Recorded research reviews across data centres and land.

Demand & infrastructure signals
234 matching entries

A review is a research check, not a new project announcement. Open a record for its source evidence.

Teltonika High-Tech Hill — AI data centreStage unconfirmed

Vilnius, Lithuania

Authority evidence preserves a later-phase AI data-centre intention within Teltonika's Vilnius technology-park programme. A 2023 concept placed it at Svylos g. 12, but the municipality now records a manufacturing project on that parcel; the current data-centre red line is therefore unresolved. The delivered 58 MW connection is for the technology park as a whole, not a data-centre allocation, and the two 63 MVA transformers are equipment ratings rather than additive import rights.

Review context

Authority evidence preserves a later-phase AI data-centre intention within Teltonika's Vilnius technology-park programme. A 2023 concept placed it at Svylos g. 12, but the municipality now records a manufacturing project on that parcel; the current data-centre red line is therefore unresolved. The delivered 58 MW connection is for the technology park as a whole, not a data-centre allocation, and the two 63 MVA transformers are equipment ratings rather than additive import rights.

Latest dated source: 16 Sept 2026. This is a source publication date, not the review or construction date.

Open full evidence
Thames Valley Park Data CentreIn planning

Earley, Reading, United Kingdom

A 5.3–5.4 ha office-campus redevelopment in outline planning for about 37,000 sqm and 72 MW IT. Microsoft is the departing office tenant, not the proposed operator. The project exposes a major delivery constraint: only 1.8 MW existing supply is described, proposed gas fuel cells would bridge the first phase, and the reported 60 MVA grid connection depends on reinforcement targeted from 2037 and remains below the 110 MW peak-facility scope.

Review context

A 5.3–5.4 ha office-campus redevelopment in outline planning for about 37,000 sqm and 72 MW IT. Microsoft is the departing office tenant, not the proposed operator. The project exposes a major delivery constraint: only 1.8 MW existing supply is described, proposed gas fuel cells would bridge the first phase, and the reported 60 MVA grid connection depends on reinforcement targeted from 2037 and remains below the 110 MW peak-facility scope.

Latest dated source: 3 Oct 2026. This is a source publication date, not the review or construction date.

Open full evidence
SINES Data Campus — SIN02Under construction

Sines, Portugal

SIN02 is now separately evidenced as under construction. Current phase-specific sources state 180 MW IT, while the May 2026 investment and programme releases call it a 200 MW building without stating the electrical basis. APA assessed a historical 120 MW IT per-building design in 2023, and Start Campus described a 240 MW IT upper phase scope in August 2024; these figures are conflicting/superseded scopes, not additive capacity. The environmental decisions remain conditional, and planned 400/150 kV infrastructure is not proof of an energised SIN02 import right.

Review context

SIN02 is now separately evidenced as under construction. Current phase-specific sources state 180 MW IT, while the May 2026 investment and programme releases call it a 200 MW building without stating the electrical basis. APA assessed a historical 120 MW IT per-building design in 2023, and Start Campus described a 240 MW IT upper phase scope in August 2024; these figures are conflicting/superseded scopes, not additive capacity. The environmental decisions remain conditional, and planned 400/150 kV infrastructure is not proof of an energised SIN02 import right.

Latest dated source: 12 May 2026. This is a source publication date, not the review or construction date.

Open full evidence
Polarise Amberg AI Factory — WertachtalStage unconfirmed

Former Wertachtal transmitter, Amberg, Unterallgäu, Bavaria, Germany

Bounded, developer-led reuse proposal at the former Wertachtal transmitter. Public evidence supports a pre-planning concept and historical consortium control of the broader conversion area, but not a completed Polarise acquisition, exact parcel title, planning application, grid import right, physical fibre route or named customer. The 69.5/70 MWp solar park, planned wind and BESS are generation/storage context and do not establish continuous data-centre import. This is market intelligence, not off-market land.

Review context

Bounded, developer-led reuse proposal at the former Wertachtal transmitter. Public evidence supports a pre-planning concept and historical consortium control of the broader conversion area, but not a completed Polarise acquisition, exact parcel title, planning application, grid import right, physical fibre route or named customer. The 69.5/70 MWp solar park, planned wind and BESS are generation/storage context and do not establish continuous data-centre import. This is market intelligence, not off-market land.

Latest dated source: 18 Aug 2026. This is a source publication date, not the review or construction date.

Open full evidence
Google Grange Castle — DC3 expansionPermitted

Grange Castle Business Park South / Profile Park, Baldonnell, Dublin 22, Ireland

Consented DC3 expansion; operating DC1/DC2 retain their separate record. Condition 3 restricts separate use or transfer without further permission. Condition 5 addresses renewable-energy CPPAs before operation; permission does not establish commissioned or available import capacity.

Review context

Consented DC3 expansion; operating DC1/DC2 retain their separate record. Condition 3 restricts separate use or transfer without further permission. Condition 5 addresses renewable-energy CPPAs before operation; permission does not establish commissioned or available import capacity.

Latest dated source: 23 Sept 2026. This is a source publication date, not the review or construction date.

Open full evidence
Nebius Pajarila — Lappeenranta campusUnder construction

Kettukuja, Pajarila, Lappeenranta, South Karelia, Finland

Nebius-owned project on city land leased to Polarnode. The utility identifies Mälkiä for the initial connection and Yllikkälä–Simolantie reinforcement for expansion. Signed import terms, permit conditions, physical fibre routes and named compute customers remain unresolved. This developer-controlled campus is market intelligence, not available off-market land.

Review context

Nebius-owned project on city land leased to Polarnode. The utility identifies Mälkiä for the initial connection and Yllikkälä–Simolantie reinforcement for expansion. Signed import terms, permit conditions, physical fibre routes and named compute customers remain unresolved. This developer-controlled campus is market intelligence, not available off-market land.

Latest dated source: 11 Aug 2026. This is a source publication date, not the review or construction date.

Open full evidence
IDA Oakfield Business and Technology ParkWatching

Oakfield, south-west of Sligo town; Phase 2 enabling-works application area 4.59 ha, within a wider historical 77-acre ground-investigation scope, Ireland

Newly structured bounded land record from older authority evidence, not a new project announcement. Sligo County Council granted conditional permission for Phase 2 access and utility works under 25/60014 on 17 February 2026 after its 15 January decision. IDA then re-tendered the works on 23 July after the first procurement ended without a winner. This establishes an active industrial-land preparation programme, not a data-centre consent or construction start.

Review context

Newly structured bounded land record from older authority evidence, not a new project announcement. Sligo County Council granted conditional permission for Phase 2 access and utility works under 25/60014 on 17 February 2026 after its 15 January decision. IDA then re-tendered the works on 23 July after the first procurement ended without a winner. This establishes an active industrial-land preparation programme, not a data-centre consent or construction start.

Next check: Retrieve the full 25/60014 grant and conditions, the NIS mitigation schedule, current Phase 2 drawings and the 2024 ground-investigation results. Reconcile those boundaries with current title, IDA allocation/marketing terms and adopted zoning. After that, request evidence of a plot-specific ESB Networks demand route and carrier entries; do not infer capacity from Srananagh or the MAN. Monitor eTenders resource 8706179 after its indicated late-October award fields. No contact made.

Open full evidence
AWS / BnM Eco Energy Park proposalIn planning

Derrygreenagh group, Irish Midlands, Ireland

Proposed AWS development within BnM’s Midlands energy park. The separately consented generation scheme includes 220 kV and 400 kV substations. This strengthens the infrastructure trail but establishes no AWS import allocation. The wider approximately 3,000 ha landbank is not the AWS campus footprint; generation, storage and PPA figures are not site import capacity.

Review context

Proposed AWS development within BnM’s Midlands energy park. The separately consented generation scheme includes 220 kV and 400 kV substations. This strengthens the infrastructure trail but establishes no AWS import allocation. The wider approximately 3,000 ha landbank is not the AWS campus footprint; generation, storage and PPA figures are not site import capacity.

Latest dated source: 28 Apr 2026. This is a source publication date, not the review or construction date.

Open full evidence
IDA Belview — Kilmurry and Gorteens landbankWatching

Kilmurry and Gorteens, north of IDA Science and Technology Business Park, Belview / Slieverue, South Kilkenny, Ireland

Weekly authority recheck of the existing landbank lead: the live ACP file still shows only the 18 June 2026 lodgement and no decision. The application contains an NIS, flood assessment, access/service drawings and statutory ecology objections. This is enabling-infrastructure evidence, not an announced data centre or land release.

Review context

Weekly authority recheck of the existing landbank lead: the live ACP file still shows only the 18 June 2026 lodgement and no decision. The application contains an NIS, flood assessment, access/service drawings and statutory ecology objections. This is enabling-infrastructure evidence, not an announced data centre or land release.

Next check: Monitor ACP-324383-26 for the Commission's decision and any further ecology material. Confirm whether the requested otter, bat-roost and lighting assessments were completed and accepted. Retrieve an executed access/right-of-way instrument, current title/allocation terms and a current Uisce Éireann agreement. Then match parcel boundaries to zoning, power and carrier entries. Review CfT 8646533 only after retrieving current status; no award is claimed. No contact made.

Open full evidence
Red Admiral — Rochfortbridge campusIn planning

Rochfortbridge, Co. Westmeath, Ireland

Six data-centre buildings in a 39 ha campus within a wider 243 ha application. The form identifies Castlelost Flex Gen Limited and acquisition options on adjoining land; freehold ownership of the complete campus is unverified. Proposed local generation/storage and proximity to Castlelost 220 kV do not establish contracted import capacity. The applicant’s June 2026 EIAR proposes fresh-air cooling with electric and absorption chillers in hot conditions, and a 40 m³/day maximum water-demand envelope. These are design assumptions, not verified utility or abstraction entitlements.

Review context

Six data-centre buildings in a 39 ha campus within a wider 243 ha application. The form identifies Castlelost Flex Gen Limited and acquisition options on adjoining land; freehold ownership of the complete campus is unverified. Proposed local generation/storage and proximity to Castlelost 220 kV do not establish contracted import capacity. The applicant’s June 2026 EIAR proposes fresh-air cooling with electric and absorption chillers in hot conditions, and a 40 m³/day maximum water-demand envelope. These are design assumptions, not verified utility or abstraction entitlements.

Latest dated source: 18 Sept 2026. This is a source publication date, not the review or construction date.

Open full evidence
Vantage CWL1 — Newport / Cardiff campusOperating

Newport, Cardiff Capital Region, South Wales, United Kingdom

Established CWL1 campus, with CWL11/CWL13 consolidated under one identity. Vantage announced a Nebius high-density AI lease on 13 August 2026; its MW, building and commissioning date were not disclosed. The existing campus design rating must not be treated as the Nebius lease allocation or available capacity. Current title and construction appointments remain unverified.

Review context

Established CWL1 campus, with CWL11/CWL13 consolidated under one identity. Vantage announced a Nebius high-density AI lease on 13 August 2026; its MW, building and commissioning date were not disclosed. The existing campus design rating must not be treated as the Nebius lease allocation or available capacity. Current title and construction appointments remain unverified.

Latest dated source: 13 Aug 2026. This is a source publication date, not the review or construction date.

Open full evidence
IDA Quignashee — Sligo Road industrial holdingWatching

Quignashee, Sligo Road / N59, Ballina, County Mayo; named IDA holding, current title boundary unverified, Ireland

Newly researched enabling-infrastructure evidence for a specific industrial holding. IDA's eTenders workspace records Ballina road-infrastructure design services published on 11 February 2026 and an award entry on 30 June 2026 for €185,815. Western People's 24 April 2026 report connects the current access/masterplanning initiative to the Sligo Road holding. The primary procurement page names Ballina, so the exact works boundary still needs reconciliation. This is industrial-land preparation, not a data-centre appointment or construction start.

Review context

Newly researched enabling-infrastructure evidence for a specific industrial holding. IDA's eTenders workspace records Ballina road-infrastructure design services published on 11 February 2026 and an award entry on 30 June 2026 for €185,815. Western People's 24 April 2026 report connects the current access/masterplanning initiative to the Sligo Road holding. The primary procurement page names Ballina, so the exact works boundary still needs reconciliation. This is industrial-land preparation, not a data-centre appointment or construction start.

Next check: Obtain the boundary drawings and current planning package behind eTenders CfT 7487743 / TED 452399-2026; match them to Quignashee title and distinguish it from the existing Bunree industrial estate. Establish the current IDA allocation/marketing position and N59/TII access resolution. Then obtain parcel-specific import and fibre-route evidence before considering capacity, score or qualification. No contact made.

Open full evidence
Mullinabro lands — Ballagh HoldingsWatching

Mullinabro, Ferrybank / South Kilkenny, northern edge of Waterford urban area, Ireland

Owner-led land and zoning signal. Kilkenny’s December 2025 report records Ballagh Holdings’ Mullinabro masterplan and data-centre utility assessments (KK-C330-65). Variation 6 was adopted on 23 March 2026. This lead was identified following a user tip, then corroborated with public records.

Review context

Owner-led land and zoning signal. Kilkenny’s December 2025 report records Ballagh Holdings’ Mullinabro masterplan and data-centre utility assessments (KK-C330-65). Variation 6 was adopted on 23 March 2026. This lead was identified following a user tip, then corroborated with public records.

Next check: Match consultant-cited folios KK11641 and KK37926F to current title, the adopted zoning and campus boundary. Establish Ballagh’s exact legal identity and Echelon relationship, then obtain current operator feasibility and application evidence before assigning MVA or preparing controlling terms. Check the separate Great Island–Belview development permission and delivery status; maritime consent alone does not authorise construction. No contact or purchase has been made.

Open full evidence
atNorth DEN01 CopenhagenOperating

Ballerup / Copenhagen, Denmark

Brownfield redevelopment at Tonsbakken 12–14 with GPP architectural attribution and a final backup-power environmental approval. Vestforbrænding confirms a heat agreement with 2028 infrastructure readiness targeted.

Review context

Brownfield redevelopment at Tonsbakken 12–14 with GPP architectural attribution and a final backup-power environmental approval. Vestforbrænding confirms a heat agreement with 2028 infrastructure readiness targeted.

Latest dated source: 17 Mar 2026. This is a source publication date, not the review or construction date.

Open full evidence
atNorth DEN02 — Ølgod / VardeIn planning

Ølgod, Varde, Denmark

Planned Ølgod campus. Varde’s published package contains proposed zoning and draft environmental/water permissions; final adoption was not verified. The authority’s 174 ha combined scheme and operator’s 171 ha campus are distinct reported boundaries.

Review context

Planned Ølgod campus. Varde’s published package contains proposed zoning and draft environmental/water permissions; final adoption was not verified. The authority’s 174 ha combined scheme and operator’s 171 ha campus are distinct reported boundaries.

Latest dated source: 11 Aug 2026. This is a source publication date, not the review or construction date.

Open full evidence
atNorth FIN02 — EspooOperating

Sinimäki, Espoo, Finland

Operating Espoo campus with an 11,200 m² Skanska expansion under construction. Caruna confirms connection reinforcement is conditional on transmission-grid capacity; Kesko heat recovery has operated since November 2025.

Review context

Operating Espoo campus with an 11,200 m² Skanska expansion under construction. Caruna confirms connection reinforcement is conditional on transmission-grid capacity; Kesko heat recovery has operated since November 2025.

Latest dated source: 4 May 2026. This is a source publication date, not the review or construction date.

Open full evidence
ClusterPower Technology Campus — first phaseOperating

Mischii, Craiova, Romania

Operating Romanian AI and colocation campus. Public 200 MW and later larger figures refer to maximum development/energy ambitions and are not treated as installed first-phase capacity.

Review context

Operating Romanian AI and colocation campus. Public 200 MW and later larger figures refer to maximum development/energy ambitions and are not treated as installed first-phase capacity.

Latest dated source: 16 Mar 2023. This is a source publication date, not the review or construction date.

Open full evidence
CRA Prague Gateway DCUnder construction

Jíloviště, Prague region, Czechia

CRA construction project with documented optical partners and an AI-cloud reservation LOI. Issuer power scopes are differentiated; utility import rights and delivery targets remain unverified.

Review context

CRA construction project with documented optical partners and an AI-cloud reservation LOI. Issuer power scopes are differentiated; utility import rights and delivery targets remain unverified.

Latest dated source: 14 Sept 2026. This is a source publication date, not the review or construction date.

Open full evidence
CyrusOne DUB1 — Grange Castle campusOperating

Clondalkin, Dublin, Ireland

The current operator page reports 14 MW of IT capacity and future expansion dependent on pipeline. It describes carrier neutrality, diverse fibre connectivity and active A/B meet-me rooms. The larger architectural masterplan is separate from current reported capacity.

Review context

The current operator page reports 14 MW of IT capacity and future expansion dependent on pipeline. It describes carrier neutrality, diverse fibre connectivity and active A/B meet-me rooms. The larger architectural masterplan is separate from current reported capacity.

Latest dated source: 26 May 2026. This is a source publication date, not the review or construction date.

Open full evidence
Data4 Athens — DC1Under construction

Paiania, Attica, Greece

First building at Data4’s Athens campus. The operator’s 90 MW electricity reserve is a separate campus metric.

Review context

First building at Data4’s Athens campus. The operator’s 90 MW electricity reserve is a separate campus metric.

Latest dated source: 2 Mar 2026. This is a source publication date, not the review or construction date.

Open full evidence
DataVita DV1 — FortisOperating

Chapelhall, North Lanarkshire, United Kingdom

Purpose-built facility opened in 2016. Current specifications contain conflicting 24 MW and 40 MW figures, so no single headline capacity is asserted.

Review context

Purpose-built facility opened in 2016. Current specifications contain conflicting 24 MW and 40 MW figures, so no single headline capacity is asserted.

Latest dated source: 16 Sept 2026. This is a source publication date, not the review or construction date.

Open full evidence
Digital Realty AMS15Operating

Hoofddorp, Netherlands

Operating De President facility with distinct original-design and later-delivery evidence. Operator-stated ownership remains subject to title verification.

Review context

Operating De President facility with distinct original-design and later-delivery evidence. Operator-stated ownership remains subject to title verification.

Latest dated source: 23 Nov 2020. This is a source publication date, not the review or construction date.

Open full evidence
Digital Realty ATH3Operating

Koropi, Attica, Greece

Operating Koropi facility with 8 MW IT fully equipped design evidence and phase-specific construction records. The operator's current N+2 cooling field conflicts with the campus factsheet's N+1 description.

Review context

Operating Koropi facility with 8 MW IT fully equipped design evidence and phase-specific construction records. The operator's current N+2 cooling field conflicts with the campus factsheet's N+1 description.

Latest dated source: 12 Aug 2025. This is a source publication date, not the review or construction date.

Open full evidence
Digital Realty Paris Digital ParkOperating

La Courneuve, Paris, France

Four-building PAR8–PAR11 campus with completed construction and current operating evidence. Team appointments distinguish PAR8 envelope/ground studies from PAR10/PAR11 fire protection.

Review context

Four-building PAR8–PAR11 campus with completed construction and current operating evidence. Team appointments distinguish PAR8 envelope/ground studies from PAR10/PAR11 fire protection.

Latest dated source: 15 May 2026. This is a source publication date, not the review or construction date.

Open full evidence
Digital Realty VIE1Operating

Vienna, Austria

Operating Building 1 at Louis-Häfliger-Gasse 10, with 10,700 m² total building area. VIX confirms an exchange presence at the shared campus; Wien Energie confirms campus heat recovery serving Klinik Floridsdorf since winter 2023/24. Neither source allocates these systems between VIE1 and VIE2. Import capacity is not published.

Review context

Operating Building 1 at Louis-Häfliger-Gasse 10, with 10,700 m² total building area. VIX confirms an exchange presence at the shared campus; Wien Energie confirms campus heat recovery serving Klinik Floridsdorf since winter 2023/24. Neither source allocates these systems between VIE1 and VIE2. Import capacity is not published.

Latest dated source: 31 Jan 2024. This is a source publication date, not the review or construction date.

Open full evidence
Digital Realty VIE2Operating

Vienna, Austria

Operating Building 2 at Louis-Häfliger-Gasse 10, with 20,400 m² total building area. VIX confirms an exchange presence at the shared campus; Wien Energie confirms campus heat recovery serving Klinik Floridsdorf since winter 2023/24. Neither source allocates these systems between VIE1 and VIE2. Import capacity is not published.

Review context

Operating Building 2 at Louis-Häfliger-Gasse 10, with 20,400 m² total building area. VIX confirms an exchange presence at the shared campus; Wien Energie confirms campus heat recovery serving Klinik Floridsdorf since winter 2023/24. Neither source allocates these systems between VIE1 and VIE2. Import capacity is not published.

Latest dated source: 31 Jan 2024. This is a source publication date, not the review or construction date.

Open full evidence
Equinix ML5Operating

Settimo Milanese, Milan, Italy

Operating Settimo Milanese facility with a dated MIX activation milestone and phase-specific ML5.1 contractor/design evidence. Full 6 MW IT design remains distinct from the consultant's 2 MW initial phase and grid import.

Review context

Operating Settimo Milanese facility with a dated MIX activation milestone and phase-specific ML5.1 contractor/design evidence. Full 6 MW IT design remains distinct from the consultant's 2 MW initial phase and grid import.

Latest dated source: Publication date not recorded. This is a source publication date, not the review or construction date.

Open full evidence
Equinix MU4.3 expansionUnder construction

Aschheim / Munich, Germany

Live-campus phase 3 expansion at Dywidagstrasse 10. Equinix’s February 2026 filing lists 1,375 planned sellable cabinets; no phase-specific MW or import allocation is published in the reviewed sources.

Review context

Live-campus phase 3 expansion at Dywidagstrasse 10. Equinix’s February 2026 filing lists 1,375 planned sellable cabinets; no phase-specific MW or import allocation is published in the reviewed sources.

Latest dated source: 16 Jul 2026. This is a source publication date, not the review or construction date.

Open full evidence
Former Goodyear Fulda worksWatching

Künzeller Straße, Fulda, Germany

A 25 September 2026 transaction-counsel announcement identifies Goodyear Germany's former production-site sale to the City of Fulda. The source was retrieved through its search index; direct access returned 403. This is a municipal-control signal, not a DC launch or available campus.

Review context

A 25 September 2026 transaction-counsel announcement identifies Goodyear Germany's former production-site sale to the City of Fulda. The source was retrieved through its search index; direct access returned 403. This is a municipal-control signal, not a DC launch or available campus.

Next check: Review the city's completed acquisition perimeter, title-holding entity and subsequent development/disposal resolutions. Obtain public site-condition/remediation evidence and distinguish the historical broker process from any current municipal release. Establish whether demand rights survived closure and the requirements of OsthessenNetz for a new continuous load. Do not promote the pre-emption area as a released campus parcel.

Open full evidence
Green Campus ZRH1 — LupfigOperating

Lupfig, Aargau, Switzerland

Three operating buildings and building 4 under construction remain one campus record. The fourth building carries a historical 12 MW IT claim, 5,526 m² data-centre area and an Implenia shell-and-core appointment. Current operator target is early 2027, later than the 2026 date in earlier releases; IBB corroborates electricity-connection design and the heat-recovery pathway.

Review context

Three operating buildings and building 4 under construction remain one campus record. The fourth building carries a historical 12 MW IT claim, 5,526 m² data-centre area and an Implenia shell-and-core appointment. Current operator target is early 2027, later than the 2026 date in earlier releases; IBB corroborates electricity-connection design and the heat-recovery pathway.

Latest dated source: 27 Mar 2025. This is a source publication date, not the review or construction date.

Open full evidence