordiant's 2026 results; full campus design is 17.3 MW IT. These are development capacities, not operational MW.

22 MW unspecified · Power supported by 2N infrastructure
2N-supported subset of the reported 26 MW site power, per Cordiant's June 2026 filing; not an additional allocation or verified import entitlement.
Published claim

26 MW unspecified · Reported site power
Site power reported by Cordiant, including the 22 MW with fully duplicated 2N infrastructure. Utility contract and available headroom are not published.
Published claim

10/10 evidence categories11 sources·6 team entries

Pure DC LON01B2 — Brent Cross expansion

Brent Cross, North London·United Kingdom

Developer Pure Data Centres Group

Under constructionStage source 3 Sept 2026
Published capacity70 MW unspecifiedPublished claim
Published B2 development capacity. The reviewed release does not distinguish IT load from facility demand; no import MVA is verified.

Published B2 development capacity. The reviewed release does not distinguish IT load from facility demand; no import MVA is verified.

6/10 evidence categories4 sources·2 team entries

DataVita DV1 — Fortis

Chapelhall, North Lanarkshire·United Kingdom

Developer DataVita

OperatingStage source 2 Sept 2026
Published capacity40 MW unspecifiedConflicting published claim
DV1 webpage overview power; conflicts with specification table.

DV1 webpage overview power; conflicts with specification table.

Capacity source

24 MW unspecified · Published power available
DV1 webpage technical specification; scope/date not reconciled with 40 MW overview.
Published claim

Published overview: DV1 webpage overview power; conflicts with specification table.

4/10 evidence categories5 sources·1 team entry

Green Mountain LON-East campus

Romford, London·United Kingdom

Developer Green Mountain

OperatingStage source 1 Sept 2026
Published capacity37 MW unspecifiedPublished claim
Secured/planned campus power capacity, including future development; not all live IT load.

Secured/planned campus power capacity, including future development; not all live IT load.

7/10 evidence categories5 sources·2 team entries

atNorth FIN04 campus

Myllykoski / Kouvola·Finland

Developer atNorth

Under constructionStage source 28 Aug 2026
Published capacity430 MW unspecifiedPublished claim
Planned total FIN04 campus capacity in the July YIT announcement; not the capacity of either individual YIT contract.

Planned total FIN04 campus capacity in the July YIT announcement; not the capacity of either individual YIT contract.

8/10 evidence categories9 sources·1 team entry

Digital Realty ZUR4

Glattbrugg / Zurich·Switzerland

Developer Digital Realty

Under constructionStage source 27 Aug 2026
Published capacity15 MW ITPublished claim
Planned ZUR4 IT capacity, additional to the ZUR1–ZUR3 campus; not operational capacity or grid MVA.

Planned ZUR4 IT capacity, additional to the ZUR1–ZUR3 campus; not operational capacity or grid MVA.

5/10 evidence categories2 sources·0 team entries

Nebius Pajarila — Lappeenranta campus

Kettukuja, Pajarila, Lappeenranta, South Karelia·Finland

Developer Nebius; Polarnode (development and enabling works)

Under constructionStage source 11 Aug 2026
Published capacity310 MW unspecifiedPublished claim
Approximate ultimate campus rating; electrical basis and commissioned extent not established. Not first-phase import, IT load or available customer capacity.

Approximate ultimate campus rating; electrical basis and commissioned extent not established. Not first-phase import, IT load or available customer capacity.

Capacity source
6/10 evidence categories7 sources·4 team entries

Greenergy Data Centers — 22 MW expansion

Hüüru, Tallinn region·Estonia

Developer MCF Group Estonia

Under constructionStage source 31 Jul 2026
Published capacity22 MW ITPublished claim
Additional IT power and cooling under the expansion contract, taking the stated campus total to 31.5 MW on completion.

Additional IT power and cooling under the expansion contract, taking the stated campus total to 31.5 MW on completion.

7/10 evidence categories5 sources·2 team entries

MERLIN Edged Barcelona — PLZF

Barcelona, Zona Franca·Spain

Developer MERLIN Properties / Edged Energy

OperatingStage source 28 Jul 2026
Published capacity22 MW ITPublished claim
Barcelona PLZF IT capacity in MERLIN's June 2026 company presentation. July results state repowering delivered; not a grid import limit or proof of spare capacity.

Barcelona PLZF IT capacity in MERLIN's June 2026 company presentation. July results state repowering delivered; not a grid import limit or proof of spare capacity.

Capacity source

16 MW IT · Legacy conflicting operator field
Second critical-load field still on the live page; superseded scope is not explained. Not additive to 22 MW and not spare capacity.
Conflicting published claim

Legacy conflicting operator field: Second critical-load field still on the live page; superseded scope is not explained. Not additive to 22 MW and not spare capacity.

7/10 evidence categories4 sources·1 team entry

MERLIN Edged Lisbon — VFX first development phase

Vila Franca de Xira, Lisbon region·Portugal

Developer MERLIN Properties / Edged Energy

Under constructionStage source 28 Jul 2026
Published capacity80 MW ITPublished claim
Lisbon component of MERLIN’s Phase II IT development programme; excludes later VFX03–05 expansion.

Lisbon component of MERLIN’s Phase II IT development programme; excludes later VFX03–05 expansion.

7/10 evidence categories7 sources·2 team entries

MERLIN Zaragoza Wind data centre proposal

Botorrita, Zaragoza, Aragón·Spain

Developer MERLIN Properties

In planningStage source 28 Jul 2026
Published capacity144 MW ITPublished claim
Selected single-building development design; not built capacity.

Selected single-building development design; not built capacity.

227.4 MW unspecified · Authority-reported access-permit power
Aragón government power statement linked to María and Los Vientos substations. Original permits, import basis, holder, conditions and transferability not inspected; distinct from 144 MW IT.
Published claim

4/10 evidence categories2 sources·0 team entries

Kao Data Kenwood Point

Stockport, Greater Manchester·United Kingdom

Developer Kao Data

In planningStage source 1 Jul 2026
Published capacity40 MW unspecifiedPublished claim
Planned site capacity; 2024 approval announcement does not label the load basis.

Planned site capacity; 2024 approval announcement does not label the load basis.

4/10 evidence categories3 sources·2 team entries

atNorth SWE02 — Akalla

Akalla, Stockholm·Sweden

Developer atNorth

Under constructionStage source 29 Jun 2026
Published capacity30 MW unspecifiedPublished claim
Operator-announced SWE02 site-power headline; not published IT load, utility import limit or MVA.

Operator-announced SWE02 site-power headline; not published IT load, utility import limit or MVA.

Capacity source
8/10 evidence categories4 sources·2 team entries

DC North Varaždin

Varaždin·Croatia

Developer DC North d.o.o.; original investment by CRATIS and Muraplast

OperatingStage source 24 Jun 2026
Published capacity4 MW unspecifiedPublished claim
Operator describes 4 MW operational capacity in June 2026; the release does not distinguish contracted import, facility or IT load.

Operator describes 4 MW operational capacity in June 2026; the release does not distinguish contracted import, facility or IT load.

Capacity source
6/10 evidence categories6 sources·1 team entry

Red Admiral — Rochfortbridge campus

Rochfortbridge, Co. Westmeath·Ireland

Developer Red Admiral DC Limited / Lumcloon Energy

In planningStage source 23 Jun 2026
Published capacity250 MW facilityPublished claim
Full campus load scenario in June 2026 EIAR; not a contracted grid import or IT capacity. No independent connection-agreement verification.

Full campus load scenario in June 2026 EIAR; not a contracted grid import or IT capacity. No independent connection-agreement verification.

5/10 evidence categories8 sources·2 team entries

Aruba Hyper Cloud Data Center — IT4

Rome, Tecnopolo Tiburtino·Italy

Developer Aruba

OperatingStage source 19 Jun 2026
Published capacity30 MW ITPublished claim
Achievable campus total across five 6 MW buildings; operating amount not separately established.

Achievable campus total across five 6 MW buildings; operating amount not separately established.

6/10 evidence categories4 sources·0 team entries

Energia Huntstown data-centre campus

North Road, Finglas, Dublin 11·Ireland

Developer Energia Group / Huntstown Power Company Limited

Under constructionStage source 18 Jun 2026
Published capacity150 MW facilityPublished claim
Whole-development electricity demand assessed in the planning inspector’s report; not IT load, available capacity or an MVA connection offer. Adjacent generation is separate.

Whole-development electricity demand assessed in the planning inspector’s report; not IT load, available capacity or an MVA connection offer. Adjacent generation is separate.

2/10 evidence categories9 sources·10 team entries

Glesys Pori / The Rock

Ulvila / Pori, Kivipellontie·Finland

Developer Ficolo (original conversion); Glesys (current operator)

OperatingStage source 16 Jun 2026
Published capacity11 MW unspecifiedPublished claim
Operator-stated total site capacity; no explicit IT/import scope or available allocation.

Operator-stated total site capacity; no explicit IT/import scope or available allocation.

Capacity source
6/10 evidence categories4 sources·0 team entries

atNorth NOR01 Haugaland

Haugaland / Tysvær·Norway

Developer atNorth

In planningStage source 3 Jun 2026
Published capacity350 MW unspecifiedPublished claim
Announced ultimate campus target; initial phases are stated at 120 MW. Neither figure is presented here as secured MVA.

Announced ultimate campus target; initial phases are stated at 120 MW. Neither figure is presented here as secured MVA.

120 MW import · Network contribution agreement reported by business park
Haugaland Næringspark reports an executed anleggsbidragsavtale with Fagne for 120 MW network capacity. Contract conditions, utility confirmation and energisation remain unverified; this is not an additional campus phase to sum.
Published claim

5/10 evidence categories4 sources·0 team entries

Art Data Centres — Ennis campus

Tooreen / Cahernalough, Ennis, County Clare·Ireland

Developer Art Data Centres Limited

PermittedStage source 29 May 2026
Published capacity200 MW unspecifiedConflicting published claim
Planned six-hall campus. The June 2022 NTS describes 200 MW IT, but EIAR chapter 2 describes 200 MW total load and 27 MW IT per hall. The published definitions conflict; no verified operating or secured-import capacity is implied.

Planned six-hall campus. The June 2022 NTS describes 200 MW IT, but EIAR chapter 2 describes 200 MW total load and 27 MW IT per hall. The published definitions conflict; no verified operating or secured-import capacity is implied.

200 MW IT · NTS IT description — conflicts with chapter 2
June 2022 NTS printed page 23 (PDF page 36), proposed ultimate load; retained as a source-specific claim, not reconciled design capacity.
Conflicting published claim

200 MW facility · EIAR chapter 2 total load description
Chapter 2 printed page 5 (PDF page 19) describes 27 MW IT / circa 34 MW total per hall, and 200 MW total across six halls. Conflicts with NTS and chapter 13 IT description.
Conflicting published claim

83.5 MVA · Historical grid application
EIAR chapter 2 section 2.4.1 records an EirGrid application at Pre-planning Stage 1 in 2022. This is not an accepted connection offer or secured import right.
Historical application

Project capacity: Planned six-hall campus. The June 2022 NTS describes 200 MW IT, but EIAR chapter 2 describes 200 MW total load and 27 MW IT per hall. The published definitions conflict; no verified operating or secured-import capacity is implied.

NTS IT description — conflicts with chapter 2: June 2022 NTS printed page 23 (PDF page 36), proposed ultimate load; retained as a source-specific claim, not reconciled design capacity.

EIAR chapter 2 total load description: Chapter 2 printed page 5 (PDF page 19) describes 27 MW IT / circa 34 MW total per hall, and 200 MW total across six halls. Conflicts with NTS and chapter 13 IT description.

7/10 evidence categories15 sources·13 team entries

atNorth SWE04 Sollefteå

Hamre, Långsele / Sollefteå·Sweden

Developer atNorth

In planningStage source 28 May 2026
Published capacity300 MW unspecifiedPublished claim
Announced ultimate campus site-power target; not energised import capacity or IT MW.

Announced ultimate campus site-power target; not energised import capacity or IT MW.

Capacity source

200 MW import · Municipality-reported phase-one connection agreement
E.ON Energidistribution–atNorth connection agreement reported 28 May 2026, subject to new station/line permissions and delivery. Not operational power or additional to the 300 MW target.
Published claim

7/10 evidence categories4 sources·1 team entry

LuxConnect Bettembourg campus — DC1.1/DC1.2/DC1.3

Bettembourg·Luxembourg

Developer LuxConnect

OperatingStage source 26 May 2026
Published capacity6.3 MVAPublished equipment / supply-leg rating
Per leg of the operator’s published dual supply; not a building import entitlement or campus subtotal.

Per leg of the operator’s published dual supply; not a building import entitlement or campus subtotal.

Capacity source

6.3 MVA · DC1.2 supply leg (2 × 6.3 MVA published)
Per leg of the operator’s published dual supply; not a building import entitlement or campus subtotal.
Published equipment / supply-leg rating

10 MVA · DC1.3 supply leg (2 × 10 MVA published)
Per leg of the operator’s published dual supply; not a building import entitlement or campus subtotal.
Published equipment / supply-leg rating

6/10 evidence categories10 sources·7 team entries

Digital Realty BCN1

Sant Adrià de Besòs, Barcelona·Spain

Developer Digital Realty

OperatingStage source 18 May 2026
Published capacity14 MW unspecifiedPublished claim
Total planned BCN1 capacity in the opening announcement; IT versus utility basis and commissioned amount are not specified.

Total planned BCN1 capacity in the opening announcement; IT versus utility basis and commissioned amount are not specified.

15 MW IT · Historical lead-designer figure
B-Global BCN1 design load; the May 2026 opening release states 14 MW total planned capacity without its electrical basis. Scope difference remains unresolved; not additive.
Published claim

5/10 evidence categories4 sources·1 team entry

Kragujevac State Data Centre

Kragujevac·Serbia

Developer Government of Serbia / Office for IT and eGovernment

OperatingStage source 30 Apr 2026
Published capacity14 MW unspecifiedPublished claim
Total energy capacity stated in the 30 April 2026 government announcement; not identified as IT load or contracted import MVA.

Total energy capacity stated in the 30 April 2026 government announcement; not identified as IT load or contracted import MVA.

7/10 evidence categories4 sources·2 team entries

Delska EU North Riga LV DC1

Riga·Latvia

Developer Delska

OperatingStage source 15 Apr 2026
Published capacity10 MW unspecifiedPublished claim
Launch capacity stated by the operator; the release does not explicitly identify IT versus total-facility basis.

Launch capacity stated by the operator; the release does not explicitly identify IT versus total-facility basis.

5/10 evidence categories3 sources·6 team entries

Data4 Jawczyce — second building

Jawczyce, Ożarów Mazowiecki·Poland

Developer Data4

OperatingStage source 9 Apr 2026
Published capacity10 MW unspecifiedPublished claim
Second-building power capacity in the opening release; IT versus facility basis unstated.

Second-building power capacity in the opening release; IT versus facility basis unstated.

4/10 evidence categories2 sources·0 team entries

MERLIN Edged Bilbao-Arasur — BIL03 first building

Rivabellosa, Álava·Spain

Developer MERLIN Properties / Edged Energy

OperatingStage source 3 Apr 2026
Published capacity22 MW ITPublished claim
First facility critical capacity; excludes BIL01, BIL02 and further campus expansion.

First facility critical capacity; excludes BIL01, BIL02 and further campus expansion.

9/10 evidence categories6 sources·1 team entry

maincubes BER02 / mainHub — Nauen campus

Nauen, Berlin region·Germany

Developer maincubes

Under constructionStage source 24 Mar 2026
Published capacity200 MVAPublished claim
Campus substation; not converted into MW or treated as available IT load.

Campus substation; not converted into MW or treated as available IT load.

Capacity source

200 MW import · Announced contracted grid connection
Operator’s August 2025 signed E.DIS connection announcement; supply targeted from 2027. Separate from published 200 MVA substation/design figure; no conversion or energisation assumption.
Published claim

9/10 evidence categories7 sources·2 team entries

Polarise Amberg AI Factory — Wertachtal

Former Wertachtal transmitter, Amberg, Unterallgäu, Bavaria·Germany

Developer Polarise

Stage unconfirmedStage source 13 Mar 2026
Published capacity65 MW unspecifiedPublished claim
Polarise's updated initial campus plan announced on 18 August 2026. It is not verified IT load, utility import entitlement or commissioned capacity.

Polarise's updated initial campus plan announced on 18 August 2026. It is not verified IT load, utility import entitlement or commissioned capacity.

Capacity source

30 MW unspecified · Original initial plan (superseded)
Original 10 March 2026 promoter plan, superseded by the later 65 MW initial plan; not import or operating IT load.
Published claim

120 MW unspecified · Ultimate scalable plan
Promoter's potential ultimate scale inclusive of the initial phase; not additional capacity or secured import.
Published claim

5/10 evidence categories6 sources·1 team entry

Ark Longcross Park

Chertsey, Surrey·United Kingdom

Developer Ark Data Centres

OperatingStage source 16 Feb 2026
Published capacity16.8 MW unspecifiedPublished claim
Sweet Projects' phase-one case-study rating; MW basis is unspecified and not treated as IT power or utility import.

Sweet Projects' phase-one case-study rating; MW basis is unspecified and not treated as IT power or utility import.

Capacity source

54 MW unspecified · Two-centre consultant design scope
Stantec describes compute capacity across two centres; exact rating basis, current commissioned extent and utility import remain unverified.
Published claim

7/10 evidence categories7 sources·3 team entries

Data4 PAR03 — Nozay

Nozay, Essonne·France

Developer Data4

In planningStage source 15 Feb 2026
Published capacity250 MW importPublished claim
Proposed grid-connection demand in the MRAe opinion; not secured import or IT load. The opinion identifies excess connection capacity beyond this project’s needs.

Proposed grid-connection demand in the MRAe opinion; not secured import or IT load. The opinion identifies excess connection capacity beyond this project’s needs.

75 MW IT · DC01 planned IT
Planned building IT load; not live or secured import.
Published claim

37.5 MW IT · DC02 planned IT
Planned building IT load; not live or secured import.
Published claim

15 MW IT · DC03 planned IT
Planned building IT load; not live or secured import.
Published claim

8/10 evidence categories6 sources·4 team entries

Kevlinx BRU01

Neder-Over-Heembeek, Brussels·Belgium

Developer Kevlinx Data Centers

OperatingStage source 9 Jan 2026
Published capacity40 MVAPublished claim
BESIX-published facility rating for the phase1A/1B project. Operator separately distinguishes 16MW IT powered shell and 4MW fitted IT at launch; 40MVA is not spare capacity.

BESIX-published facility rating for the phase1A/1B project. Operator separately distinguishes 16MW IT powered shell and 4MW fitted IT at launch; 40MVA is not spare capacity.

Capacity source
8/10 evidence categories8 sources·4 team entries

AWS Cruiserath — buildings E, F and G

Cruiserath Road, Dublin 15·Ireland

Developer Amazon Web Services / Universal Developers LLC (planning applicant)

In planningStage source 19 Dec 2025
Published capacity240 MVAPublished claim
EirGrid letter of 27 May 2025 confirms the campus agreement with Amazon Data Services Ireland Limited, modified 14 February 2025. EirGrid expressly does not allocate supply to individual buildings. No spare capacity or third-party transferability established.

EirGrid letter of 27 May 2025 confirms the campus agreement with Amazon Data Services Ireland Limited, modified 14 February 2025. EirGrid expressly does not allocate supply to individual buildings. No spare capacity or third-party transferability established.

Capacity source
3/10 evidence categories10 sources·3 team entries

Digital Realty AMS11

Schiphol-Rijk, Amsterdam·Netherlands

Developer Digital Realty

OperatingStage source 20 Nov 2025
Published capacity27 MW ITPublished claim
Approximate full-facility four-phase design IT capacity; not all commissioned at the November 2025 opening or available to new customers.

Approximate full-facility four-phase design IT capacity; not all commissioned at the November 2025 opening or available to new customers.

6/10 evidence categories7 sources·3 team entries

Atman WAW-3 — first building

Duchnice, Warsaw region·Poland

Developer Atman

OperatingStage source 18 Sept 2025
Published capacity14.4 MW ITPublished claim
First operational WAW-3 building only; excludes later campus buildings.

First operational WAW-3 building only; excludes later campus buildings.

5/10 evidence categories4 sources·1 team entry

Kao Data KLON-03

Harlow·United Kingdom

Developer Kao Data

Under constructionStage source 18 Aug 2025
Published capacity17.6 MW ITPublished claim
KLON-03 planned hybrid-cooled IT capacity. Not secured utility MVA.

KLON-03 planned hybrid-cooled IT capacity. Not secured utility MVA.

8/10 evidence categories13 sources·4 team entries

Digital Realty ATH3

Koropi, Attica·Greece

Developer Digital Realty

OperatingStage source 12 Aug 2025
Published capacity8 MW ITPublished claim
ATH3 fully equipped IT design stated by ELEMKA; not metered load, contracted grid import, or proof that all IT capacity is occupied.

ATH3 fully equipped IT design stated by ELEMKA; not metered load, contracted grid import, or proof that all IT capacity is occupied.

6.8 MW unspecified · Historical annual-report design figure
The 2021 annual report, p. 103, describes a 2 February 2022 appointment and 6.8 MW without an IT/import basis, with phase one then expected in December 2022. Not additive to or a conversion of ELEMKA's later 8 MW IT fully equipped design.
Published claim

8/10 evidence categories9 sources·3 team entries

GreenScale Derry — RRY10 campus (formerly Atlantic Hub)

Foyle Port Innovation Park, Maydown, Derry·United Kingdom

Developer GreenScale

Under constructionStage source 7 Aug 2025
Published capacity100 MW importPublished claim
Campus grid connections reported as secured by GreenScale; not commissioned IT load. Proposed expansion to 300+ MW is separate.

Campus grid connections reported as secured by GreenScale; not commissioned IT load. Proposed expansion to 300+ MW is separate.

5/10 evidence categories8 sources·5 team entries

CyrusOne LON6 — Iver Heath Data Park

Iver Heath·United Kingdom

Developer CyrusOne

In planningStage source 20 Jun 2025
Published capacity108 MW ITPublished claim
Current undated operator LON6 specification; planned capacity, not live or available capacity. The 2025 announcement and architect design still describe 90 MW IT; the change is not reconciled.

Current undated operator LON6 specification; planned capacity, not live or available capacity. The 2025 announcement and architect design still describe 90 MW IT; the change is not reconciled.

90 MW IT · Earlier announced design
June 2025 LON6 announcement and architect design; retained alongside the current 108 MW operator claim.
Published claim

160 MVA · Published incoming supply
Operator-published 132 kV active/active supply design. No utility agreement or transferable import rights independently verified; redundant feeds are not summed.
Published claim

8/10 evidence categories7 sources·9 team entries

Data4 PAR01 — Marcoussis

Marcoussis / Nozay·France

Developer Data4

OperatingStage source 16 May 2025
Published capacity250 MW unspecifiedPublished claim
Campus-specific electrical/power capacity on operator page; not confirmed commissioned IT load.

Campus-specific electrical/power capacity on operator page; not confirmed commissioned IT load.

8/10 evidence categories10 sources·10 team entries

Nessus Data Center 3

Vienna·Austria

Developer Nessus GmbH

OperatingStage source 1 May 2025
Published capacity14 MW importPublished claim
Operator-stated 14 MW Anschlussleistung (connection power) for NDC3. Utility contract, allocated/energised amount and spare headroom are not disclosed; no MVA conversion.

Operator-stated 14 MW Anschlussleistung (connection power) for NDC3. Utility contract, allocated/energised amount and spare headroom are not disclosed; no MVA conversion.

6/10 evidence categories3 sources·0 team entries

Digital Realty HER1

Heraklion, Crete·Greece

Developer Digital Realty

OperatingStage source 9 Apr 2025
Published capacity6.5 MW ITPublished claim
Potential installed IT load at full growth in Hill's project brief; not a statement that 6.5 MW was commissioned at launch.

Potential installed IT load at full growth in Hill's project brief; not a statement that 6.5 MW was commissioned at launch.

10 MVA · Operator-stated power connection
HER1 factsheet connection rating; not verified transferable or available utility import and not converted to MW IT.
Published claim

1 MW unspecified · Pre-opening expectation
EXA's February 2025 initial expected facility capacity; basis unspecified and not evidence of commissioning. Not additive to Hill's 6.5 MW IT full-growth potential.
Published claim

7/10 evidence categories5 sources·2 team entries

SINES Data Campus — SIN01

Sines·Portugal

Developer Start Campus

OperatingStage source 4 Apr 2025
Published capacity33 MW ITPublished claim
Operational SIN01 figure in Jacobs' undated current case study. The inauguration release reported 26 MW; expansion/scope reconciliation remains required.

Operational SIN01 figure in Jacobs' undated current case study. The inauguration release reported 26 MW; expansion/scope reconciliation remains required.

26 MW unspecified · Inauguration figure
April 2025 inauguration release facility figure; electrical basis and reconciliation with Jacobs' current 33 MW IT are unresolved.
Published claim

15 MW IT · Original NEST screening design
Historical SIN01/NEST design recorded in APA's July 2023 opinion; not current operating capacity or an additive phase.
Published claim

10/10 evidence categories6 sources·6 team entries

VIRTUS LONDON2 — Hayes

Hayes, London·United Kingdom

Developer VIRTUS Data Centres

OperatingStage source 25 Apr 2024
Published capacity12.3 MW ITPublished claim
Current operator Hayes webpage rating. The specification PDF states 12.2 MW IT; the discrepancy is unresolved. Neither figure establishes spare capacity.

Current operator Hayes webpage rating. The specification PDF states 12.2 MW IT; the discrepancy is unresolved. Neither figure establishes spare capacity.

12.2 MW IT · Specification-sheet IT rating
LONDON2 PDF rating differs from the current webpage's 12.3 MW IT.
Published claim

20 MVA · Published incoming supply
Operator specification and September 2013 secured-supply announcement; not an independently inspected utility agreement or available expansion allocation.
Published claim

6/10 evidence categories6 sources·2 team entries

AWS Drogheda — Building A

Drogheda IDA Business and Technology Park, Donore Road, County Meath·Ireland

Developer Amazon Data Services Ireland Limited

OperatingStage source 15 Mar 2024
Published capacityNot published
2/10 evidence categories2 sources·0 team entries

Vantage CWL1 — Newport / Cardiff campus

Newport, Cardiff Capital Region, South Wales·United Kingdom

Developer Vantage Data Centers

OperatingStage source 31 Jan 2024
Published capacity148 MW ITPublished claim
Full-campus design rating in the operator specification, consistent with January 2026 campus MW disclosure. Not commissioned, spare or transferable import capacity.

Full-campus design rating in the operator specification, consistent with January 2026 campus MW disclosure. Not commissioned, spare or transferable import capacity.

5/10 evidence categories4 sources·0 team entries

Kao Data KLON-02

Harlow·United Kingdom

Developer Kao Data

OperatingStage source 28 Nov 2023
Published capacity10 MW ITPublished claim
KLON-02 expandable design/2023 opening headline. Operator described 8.8 MW base expandable to 10 MW; current undated campus page still lists 8.8 MW. Neither is spare capacity or utility import.

KLON-02 expandable design/2023 opening headline. Operator described 8.8 MW base expandable to 10 MW; current undated campus page still lists 8.8 MW. Neither is spare capacity or utility import.

8.8 MW IT · Current campus-page building rating
KLON-02 operating rating on undated Harlow page; the 2023 design explanation identifies expansion to 10 MW.
Published claim

7/10 evidence categories13 sources·4 team entries

Google Hanau campus

Hanau-Wolfgang·Germany

Developer Google; original development by NDC-GARBE, now GARBE.DC

OperatingStage source 6 Oct 2023
Published capacityNot published
6/10 evidence categories9 sources·1 team entry

Digital Realty FRA17

Frankfurt am Main·Germany

Developer Digital Realty

OperatingStage source 23 Jun 2023
Published capacity10.2 MW ITPublished claim
FRA17 design IT capacity across eight data halls; not a utility MVA figure or available headroom.

FRA17 design IT capacity across eight data halls; not a utility MVA figure or available headroom.

8/10 evidence categories5 sources·2 team entries

Data4 PAR02 — Marcoussis

Marcoussis·France

Developer Data4

OperatingStage source 19 May 2023
Published capacity5 MW unspecifiedPublished claim
Campus-specific electrical/power capacity on operator page; not confirmed commissioned IT load.

Campus-specific electrical/power capacity on operator page; not confirmed commissioned IT load.

5/10 evidence categories4 sources·0 team entries

AWS Drogheda — Building B

Drogheda IDA Business and Technology Park, Donore Road, County Meath·Ireland

Developer Tunis Properties LLC / Amazon Data Services Ireland Limited

In planningStage source 14 Apr 2022
Published capacity48 MW facilityPublished claim
Building B maximum electricity demand in the planning inspector’s report; not IT capacity, contracted import or availability.

Building B maximum electricity demand in the planning inspector’s report; not IT capacity, contracted import or availability.

2/10 evidence categories3 sources·1 team entry

Turkcell Avrupa Data Centre

Karaağaç OSB, Kapaklı, Tekirdağ (European Turkey)·Turkey

Developer Turkcell

OperatingStage source 13 Sept 2021
Published capacity13.6 MW unspecifiedPublished claim
SERBAN historical project total-power claim; IT versus utility/import scope and current capacity unverified

SERBAN historical project total-power claim; IT versus utility/import scope and current capacity unverified

Capacity source
3/10 evidence categories3 sources·1 team entry

Echelon DUB30 — Kish Business Park

Arklow, County Wicklow·Ireland

Developer Echelon Data Centres

PermittedStage source 10 Jun 2021
Published capacity90 MW ITPublished claim
Initial campus IT target stated by Echelon; not commissioned load or utility-import capacity.

Initial campus IT target stated by Echelon; not commissioned load or utility-import capacity.

3/10 evidence categories9 sources·1 team entry

Alcalá Data Center — ADC1 & ADC2

Alcalá de Henares, Madrid·Spain

Developer Nabiax

OperatingStage date not published
Published capacity22.3 MW ITPublished claim
Combined operating ADC1 and ADC2 capacity stated by Nabiax; not ADC3 or the potential full-campus expansion.

Combined operating ADC1 and ADC2 capacity stated by Nabiax; not ADC3 or the potential full-campus expansion.

35 MW IT · Unreconciled cooling-contractor campus figure
ENGIE's February 2026 cooling article uses 35 MW IT for the campus; it is not evidence that additional ADC1/ADC2 load is commissioned. Nabiax's phase-specific 22.3 MW remains the main figure.
Published claim

6/10 evidence categories5 sources·6 team entries

Arnes Data Centre Maribor

Maribor, Studenci·Slovenia

Developer Arnes — Academic and Research Network of Slovenia

OperatingStage date not published
Published capacity1.6 MW facilityPublished claim
Approximate gross reservation; not IT load or executed import rights.

Approximate gross reservation; not IT load or executed import rights.

Capacity source

6.3 MW facility · Future supercomputer reservation
Separate gross design reservation; not commissioned or added to Arnes capacity.
Published claim

10/10 evidence categories4 sources·6 team entries

Aruba Global Cloud Data Center — IT3

Ponte San Pietro, Bergamo·Italy

Developer Aruba

OperatingStage date not published
Published capacity45 MW ITPublished claim
Achievable full-campus IT power, not proof that all capacity is fitted out or occupied.

Achievable full-campus IT power, not proof that all capacity is fitted out or occupied.

10/10 evidence categories6 sources·1 team entry

AtlasEdge Lisbon campus — LIS001 and planned expansion

Carnaxide, Oeiras·Portugal

Developer AtlasEdge

OperatingStage date not published
Published capacity5.1 MW unspecifiedPublished claim
LIS001 power figure on the current operator page; IT versus utility basis is unstated. Excludes planned LIS002/LIS003 and does not establish spare supply.

LIS001 power figure on the current operator page; IT versus utility basis is unstated. Excludes planned LIS002/LIS003 and does not establish spare supply.

Capacity source

10 MVA · Operator-stated LIS001 power provision
Undated LIS001 factsheet total power provision. No executed utility agreement, rights holder or available transferable import verified; not a conversion of the separate 5.1 MW figure.
Published claim

7/10 evidence categories4 sources·3 team entries

atNorth DEN01 Copenhagen

Ballerup / Copenhagen·Denmark

Developer atNorth

OperatingStage date not published
Published capacity30 MW facilityPublished claim
Operator-advertised total campus power capacity; first-phase commissioned capacity is not separately disclosed.

Operator-advertised total campus power capacity; first-phase commissioned capacity is not separately disclosed.

8/10 evidence categories9 sources·4 team entries

atNorth FIN01 — Helsinki metro site

Helsinki·Finland

Developer atNorth

OperatingStage date not published
Published capacity1.6 MW unspecifiedPublished claim
Current operator headline power capacity; IT, facility-demand and contracted-import bases are not distinguished. No spare or transferable allocation established.

Current operator headline power capacity; IT, facility-demand and contracted-import bases are not distinguished. No spare or transferable allocation established.

Capacity source
4/10 evidence categories3 sources·1 team entry

atNorth FIN02 — Espoo

Sinimäki, Espoo·Finland

Developer atNorth

OperatingStage date not published
Published capacity45 MW importPublished claim
Power access agreed with Caruna Espoo Oy; separate from 40 MW campus headline, not unallocated headroom.

Power access agreed with Caruna Espoo Oy; separate from 40 MW campus headline, not unallocated headroom.

Capacity source

45 MW import · Operator-reported power-access agreement
Operator reports 45 MW access agreed with Caruna. Caruna says use of the expanded connection depends on additional transmission-grid capacity; current energised import and spare capacity are not established.
Published claim

45 MW facility · Skanska planned whole-facility gross capacity
Whole-facility gross capacity after expansion, as described by Skanska on 4 May 2026. Separate scope from agreed access; do not add these figures or infer IT MW.
Published claim

7/10 evidence categories7 sources·3 team entries

atNorth ICE01 — Reykjavik

Hafnarfjörður / Reykjavík metro·Iceland

Developer atNorth

OperatingStage date not published
Published capacity3.2 MW unspecifiedPublished claim
Current operator site-power headline; IT/import definition and demand rights are not stated.

Current operator site-power headline; IT/import definition and demand rights are not stated.

Capacity source
6/10 evidence categories5 sources·0 team entries

atNorth ICE02 — Keflavik

Keflavik·Iceland

Developer atNorth

OperatingStage date not published
Published capacity83 MW unspecifiedPublished claim
Operator-stated campus power capacity; IT/import basis and presently energised allocation are not specified.

Operator-stated campus power capacity; IT/import basis and presently energised allocation are not specified.

Capacity source
6/10 evidence categories5 sources·1 team entry

atNorth ICE03 Akureyri

Akureyri·Iceland

Developer atNorth

OperatingStage date not published
Published capacity50 MW facilityPublished claim
Operator-advertised campus power capacity. Energised and occupied phase breakdown is not disclosed.

Operator-advertised campus power capacity. Energised and occupied phase breakdown is not disclosed.

4/10 evidence categories6 sources·1 team entry

atNorth SWE01 Stockholm

Kista / Stockholm·Sweden

Developer atNorth

OperatingStage date not published
Published capacity12 MW facilityPublished claim
Operator-stated site power capacity for SWE01. IT capacity and utility MVA are not separately given.

Operator-stated site power capacity for SWE01. IT capacity and utility MVA are not separately given.

1.5 MW unspecified · Historical first phase opened March 2022
Veidekke’s dated opening report; not present total campus capacity.
Published claim

11 MW unspecified · Historical full-build design
Veidekke’s March 2022 three-phase design scope. Basis and reconciliation to current operator 12 MW facility figure remain unresolved.
Published claim

6/10 evidence categories5 sources·1 team entry

Beyond.pl Data Center 2

Poznań·Poland

Developer Beyond.pl

OperatingStage date not published
Published capacity42 MW ITPublished claim
DC2 target capacity, not verified current occupied or commissioned load.

DC2 target capacity, not verified current occupied or commissioned load.

Capacity source
5/10 evidence categories5 sources·2 team entries

CloudHQ CDG campus, Lisses

Lisses, Essonne·France

Developer CloudHQ

OperatingStage date not published
Published capacity150 MW ITPublished claim
Operator headline campus design capacity. The same page separately describes two buildings at 74.4 MW IT each; this numerical difference is unresolved. Not verified commissioned IT or contracted grid import.

Operator headline campus design capacity. The same page separately describes two buildings at 74.4 MW IT each; this numerical difference is unresolved. Not verified commissioned IT or contracted grid import.

Capacity source

74.4 MW IT · Per-building design claim
Operator states this separately for each of two buildings. Not summed, converted or reconciled with the 150 MW IT headline.
Published claim

7/10 evidence categories5 sources·2 team entries

CyrusOne DUB1 — Grange Castle campus

Clondalkin, Dublin·Ireland

Developer CyrusOne

OperatingStage date not published
Published capacity14 MW ITPublished claim
Current campus IT capacity explicitly reported by CyrusOne; excludes the larger masterplan and does not represent available capacity.

Current campus IT capacity explicitly reported by CyrusOne; excludes the larger masterplan and does not represent available capacity.

54 MW IT · Architectural masterplan
Hyphen describes the overall Dublin I campus masterplan; this is not the current operating total and must not be added to 14 MW.
Published claim

5/10 evidence categories5 sources·2 team entries

Data4 Athens — DC1

Paiania, Attica·Greece

Developer Data4

Under constructionStage date not published
Published capacity15 MW unspecifiedPublished claim
DC1 design capacity named by contractor and project manager; the sources do not expressly identify IT versus facility basis.

DC1 design capacity named by contractor and project manager; the sources do not expressly identify IT versus facility basis.

6/10 evidence categories7 sources·2 team entries

DATA4 MIL01 Cornaredo campus

Cornaredo / Settimo Milanese, Milan·Italy

Developer DATA4; DATA 4 MILAN S.P.A. is named as masterplan EIA proponent

OperatingStage date not published
Published capacity170 MW unspecifiedPublished claim
MIL01 campus specification on DATA4 Italy page. Basis, commissioned amount and contractual import are not published; excludes MIL02 and Italy-wide totals.

MIL01 campus specification on DATA4 Italy page. Basis, commissioned amount and contractual import are not published; excludes MIL02 and Italy-wide totals.

Capacity source
6/10 evidence categories5 sources·1 team entry

Delska EU North Vilnius LT DC1 — Data Inn

Vilnius·Lithuania

Developer Duomenų Logistikos Centras / Delska

OperatingStage date not published
Published capacity2 MW facilityPublished claim
Explicit facility power published by Delska; not IT load or spare capacity.

Explicit facility power published by Delska; not IT load or spare capacity.

4/10 evidence categories2 sources·1 team entry

Digital Realty MRS5

Marseille·France

Developer Digital Realty

Under constructionStage date not published
Published capacity22 MW unspecifiedPublished claim
Planned MRS5 facility power in construction supplier case study; load basis not stated there.

Planned MRS5 facility power in construction supplier case study; load basis not stated there.

5/10 evidence categories3 sources·10 team entries

Digital Realty Paris Digital Park

La Courneuve, Paris·France

Developer Digital Realty

OperatingStage date not published
Published capacity76 MW ITPublished claim
Combined PAR8, PAR9, PAR10 and PAR11 campus design IT capacity; no available-capacity or MVA inference.

Combined PAR8, PAR9, PAR10 and PAR11 campus design IT capacity; no available-capacity or MVA inference.

7/10 evidence categories9 sources·6 team entries

Equinix ML5

Settimo Milanese, Milan·Italy

Developer Equinix

OperatingStage date not published
Published capacity6 MW ITPublished claim
Full ML5 design capacity in Deerns' case study; first-phase commissioning described separately at 2 MW.

Full ML5 design capacity in Deerns' case study; first-phase commissioning described separately at 2 MW.

9/10 evidence categories9 sources·4 team entries

Green Campus ZRH1 — Lupfig

Lupfig, Aargau·Switzerland

Developer Green Datacenter AG

OperatingStage date not published
Published capacity12 MW ITPublished claim
Zurich West 4 only: operator’s 26 August 2024 output claim for customer systems. Not whole-campus capacity or utility import entitlement.

Zurich West 4 only: operator’s 26 August 2024 output claim for customer systems. Not whole-campus capacity or utility import entitlement.

Capacity source
7/10 evidence categories7 sources·2 team entries

Green Mountain OSL-Hamar

Hamar / Heggvin·Norway

Developer Green Mountain

OperatingStage date not published
Published capacity90 MW ITPublished claim
Three operating 30 MW buildings committed to TikTok. Ultimate 150 MW campus potential includes two planned buildings.

Three operating 30 MW buildings committed to TikTok. Ultimate 150 MW campus potential includes two planned buildings.

5/10 evidence categories5 sources·1 team entry

Green Mountain SVG-Rennesøy

Rennesøy, Stavanger region·Norway

Developer Green Mountain

OperatingStage date not published
Published capacity25 MW ITPublished claim
Maximum site IT capacity, not current customer availability.

Maximum site IT capacity, not current customer availability.

6/10 evidence categories3 sources·2 team entries

Green Mountain TEL-Rjukan

Rjukan, Telemark·Norway

Developer Green Mountain

OperatingStage date not published
Published capacity50 MW ITPublished claim
Maximum potential site IT capacity; not delivered or available load.

Maximum potential site IT capacity; not delivered or available load.

Capacity source
7/10 evidence categories8 sources·3 team entries

JCD EPark — DC1

Little Island, Cork·Ireland

Developer JCD Group

Under constructionStage date not published
Published capacity12 MW importPublished claim
DC1 electrical grid capacity reported as secured by JCD; energisation and IT capacity unverified. No MVA conversion.

DC1 electrical grid capacity reported as secured by JCD; energisation and IT capacity unverified. No MVA conversion.

Capacity source
3/10 evidence categories5 sources·3 team entries

JCD EPark — DC2

Little Island, Cork·Ireland

Developer JCD Group

In planningStage date not published
Published capacity10 MW importPublished claim
DC2 grid capacity stated by JCD; energisation and offer terms not independently verified. Not IT MW or MVA.

DC2 grid capacity stated by JCD; energisation and offer terms not independently verified. Not IT MW or MVA.

Capacity source
4/10 evidence categories3 sources·0 team entries

JCD EPark — DC3

Little Island, Cork·Ireland

Developer JCD Group

In planningStage date not published
Published capacity60 MW importConnection pending
Proposed DC3 grid connection — PENDING, not secured or energised capacity.

Proposed DC3 grid connection — PENDING, not secured or energised capacity.

Capacity source
4/10 evidence categories3 sources·0 team entries

LuxConnect DC2

Bissen·Luxembourg

Developer LuxConnect

OperatingStage date not published
Published capacity12.6 MVAPublished equipment / supply-leg rating
Per published supply leg: operator lists 2 × 12.6 MVA with redundant infrastructure. No 25.2 MVA firm-import total, IT equivalence or spare headroom is inferred.

Per published supply leg: operator lists 2 × 12.6 MVA with redundant infrastructure. No 25.2 MVA firm-import total, IT equivalence or spare headroom is inferred.

Capacity source
5/10 evidence categories5 sources·4 team entries

maincubes BER01 — Go West campus

Berlin·Germany

Developer maincubes

OperatingStage date not published
Published capacity9 MW ITPublished claim
BER01 facility, current operator claim; not utility import entitlement. Earlier design source stated 8.2 MW IT.

BER01 facility, current operator claim; not utility import entitlement. Earlier design source stated 8.2 MW IT.

Capacity source

8.2 MW IT · Earlier design claim
BER01 design reported by project manager in November 2023; current operator page states 9 MW IT. Reconciliation of the design change is not published.
Published claim

6/10 evidence categories8 sources·3 team entries

maincubes FRA03 — Schwalbach

Schwalbach am Taunus, Frankfurt region·Germany

Developer maincubes

OperatingStage date not published
Published capacity16 MW ITPublished claim
Overall FRA03 facility; phase 1 operating, phase 2 scheduled for 2026/27.

Overall FRA03 facility; phase 1 operating, phase 2 scheduled for 2026/27.

5/10 evidence categories3 sources·3 team entries

maincubes FRA04 — Dietzenbach

Dietzenbach, Frankfurt region·Germany

Developer maincubes

In planningStage date not published
Published capacity40 MW ITPublished claim
Proposed full FRA04 development; capacity depends on design.

Proposed full FRA04 development; capacity depends on design.

60 MW import · Acquisition-stage committed power
Operator-stated committed electrical supply when the site was acquired in January 2024; contract details, current energisation and available headroom unverified. Distinct from 40 MW IT design.
Published claim

7/10 evidence categories5 sources·0 team entries

NorthC Aalsmeer

Aalsmeer·Netherlands

Developer NorthC Datacenters

OperatingStage date not published
Published capacity14 MW unspecifiedPublished claim
Published installed electrical capacity; not explicitly an IT-load figure.

Published installed electrical capacity; not explicitly an IT-load figure.

6/10 evidence categories8 sources·3 team entries

NorthC Amsterdam 2 — former Colt

Amsterdam Zuidoost·Netherlands

Developer NorthC Datacenters

OperatingStage date not published
Published capacity3.44 MW unspecifiedPublished claim
Published installed electrical capacity; the proposed 3.8 MW upgrade is separate.

Published installed electrical capacity; the proposed 3.8 MW upgrade is separate.

3/10 evidence categories2 sources·0 team entries

NorthC Eindhoven 2 — High Tech Gateway

Eindhoven·Netherlands

Developer NorthC Datacenters

OperatingStage date not published
Published capacity4.5 MW unspecifiedPublished claim
Operator-published installed electrical capacity, not expressly IT load.

Operator-published installed electrical capacity, not expressly IT load.

8/10 evidence categories5 sources·1 team entry

NXDATA-3 / BUH3

Tunari, Ilfov·Romania

Developer NXDATA

Under constructionStage date not published
Published capacity3 MW ITPublished claim
Proposed total IT capacity; 5 MW total electrical capacity is separate.

Proposed total IT capacity; 5 MW total electrical capacity is separate.

Capacity source

5 MW facility · Total electrical design capacity
NXDATA-3 operator design claim; separate from 3 MW IT and not evidence of energised import rights.
Published claim

6/10 evidence categories3 sources·0 team entries

SINES Data Campus — SIN02

Sines·Portugal

Developer Start Campus

Under constructionStage date not published
Published capacity180 MW ITPublished claim
SIN02 design figure stated by Start Campus in May 2025 and by Gleeds on its current phase-specific project page. It is not an import entitlement or disclosed leased load.

SIN02 design figure stated by Start Campus in May 2025 and by Gleeds on its current phase-specific project page. It is not an import entitlement or disclosed leased load.

200 MW unspecified · Current investment and programme figure
Second-building figure in the May 2026 Nscale and Start Campus releases. The electrical basis is not stated and it is not disclosed leased load.
Published claim

120 MW IT · Historical AIA design
Per-building maximum for SIN02–SIN06 assessed in APA's 2023 environmental process; not current capacity or an import right.
Published claim

240 MW IT · Historical developer upper scope
August 2024 Start Campus description of each SIN02–SIN06 building as up to 240 MW IT. Later phase-specific sources state 180 MW IT and 200 MW unspecified; the scopes remain unresolved and are not additive.
Published claim

10/10 evidence categories15 sources·4 team entries

Vantage DUB1 — DUB11 and DUB12

Profile Park, Grange Castle, Dublin·Ireland

Developer Vantage Data Centers

Under constructionStage date not published
Published capacity52 MW ITPublished claim
Combined design capacity of the first two buildings (32MW + 20MW). Excludes DUB13 and is not commissioned load or utility import.

Combined design capacity of the first two buildings (32MW + 20MW). Excludes DUB13 and is not commissioned load or utility import.

2/10 evidence categories10 sources·7 team entries

VIRTUS Stockley Park campus

Stockley Park, London·United Kingdom

Developer VIRTUS Data Centres

OperatingStage date not published
Published capacity112.5 MW ITPublished claim
Operator-published total campus IT load; not a statement of spare or occupied capacity.

Operator-published total campus IT load; not a statement of spare or occupied capacity.

27 MW IT · LONDON7 contractor design rating
Equans' LONDON7 design-and-build case study; historical phase-specific rating, not added to campus total.
Published claim

32.5 MW IT · LONDON7 current marketed rating
Current campus webpage's LONDON7 rating differs from Equans' 27 MW design scope; upgrade history not verified and not added to campus total.
Published claim

8/10 evidence categories6 sources·1 team entry
Project intelligence. Capacity claims do not establish available land or spare power.Suggest a project