CRA construction project with documented optical partners and an AI-cloud reservation LOI. Issuer power scopes are differentiated; utility import rights and delivery targets remain unverified.
Read overviewCRA Prague Gateway DC
Jíloviště, Prague region, Czechia
Watch this site
Watch CRA Prague Gateway DC
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
11 cited sources · 10 utility and planning categories reviewed.
Review evidence and gapsVerify utility agreement, energisation and available contracted demand; do not sum 22/26 MW.
Open the full checkOverview
CRA construction project with documented optical partners and an AI-cloud reservation LOI. Issuer power scopes are differentiated; utility import rights and delivery targets remain unverified.
- Developer / applicant
- CRA Prague Gateway DC a.s. / České Radiokomunikace
- Owner
- Not verified
- Operator
- České Radiokomunikace — intended operator
Planning and delivery status
The September update reports completed preparatory groundworks and an August Skanska construction contract. Main-structure completion and operational handover are not established.
Stage source: 7 Sept 2026Project intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
Czechia grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Initial phase-one IT module in Cordiant's 2026 results; full campus design is 17.3 MW IT. These are development capacities, not operational MW.
Published claimProject source record2N-supported subset of the reported 26 MW site power, per Cordiant's June 2026 filing; not an additional allocation or verified import entitlement.
Published claimCapacity sourceSite power reported by Cordiant, including the 22 MW with fully duplicated 2N infrastructure. Utility contract and available headroom are not published.
Published claimCapacity sourceCordiant reports 26 MW site power, including 22 MW supported by fully duplicated 2N infrastructure. Import rights remain unverified; initial 4 MW IT and 17.3 MW full-build customer capacity are separate.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
10 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidencePrague 16 stormwater decision P16-008411/2025/OŽP of 21 January 2025 cites main-campus siting decision MMpB-SÚ/443/24-965/2024-Ptá of 19 November 2024. It did not then hold the main building permission; CRA subsequently reported that permit in July 2025. The drainage works must finish within two years of legal finality, which remains unverified.
Sources & next check
Land-use zoning
Partial evidenceEIA STC2745 identifies the campus building plots as TI technical-infrastructure land under the local plan. It separately identifies 114 m² of forest land required for entrance widening.
Sources & next check
Grid & import rights
Partial evidenceCordiant reports 26 MW site power, including 22 MW supported by fully duplicated 2N infrastructure. Import rights remain unverified; initial 4 MW IT and 17.3 MW full-build customer capacity are separate.
Sources & next check
Fibre & dark fibre
Partial evidenceCRA names five optical partners; connections are partly complete and partly under construction. Bought/leased infrastructure and new routes are described.
Sources & next check
Ownership & development control
Partial evidenceCRA says it owns the former transmitter site. Third-party development control is not established.
Sources & next check
Land, footprint & access
Partial evidenceThe authority screening file identifies 53,764 m² and Jíloviště parcels 505/2, 505/3, 505/14, 527–538 and building parcels st.375, st.376, st.377 and st.379. This is the assessed campus footprint, not available land or a title extract.
Sources & next check
Flood, ground & environment
Partial evidenceScreening decision 010565/2025/KUSK, file SZ_157669/2024/KUSK, dated 22 January 2025, concludes that EIA STC2745 need not undergo full assessment. Its scope includes standby diesel and fuel storage. This is screening, not proof of all environmental permissions or condition compliance.
Sources & next check
Water, cooling & heat
Partial evidenceWastewater works decision P16-009601/2025/OŽP approves temporary treatment/sewer works pending public-sewer connection, but expressly requires separate water-use permission for enforceability. Its cover says 21 January 2024; proceedings and the paired stormwater decision identify 21 January 2025. No abstraction or cooling-water entitlement is established.
Sources & next check
Demand & location fit
Partial evidencePolarise reports an LOI reserving 15 MW for AI cloud. Binding occupancy and campus operation by Polarise are not established.
Sources & next check
Programme & delivery
Partial evidenceDeveloper material targets H1 2028; Polarise describes mid-2027. Neither is achieved energisation.
Sources & next check
Project team
Appointments are limited to the project, phase and scope supported by each source.
Main contractor
Initial main construction scope covers site infrastructure, foundations and the load-bearing precast concrete structure; later packages must be checked separately.
Appointment sourceSpecialists & vendors
Optical infrastructure partner; connections partly under construction. No campus GC role inferred.
Appointment sourceOptical infrastructure partner; connections partly under construction. No campus GC role inferred.
Appointment sourceOptical infrastructure partner; connections partly under construction. No campus GC role inferred.
Appointment sourceOptical infrastructure partner; connections partly under construction. No campus GC role inferred.
Appointment sourceOptical infrastructure partner; connections partly under construction. No campus GC role inferred.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- CRA — Skanska appointed and construction beginscra.cz · 24 Aug 2026
- Cordiant Digital Infrastructure — 2026 results and Prague Gateway phase scopedata.fca.org.uk · 19 Jun 2026
- Prague Gateway — current capacity and programmepraguegateway.com · Publication date unstated
- CRA — permit and land/power claimscra.cz · 31 Jul 2025
- CRA — primary optical connections securedpraguegateway.com · 14 Sept 2026
- CRA — August construction updatepraguegateway.com · 7 Sept 2026
- Polarise — Prague Gateway reservation LOIpolarise.eu · 9 Sept 2026
- CRA — contracted optical partners and route progresscra.cz · 14 Sept 2026
- Středočeský kraj — EIA STC2745 screening decision 010565/2025/KUSKportal.cenia.cz · 22 Jan 2025
- Prague 16 — stormwater works decision P16-008411/2025/OŽPjiloviste.cz · 21 Jan 2025
- Prague 16 — wastewater works decision P16-009601/2025/OŽP, inconsistent cover yearjiloviste.cz · Publication date unstated
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.