atNorth DEN01 Copenhagen

Ballerup / Copenhagen, Denmark

Reviewed 28 Sept 20269 sources
Watch this site

Watch atNorth DEN01 Copenhagen

Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.

Fields marked * are required.

Checking enquiry availability…

Request details

Register your interest in monitoring this record. Alerts are not active yet. Site Watch will cost €150 per site per month excluding VAT after any included trial.

Optional. Public information only. Do not include confidential or non-public information.

Project brief

Brownfield redevelopment at Tonsbakken 12–14 with GPP architectural attribution and a final backup-power environmental approval. Vestforbrænding confirms a heat agreement with 2028 infrastructure readiness…

Read overview
Next check

Obtain network-approved metering/supply design and the site-specific demand connection agreement.

Open the full check

Overview

Brownfield redevelopment at Tonsbakken 12–14 with GPP architectural attribution and a final backup-power environmental approval. Vestforbrænding confirms a heat agreement with 2028 infrastructure readiness targeted.

Developer / applicant
atNorth
Owner
Not verified
Operator
atNorth

Planning and delivery status

The current undated operator page confirms the first phase went live in Q4 2025. It does not identify the operating MW of that first phase.

Stage source: Publication date unstated

Project intelligence. This record does not establish that the land or facility is available to acquire.

POWER STUDY

Power

What the power evidence establishes

The site-specific connection scope has not been established for this record.

Power classDNo qualifying rung

No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.

The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.

Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.

Read the rules and verification levels
01

Capacity ladder and evidence

Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.

01

Applied

Unknown

Not established from the public records reviewed.

What applied mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the applied connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the applied connection evidence cover?
Verification
Unknown
02

Offered

Unknown

Not established from the public records reviewed.

What offered mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the offered connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the offered connection evidence cover?
Verification
Unknown
03

Accepted / contracted

Unknown

Not established from the public records reviewed.

What accepted or contracted mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the accepted connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the accepted connection evidence cover?
Verification
Unknown
04

Energised

Unknown

Not established from the public records reviewed.

What energised mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the energised connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the energised connection evidence cover?
Verification
Unknown
Connection point and load boundaries
Network operator
Unknown

Not established from the public records reviewed.

Which TSO or DSO is responsible for this demand connection?
Connection point
Unknown

Not established from the public records reviewed.

What is the operator-confirmed connection substation or circuit?
Voltage
Unknown

Not established from the public records reviewed.

What voltage level is specified for the demand connection?
Straight-line distance
Unknown

Not established from the public records reviewed.

What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Published route length
Unknown

Not established from the public records reviewed.

What grid route length is published, and for which circuit?

IT load

Unknown

Not established from the public records reviewed.

What is the published IT load in MW?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the IT load in MW stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the IT load in MW cover?

Facility load

Unknown

Not established from the public records reviewed.

What is the published facility load in MW?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the facility load in MW stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the facility load in MW cover?

Import capacity

Unknown

Not established from the public records reviewed.

What is the published import capacity in MVA?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the import capacity in MVA stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the import capacity in MVA cover?

These are different electrical quantities. No power factor, PUE or available import is assumed from an IT-load statement.

Connection agreement and conditions
Agreement type
Unknown

Not established from the public records reviewed.

What connection agreement type and current status are documented?
Phased capacity
Unknown

Not established from the public records reviewed.

Does the agreement impose phased import-capacity limits?
Flexibility obligations
Unknown

Not established from the public records reviewed.

What flexibility or curtailment obligations apply?
On-site generation obligations
Unknown

Not established from the public records reviewed.

What on-site generation obligations apply?
Securities posted
Unknown

Not established from the public records reviewed.

What securities are required, posted and still valid?
Longstop dates
Unknown

Not established from the public records reviewed.

What connection longstop or milestone dates apply?
02

Conflicts and scope comparisons

No conflicting pair is recorded. This does not establish that all public statements have been reconciled.

03

Denmark grid context

Network publications frame the claim. They do not allocate capacity to this site.

No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.

Country coverage: prepared sources; site-level research not extended. View all country sources and refresh schedules.

04

Derived energisation window

Earliest plausible yearUnknown
Latest plausible yearUnknown

The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.

Rule

Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.

No observed inputs establish this result.

Dependencies driving the range

  • Connection-dependent reinforcement scope and completion dates: unknown.
  • Grid-works planning status and programme: unknown.
  • Applicable connection-policy conditions and programme: unknown.

What the earliest case requires

  • Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
  • Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
  • Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.

Missing inputs leave the range open

  • A dated, document-verified import-MVA rung for the assessed scope.
  • An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
  • Connection-dependent reinforcement scope and completion dates
  • Grid-works planning status and programme
  • Applicable connection-policy conditions and programme
05

Indicative HV and connection capex

Unknown

Rule and scope

Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.

No observed inputs establish this result.

Published connection works scope
Unknown

Not established from the public records reviewed.

What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Scope completeness
Unknown

Not established from the public records reviewed.

Is the published connection scope complete enough to match every component to a sourced benchmark?

Scope questions

  • Obtain a published complete connection scope with voltage, configuration and measured quantities.
  • Establish that every necessary connection-work component is included in the published scope.
  • Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Country reference bands and sources

No eligible published capex reference has been recorded. Country bands remain unknown.

06

Alternatives and policy exposure

Behind-the-meter generation

Unknown

Not established from the public records reviewed.

What behind-the-meter generation is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require behind-the-meter generation?

Battery storage

Unknown

Not established from the public records reviewed.

What battery storage is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require battery storage?

Private wire

Unknown

Not established from the public records reviewed.

What a private wire is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require a private wire?

Gas

Unknown

Not established from the public records reviewed.

What gas supply or generation is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require gas supply or generation?

Connection claim against current policy

Unknown

Not established from the public records reviewed.

Does the published connection claim meet the policy applicable to its application date, location and agreement status?
07

Open questions for a Reality Check

Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.

60 questions to resolve
  1. Which TSO or DSO is responsible for this demand connection?

    Not established from the public records reviewed.

  2. What is the operator-confirmed connection substation or circuit?

    Not established from the public records reviewed.

  3. What voltage level is specified for the demand connection?

    Not established from the public records reviewed.

  4. What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?

    Not established from the public records reviewed.

  5. What grid route length is published, and for which circuit?

    Not established from the public records reviewed.

  6. What applied mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  7. What is the effective date of the applied connection evidence?

    Not established from the public records reviewed.

  8. Which buildings or phases does the applied connection evidence cover?

    Not established from the public records reviewed.

  9. What evidence level can be supported for capacityLadder.applied?

    Verification has not been established.

  10. What offered mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  11. What is the effective date of the offered connection evidence?

    Not established from the public records reviewed.

  12. Which buildings or phases does the offered connection evidence cover?

    Not established from the public records reviewed.

  13. What evidence level can be supported for capacityLadder.offered?

    Verification has not been established.

  14. What accepted or contracted mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  15. What is the effective date of the accepted connection evidence?

    Not established from the public records reviewed.

  16. Which buildings or phases does the accepted connection evidence cover?

    Not established from the public records reviewed.

  17. What evidence level can be supported for capacityLadder.accepted?

    Verification has not been established.

  18. What energised mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  19. What is the effective date of the energised connection evidence?

    Not established from the public records reviewed.

  20. Which buildings or phases does the energised connection evidence cover?

    Not established from the public records reviewed.

  21. What evidence level can be supported for capacityLadder.energised?

    Verification has not been established.

  22. What connection agreement type and current status are documented?

    Not established from the public records reviewed.

  23. Does the agreement impose phased import-capacity limits?

    Not established from the public records reviewed.

  24. What flexibility or curtailment obligations apply?

    Not established from the public records reviewed.

  25. What on-site generation obligations apply?

    Not established from the public records reviewed.

  26. What securities are required, posted and still valid?

    Not established from the public records reviewed.

  27. What connection longstop or milestone dates apply?

    Not established from the public records reviewed.

  28. What is the published IT load in MW?

    Not established from the public records reviewed.

  29. On what electrical basis is the IT load in MW stated?

    Not established from the public records reviewed.

  30. Which phase or campus does the IT load in MW cover?

    Not established from the public records reviewed.

  31. What is the published facility load in MW?

    Not established from the public records reviewed.

  32. On what electrical basis is the facility load in MW stated?

    Not established from the public records reviewed.

  33. Which phase or campus does the facility load in MW cover?

    Not established from the public records reviewed.

  34. What is the published import capacity in MVA?

    Not established from the public records reviewed.

  35. On what electrical basis is the import capacity in MVA stated?

    Not established from the public records reviewed.

  36. Which phase or campus does the import capacity in MVA cover?

    Not established from the public records reviewed.

  37. What operator-published connection-to-energisation duration applies to this site and connection stage?

    An application-to-offer processing target is not an energisation duration.

  38. Which reinforcements does the connection depend on, and what dates are published?

    Not established from the public records reviewed.

  39. Which grid works require planning, and what is their current consent status and dated programme?

    Not established from the public records reviewed.

  40. Which connection-policy conditions apply, and when could they be satisfied?

    Not established from the public records reviewed.

  41. What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?

    Not established from the public records reviewed.

  42. Is the published connection scope complete enough to match every component to a sourced benchmark?

    Not established from the public records reviewed.

  43. What behind-the-meter generation is evidenced, and at what scope?

    Not established from the public records reviewed.

  44. Does the applicable planning or connection policy require behind-the-meter generation?

    Not established from the public records reviewed.

  45. What battery storage is evidenced, and at what scope?

    Not established from the public records reviewed.

  46. Does the applicable planning or connection policy require battery storage?

    Not established from the public records reviewed.

  47. What a private wire is evidenced, and at what scope?

    Not established from the public records reviewed.

  48. Does the applicable planning or connection policy require a private wire?

    Not established from the public records reviewed.

  49. What gas supply or generation is evidenced, and at what scope?

    Not established from the public records reviewed.

  50. Does the applicable planning or connection policy require gas supply or generation?

    Not established from the public records reviewed.

  51. Does the published connection claim meet the policy applicable to its application date, location and agreement status?

    Not established from the public records reviewed.

  52. Which checked country-grid sources and location-specific constraints apply to this connection?

    No country-context relationship has been established for this record.

  53. Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.

    Connection-cost scope question.

  54. Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.

    This missing input leaves an energisation bound unknown.

  55. Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.

    This missing input leaves an energisation bound unknown.

  56. Resolve the energisation input: Connection-dependent reinforcement scope and completion dates

    This missing input leaves an energisation bound unknown.

  57. Resolve the energisation input: Grid-works planning status and programme

    This missing input leaves an energisation bound unknown.

  58. Resolve the energisation input: Applicable connection-policy conditions and programme

    This missing input leaves an energisation bound unknown.

  59. Obtain a published complete connection scope with voltage, configuration and measured quantities.

    This scope or reference gap prevents a complete indicative connection capex band.

  60. Establish that every necessary connection-work component is included in the published scope.

    This scope or reference gap prevents a complete indicative connection capex band.

Use these questions to scope a Power Reality Check.

Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.

Request a Reality Check
Earlier capacity notes and source context
30 MW facilityProject capacity

Operator-advertised total campus power capacity; first-phase commissioned capacity is not separately disclosed.

Published claimProject source record
Import rights and connection evidence

The municipal technical attachment describes atNorth as a 50 kV Ahøj customer and proposes feeding heat pumps through its internal 20 kV network. This supplies connection-design context, not a verified campus import limit or spare allocation.

IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.

Planning & utilities

8 of 10 categories contain evidence. Each status applies to its specific claim.

Planning & decisions

Partial evidence

Alongside the 2 December 2024 backup-power approval, Ballerup issued a no-full-EIA screening decision on 17 March 2026 for Vestforbrænding’s heat-pump project, case 13.03.18-P15-3-26. It lapses if unused within three years; appeal outcome remains unchecked.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Verify use/commencement of the heat-project screening decision, appeal outcomes and separate building approvals.

Land-use zoning

Documented

The approval identifies Tonsbakken 12–14 on parcel 14dm, Skovlunde By, Skovlunde, within local plan 121 (2006).

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Check subsequent local-plan amendments and match the operational footprint to parcel 14dm.

Grid & import rights

Partial evidence

The municipal technical attachment describes atNorth as a 50 kV Ahøj customer and proposes feeding heat pumps through its internal 20 kV network. This supplies connection-design context, not a verified campus import limit or spare allocation.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Obtain network-approved metering/supply design and the site-specific demand connection agreement.

Ownership & development control

Partial evidence

Seller CapMan confirms sale of Tonsbakken 12–14 to two separate parties, atNorth and Propreco. The announcement does not allocate the property between them or establish the registered title to DEN01.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Reconcile the subdivision and registered owner of parcel 14dm; do not assign the entire former warehouse property to atNorth.

Land, footprint & access

Partial evidence

The approval describes an existing developed site, a 26,748 m² plot and 9,700 m² full-build building area. GPP’s separate 10,798 m² project-area metric is not land area.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Reconcile approved building area and actual phase boundaries, access and remaining expansion land.

Flood, ground & environment

Partial evidence

The permit requires daytime testing one generator at a time, limits each generator’s operating hours, and requires emissions evidence after each phase’s initial tests. Backup-generator ratings are not demand capacity.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Check submitted emissions/noise testing and operating notifications in DMA for every commissioned phase.

Water, cooling & heat

Partial evidence

The screened heat-pump project serves the planned Ballerup Boulevard transmission network. Viegand Maagøe’s 26 June 2025 study uses 15 MW thermal recovery for its business case, with 2028 as the expectation; summertime heat offtake is uncertain. No commissioned heat output is established.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Reconcile final heat-pump selection, pipeline and operating acceptance with the utility’s 2028 programme.

Programme & delivery

Partial evidence

The current operator says phase one went live in Q4 2025; Vestforbrænding’s November 2025 announcement forecast data-centre operation in Q1 2026. The difference is retained; neither gives phase-one operating MW.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Match occupancy/commissioning evidence and individual hall dates before treating 30 MW full-campus capacity as live.

Not assessed

Fibre & dark fibreDemand & location fit
Evidence still needed
  • Fibre & dark fibre

    No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.

  • Demand & location fit

    Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.

Project team

Appointments are limited to the project, phase and scope supported by each source.

Architect

Engineering consultant

Søren Jensen Rådgivende Ingeniørfirma A/SOther projects

DEN01 developer adviser and client for C7’s environmental technical description, as identified in the municipal permit attachment; specific design disciplines are not allocated.

Appointment source
C7 Consulting A/SOther projects

Prepared DEN01 environmental technical description and applied on behalf of Søren Jensen; environmental application scope.

Appointment source
Viegand MaagøeOther projects

Prepared Vestforbrænding’s 26 June 2025 technical options and business-case note for the DEN01 heat-pump/heat-recovery plant; not campus-wide MEP designer.

Appointment source

Unlisted roles have no project-specific appointment recorded.

Sources

Publication dates are shown where known. Review dates do not establish approval or commissioning.

  1. atNorth: DEN01 Copenhagen profile and first-phase openingatnorth.com · Publication date unstated
  2. Ballerup municipality — DEN01 environmental approval dated 2 December 2024ballerup.dk · 2 Dec 2024
  3. Danish DMA — final backup-power approval, published 13 January 2025dma.mst.dk · 13 Jan 2025
  4. Vestforbrænding — DEN01 heat agreement and 2028 infrastructure targetvestfor.dk · 26 Nov 2025
  5. CapMan — Tonsbakken 12–14 sale to atNorth and Propreconews.cision.com · 12 Oct 2023
  6. GPP Arkitekter — DEN01 architectural project sheet, project years 2023–2025gpp.dk · Publication date unstated
  7. Ballerup: DEN01 heat-pump project EIA screening decision, case 13.03.18-P15-3-26ballerup.dk · 17 Mar 2026
  8. Viegand Maagøe for Vestforbrænding: DEN01 heat-recovery technical options, municipal attachmentballerup.dk · 26 Jun 2025
  9. Ballerup: DEN01 environmental technical description, C7 Consulting for Søren Jensen; cover dated 21 March 2024 with later referencesballerup.dk · Publication date unstated