The Power Reality Check

Before you commit to a site, check the claim.

A concise, independent commercial assessment of one European data-centre or powered-land site. Understand what is evidenced, what remains unknown and what to check next.

Public records and documents you are authorised to share.

Explore the data
01

What can you rely on?

Separate the published facts, attributed claims and calculations from the gaps.

02

What could stop the site?

Read power, planning and development constraints together, with conflicts kept visible.

03

What should happen next?

A go, no-go or proceed-with-conditions commercial view, with the documents and specialist checks needed.

Ten connected checks

Power is central. The site still has to work.

Read the methodology
01

Planning and decisions

Permissions, conditions, appeals and the next decision needed.

02

Land-use zoning

The adopted policy and whether the proposed use fits.

03

Grid and import position

Applications, offers and connection claims, with their actual evidence.

04

Fibre

Site entry, route evidence and the questions around diversity.

05

Ownership and control

The published ownership position and documents needed to verify control.

06

Land and access

Site boundaries, usable footprint, access and stated constraints.

07

Environment and ground

Published flood, ground, ecology, heritage and environmental issues.

08

Water, cooling and heat

The evidenced utility position and unresolved dependencies.

09

Demand and location

The stated use case and the evidence behind the location claim.

10

Programme and delivery

Grid works, planning, procurement and other dependencies that drive timing.

From question to written opinion

Start with the site and the decision you face.

Send the location, the claim you want tested and any public links. We aim to confirm scope and timing within one working day after reviewing the available information.

If you tell us in writing within five working days of delivery that the opinion added nothing to your existing knowledge, the fee is waived.

Request a Reality Check

The research behind the service

Explore the public records, evidence and unresolved questions.

173Data-centre projects
31Active land investigations & watches
31Demand & infrastructure signals
24Connected location groups

The research atlas

Explore Europe

Choose a country to see the projects and land behind the signals.

Open workspace
Jump to

All Europe 173 records

View all

Ordered by depth of linked evidence

IrelandPermitted

Art Data Centres — Ennis campus

Art Data Centres Limited

200 MW unspecifiedCapacity basis

Conflicting published claim · Planned six-hall campus. The June 2022 NTS describes 200 MW IT, but EIAR chapter 2 describes 200 MW total load and 27 MW IT per hall. The published definitions conflict; no verified operating or secured-import capacity is implied.

15 sources
United KingdomOperating

Kao Data KLON-02

Kao Data

10 MW ITCapacity basis

Published claim · KLON-02 expandable design/2023 opening headline. Operator described 8.8 MW base expandable to 10 MW; current undated campus page still lists 8.8 MW. Neither is spare capacity or utility import.

13 sources
United KingdomUnder construction

Kao Data KLON-03

Kao Data

17.6 MW ITCapacity basis

Published claim · KLON-03 planned hybrid-cooled IT capacity. Not secured utility MVA.

13 sources
CzechiaUnder construction

CRA Prague Gateway DC

CRA Prague Gateway DC a.s. / České Radiokomunikace

4 MW ITCapacity basis

Published claim · Initial phase-one IT module in Cordiant's 2026 results; full campus design is 17.3 MW IT. These are development capacities, not operational MW.

11 sources
Open full directory
Coverage is developing. Published capacity is not proof of available grid import.Country coverage

Beyond the project directory

A signal is a starting point.

Follow it through the infrastructure, the site and the people involved.

All intelligence
Power + fibre

Western Ireland

Where could the next cluster emerge?

Transmission plans meet a new fibre corridor. The connection horizon is the deciding constraint.Follow the story
Land + planning

Belview, Ireland

What happens before a project is announced?

Access and utility preparation reveal a landbank worth watching. Import capacity remains unverified.Follow the story
Demand + delivery

Prague, Czechia

Who is turning demand into a project?

Connect the capacity reservation, contractor appointment and fibre procurement to one campus.Follow the story
Find the project teamDevelopers, contractors and consultants in one place.
Compare the evidenceBring land, power and planning side by side.