Meta Clonee campus

Clonee, County Meath, Ireland

Reviewed 28 Sept 202610 sources
Watch this site

Watch Meta Clonee campus

Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.

Fields marked * are required.

Checking enquiry availability…

Request details

Register your interest in monitoring this record. Alerts are not active yet. Site Watch will cost €150 per site per month excluding VAT after any included trial.

Optional. Public information only. Do not include confidential or non-public information.

Project brief

Meta’s first Irish data-centre campus, distinct from neighbouring EngineNode. Named delivery appointments are recorded by package and phase. The developer’s 219 MW renewable-energy figure covers generation…

Read overview
Next check

Match current supply agreements and asset boundaries to the two substations; obtain scoped import MVA/MW and rights-holder evidence.

Open the full check

Overview

Meta’s first Irish data-centre campus, distinct from neighbouring EngineNode. Named delivery appointments are recorded by package and phase. The developer’s 219 MW renewable-energy figure covers generation projects and is not campus IT load or contracted import; an older architect’s 108 MVA design statement is not treated as a current connection agreement.

Developer / applicant
Meta (Facebook)
Owner
Not verified
Operator
Meta

Planning and delivery status

Meta’s current Clonee information sheet identifies operational data-centre buildings and operational jobs. Historical contractor portfolios evidence completed early phases; the status of every later phase is not implied.

Stage source: Publication date unstated

Project intelligence. This record does not establish that the land or facility is available to acquire.

POWER STUDY

Power

What the power evidence establishes

Historical 2018 Clonee campus demand and related extension infrastructure, retained separately from current import rights.

Power classDNo qualifying rung

No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.

The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.

Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. Evidence reviewed 19 October 2026.

Read the rules and verification levels
01

Capacity ladder and evidence

Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.

01

Applied

Unknown

Not established from the public records reviewed.

What applied import MVA is evidenced for this campus or phase?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the applied import-capacity evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings and phases does the applied import capacity cover?
Verification
Unknown
02

Offered

Unknown

Not established from the public records reviewed.

What offered import MVA is evidenced for this campus or phase?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the offered import-capacity evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings and phases does the offered import capacity cover?
Verification
Unknown
03

Accepted / contracted

Unknown

Not established from the public records reviewed.

What accepted import MVA is evidenced for this campus or phase?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the accepted import-capacity evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings and phases does the accepted import capacity cover?
Verification
Unknown
04

Energised

Unknown

Not established from the public records reviewed.

What energised import MVA is evidenced for this campus or phase?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the energised import-capacity evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings and phases does the energised import capacity cover?
Verification
Unknown

The 2018 inspector describes an existing grid supply, but publishes no energised import MVA or effective energisation date. Operating campus status cannot fill these fields.

Connection point and load boundaries
Network operator
Observed
EirGrid (TSO)
Connection point
Observed
Existing Portan 220 kV loop-in substation; the extension proposed a new on-site station linked to it.
Voltage
Observed
220 kV
Straight-line distance
Unknown

Not established from the public records reviewed.

What are the verified site and connection-point coordinates, and their calculated straight-line distance?
Published route length
Unknown

The report gives an approximate 2.5-kilometre cable description but does not resolve the measurement basis for a complete current connection route.

Does the 2018 description of two cables at approximately 2.5 kilometres mean route length per circuit or aggregate cable length, and what was built?

IT load

Unknown

Not established from the public records reviewed.

What IT load in MW is evidenced?
Basis
Unknown

Not established from the public records reviewed.

What electrical basis is stated for IT load in MW?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase and campus boundary does IT load in MW cover?

Facility load

Observed
180 MW
Basis
Observed
Maximum campus electrical demand reported in the 2018 planning assessment, not IT load or import MVA.
Site / phase boundary
Observed
Overall campus as assessed in 2018; the added development was separately described as 72 MW.

Import capacity

Unknown

Not established from the public records reviewed.

What import capacity in MVA is evidenced?
Basis
Unknown

Not established from the public records reviewed.

What electrical basis is stated for import capacity in MVA?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase and campus boundary does import capacity in MVA cover?

These are different electrical quantities. No power factor, PUE or available import is assumed from an IT-load statement.

Connection agreement and conditions
Agreement type
Observed
The inspector records an EirGrid accommodation letter conditional on a modified connection agreement; the executed agreement and allocated MVA were not reviewed.
Phased capacity
Unknown

Not established from the public records reviewed.

What phased import limits apply?
Flexibility obligations
Unknown

Not established from the public records reviewed.

What flexibility or curtailment obligations apply?
On-site generation obligations
Unknown

Not established from the public records reviewed.

What generation or storage obligations apply to this agreement?
Securities posted
Unknown

Not established from the public records reviewed.

What securities are required, posted and still valid?
Longstop dates
Unknown

Not established from the public records reviewed.

What connection milestones or longstop dates apply?
Source quotations and access log (12)
  1. ABP-301923-18 inspector report, pages 6 to 9 and 63An Bord Pleanála, now An Coimisiún Pleanála · Published 15 November 2018 · Accessed 19 October 2026
    EirGrid
    220kV
    modified connection agreement
    180 MW
    72 MW
    back-up generator
  2. Clonee extension grid infrastructure consentAn Coimisiún Pleanála · Published 6 December 2018 · Accessed 19 October 2026
    Approve with Conditions
  3. Energy infrastructure unit investment cost (UIC) indicators, 2026Agency for the Cooperation of Energy Regulators (ACER) · Published 24 April 2026 · Accessed 19 October 2026
    Meur/km
    Meur/asset
  4. Standard Prices for Generator Connections 2026, revision 16, effective 1 January 2026ESB Networks DAC · Published 2026 · Accessed 19 October 2026
    Standard Charge
  5. CRU/2025236: Large Energy Users Connection Policy decisionCommission for Regulation of Utilities · Published 12 December 2025 · Accessed 19 October 2026
    Large Energy Users Connection Policy
  6. Data Centre Connection Offer Process and Policy, Version 3EirGrid · Published 20 May 2026 · Accessed 19 October 2026
    a data centre application cannot be progressed if it is in a constrained area
  7. Data Centre Technical AssessmentEirGrid · Published 20 May 2026 · Accessed 19 October 2026
    will need to focus on connection voltages above 110 kV
  8. Data Centre Constrained Area OverviewEirGrid · Published 20 May 2026 · Accessed 19 October 2026
    New capacity is not secured until a connection agreement contract is executed.
  9. CRU2026145: Grid Code Modification MPID 345 and Compliance and Derogation FrameworkCommission for Regulation of Utilities · Published 22 September 2026 · Accessed 19 October 2026
    both currently connected and future connections
  10. MPID 345 CRU approval letter and effective dateCommission for Regulation of Utilities, hosted by EirGrid · Published 22 September 2026 · Accessed 19 October 2026
    The Grid Code will be deemed to be amended five weeks from the date of this decision letter.
  11. Transmission Development Plan 2024 and regulatory publications registerEirGrid · Published Unknown · Accessed 19 October 2026
    Transmission Development Plan 2024
  12. An Coimisiún Pleanála case search and strategic infrastructure casesAn Coimisiún Pleanála · Published Unknown · Accessed 19 October 2026
    Case search
02

Conflicts and scope comparisons

Different bases; relationship unresolved

180 MW campus and 72 MW addition have different scopes

Keep whole-campus and addition values separate; neither is a current import-MVA entitlement.

Historical whole-campus maximum electrical demand
Observed
180

MW facility demand, whole 2018 campus

Added development maximum electrical demand
Observed
72

MW facility demand, added development only

Resolution
Derived
Different development scopes, not competing measurements of the same import capacity.
Rule and inputs

Compare values only after electrical basis, date and development boundary match.

Whole-campus facility demand
180 MW
Added-development facility demand
72 MW
03

Ireland grid context

Network publications frame the claim. They do not allocate capacity to this site.

CRU/2025236: Large Energy Users Connection Policy decisionCommission for Regulation of Utilities · Source checked

Connection policy for new data centre applications, including matching dispatchable generation or storage, additional renewable electricity and network location assessment. At least 80% of annual demand must be met by additional renewable electricity generated in the Republic of Ireland, with a six-year glide path from energisation. Requirements and transitional scope must be checked against the actual application date and connection position.

A policy requirement is not evidence that a particular site has complied or has connection rights. Onsite or proximate generation is permitted; onsite-only generation is not a universal requirement. Do not retrospectively apply the new application rules to an earlier agreement without checking transitional scope. No fixed publisher update cadence is stated; PowerPlotr proposes a weekly policy check.

Commission for Regulation of Utilities: CRU/2025236: Large Energy Users Connection Policy decisionPublished 12 December 2025 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotation
Data Centre Connection Offer Process and Policy, Version 3EirGrid · Source checked

Implements CRU/2025236. For new transmission data centres at or above 10 MVA, nominated dispatchable generation or storage must match MIC after applicable de-rating and be delivered before energisation or demand ramp-up. Nominated generation is separately connected and metered and participates in the SEM. The stated offer-processing periods are approximately 7.5 calendar months where nominated generation and renewables already have offers, or up to 18 months where associated generation has newly applied through ECP-GSS.

These are conditional application-to-offer periods, not construction or energisation durations, and are excluded from energisation calculations. A complete application, linked generation status and fees matter. An offer is not an accepted agreement. Earlier applications can remain under CRU/21/124. Publisher updates are event-driven; proposed review is weekly.

EirGrid: Data Centre Connection Offer Process and Policy, Version 3Published 20 May 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotation
Data Centre Technical AssessmentEirGrid · Source checked

Explains application-specific assessment of capacity, voltage, system stability, short-circuit effects and outages. Continuous demand above 50 MW is significant for the Irish 110 kV network and should focus on connection voltages above 110 kV. Dedicated loop-in connections are difficult to integrate and require wider system benefit.

General technical context cannot establish a connection point, headroom or capacity allocation for a particular site. Every proposal still requires operator assessment. Publisher cadence is event-driven; proposed review is monthly and after a related policy decision.

EirGrid: Data Centre Technical AssessmentPublished 20 May 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 30 daysRead the source quotation
Data Centre Constrained Area OverviewEirGrid · Source checked

Pages 11 to 12 identify high-level potential on the 220 kV network around Galway, Limerick and Cork, subject to individual assessment and policy compliance. The overview considers greater Dublin fully constrained for new data centre development. It advises a prudent mid-2030s assumption for new connections in the identified areas because of work and outage programmes.

Regional opportunity is not site-specific capacity or a contractual right. Mid-2030s is qualitative operator context, not a bounded energisation window or a promised 2035 date. Earlier applications and agreements require their own transitional-policy check. Detailed heat maps are planned through the 2027 Ten Year Transmission Forecast Statement. No recurring publisher cadence is specified; proposed review is monthly.

EirGrid: Data Centre Constrained Area OverviewPublished 20 May 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 30 daysRead the source quotation
CRU2026145: Grid Code Modification MPID 345 and Compliance and Derogation FrameworkCommission for Regulation of Utilities · Source checked

Approves fault ride-through, rate of change of frequency and active power recovery requirements for existing and future transmission-connected demand facilities. The technical requirements include remaining connected within the specified voltage profile, withstanding plus or minus 1 Hz/s and recovering 90% of pre-fault active power within 500 milliseconds after fault clearance and voltage recovery to 0.9 per unit. Compliance is assessed at the point of connection.

The associated Grid Code amendment takes effect on 27 October 2026. This is a separate technical requirement from the December 2025 connection policy. Site compliance, an approved derogation and any demand utilisation restriction need direct evidence. Missing public compliance evidence means unverified, not automatically non-compliant. Publisher updates are event-driven; proposed review is weekly.

Commission for Regulation of Utilities: CRU2026145: Grid Code Modification MPID 345 and Compliance and Derogation FrameworkPublished 22 September 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotation
MPID 345 CRU approval letter and effective dateCommission for Regulation of Utilities, hosted by EirGrid · Source checked

The CRU directs EirGrid to amend the Grid Code five weeks after the 22 September 2026 decision. EirGrid's Grid Code Modifications register labels this approval effective 27 October 2026. The letter applies the technical requirements to all transmission-connected demand facilities.

The effective date does not itself prove compliance or an energisation entitlement at any site. Review the decision, current Grid Code and any approved derogation together. Publisher cadence is event-driven; proposed review is weekly through implementation.

Commission for Regulation of Utilities, hosted by EirGrid: MPID 345 CRU approval letter and effective datePublished 22 September 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotation
Transmission Development Plan 2024 and regulatory publications registerEirGrid · Source checked

The checked regulatory publication register lists Transmission Development Plan 2024, the 2024 Ten-Year Transmission Forecast Statement and current adequacy publications. This is the discovery and version-control entry for the earlier published development plan while the 2026 to 2035 draft is under CRU consultation.

A listed project is not evidence that it supplies a particular site, has all consents, or guarantees a delivery date. No reinforcement dependency has been assigned to a pilot merely from geographic proximity. The statutory development-plan cycle is two years; PowerPlotr proposes monthly checks for a new approved version or delivery update.

EirGrid: Transmission Development Plan 2024 and regulatory publications registerPublished Unknown · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 30 daysRead the source quotation
An Coimisiún Pleanála case search and strategic infrastructure casesAn Coimisiún Pleanála · Source checked

Official search for appeals, direct strategic infrastructure applications and related cases, including grid works. The current authority is An Coimisiún Pleanála, formerly An Bord Pleanála. Search by case reference, location, applicant and infrastructure to match a site with grid planning decisions and conditions. Proposed review is weekly and whenever a relevant case changes.

A grid planning application, pre-application consultation or permission does not establish an executed connection agreement, import capacity, route rights or energisation. Check the actual decision documents and exact development boundary. A target decision date is not the decision. The portal has no guaranteed fixed case-update interval.

An Coimisiún Pleanála: An Coimisiún Pleanála case search and strategic infrastructure casesPublished Unknown · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotation

Country coverage: Ireland pilot. View all country sources and refresh schedules.

04

Derived energisation window

Earliest plausible yearUnknown
Latest plausible yearUnknown

The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.

Rule

Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.

Clonee extension grid infrastructure consent: earliest readiness
Unknown
Input evidence
Clonee extension grid infrastructure consent: latest readiness
Unknown
Input evidence

Dependencies driving the range

  • Connection-dependent reinforcement scope and completion dates: unknown.
  • Clonee extension grid infrastructure consent: Conditional planning consent signed 2018-12-06. This is a planning decision only; electrical completion years and current programme are unknown.
  • Applicable connection-policy conditions and programme: unknown.

What the earliest case requires

  • Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
  • Clonee extension grid infrastructure consent is ready by the earliest case, which has no published readiness date: Conditional planning consent signed 2018-12-06. This is a planning decision only; electrical completion years and current programme are unknown.
  • Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.

Missing inputs leave the range open

  • A dated, document-verified import-MVA rung for the assessed scope.
  • An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
  • Connection-dependent reinforcement scope and completion dates
  • Earliest readiness for Clonee extension grid infrastructure consent.
  • A published upper readiness year for Clonee extension grid infrastructure consent.
  • Applicable connection-policy conditions and programme
05

Indicative HV and connection capex

Unknown

Rule and scope

Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.

No observed inputs establish this result.

Published connection works scope
Observed
  • Proposed 220 kV outdoor AIS station with seven bays and two oil-filled step-down transformers; customer and network compounds described separately. · 220 kV · station · 1 item · Reference
Scope completeness
Derived
partial
Rule and inputs

A station configuration is published, but complete route quantities, ratings and the same-scope cost reference are not verified.

Published proposed station
220 kV AIS; seven bays; two step-down transformers
Input evidence
Complete current priced connection scope
Unknown

Scope questions

  • Establish that every necessary connection-work component is included in the published scope.
  • Separate network and customer costs, upstream reinforcement, land, wayleaves, fees, taxes, securities, contingency and price base.
  • Verify the approved and built station topology, transformer ratings and customer/network boundary.
  • Resolve whether the approximate 2.5 kilometres describes each cable, their common corridor or aggregate cable length.
  • Obtain a published Irish construction comparator for the same 220 kV AIS configuration and price base.
Country reference bands and sources
Ireland: published reference bands and missing configurations
ConfigurationVoltageType / unitLowHighCurrencyPrice baseUse and source
110 to 150 kV, 1 circuit110 / 132 / 150 kVoverhead
per km
570,000910,000EURUnknownContext only
110 to 150 kV, 2 circuits110 / 132 / 150 kVoverhead
per km
300,000390,000EURUnknownContext only
220 kV, 1 circuit220 kVoverhead
per km
320,000510,000EURUnknownContext only
220 kV, 2 circuits220 kVoverhead
per km
440,000740,000EURUnknownContext only
110 to 150 kV, 1 circuit110 / 132 / 150 kVunderground
per km
560,0001,590,000EURUnknownContext only
110 to 150 kV, 2 circuits110 / 132 / 150 kVunderground
per km
1,330,0003,580,000EURUnknownContext only
220 kV, 1 circuit220 kVunderground
per km
1,030,0002,400,000EURUnknownContext only
220 kV, 2 circuits220 kVunderground
per km
2,990,0004,690,000EURUnknownContext only
New GIS station, 0 to 5 bays, all reported voltage classes kVstation
per item
5,480,00015,110,000EURUnknownContext only
New GIS station, 6 to 9 bays, all reported voltage classes kVstation
per item
8,540,00012,600,000EURUnknownContext only
New AIS line bay in existing 110 kV single busbar outdoor station110 kVbay
per item
763,440763,440EUR2026Context only
630 square millimetre aluminium XLPE, single circuit, exactly one kilometre110 kVunderground
per km
398,640398,640EUR2026Context only
Outdoor 110/38 kV, one 31.5 MVA transformer and 38 kV bay and two-bay busbar extension110 kVstation
per item
1,504,2101,504,210EUR2026Context only
Outdoor 110/38 kV, one 63 MVA transformer and 38 kV bay and two-bay busbar extension110 kVstation
per item
1,826,8501,826,850EUR2026Context only
Complete shared substation bay connection in Ireland110 / 220 kVUnknown: A published AIS electrical bay component does not establish civils, shared allocation or a complete connection cost.
Scope questions
  • Which bay type, voltage, scope and cost-sharing arrangement apply?
  • What civils, protection, remote-end and reinforcement works are chargeable?
No eligible reference
Complete new 110 kV substation in Ireland110 kVUnknown: The ESB Networks 2026 whole-station types are discontinued; current transformer components exclude civil works.
Scope questions
  • What busbar arrangement, bay count, transformers, buildings and site works are published?
  • Is an Irish report or tender award available for the same scope and price base?
No eligible reference
New 132 kV substation132 kVUnknown: No Irish same-scope published cost band established; the voltage is a UK comparison requirement.
Scope questions
  • Which jurisdiction and operator standard apply?
  • What published construction reference matches the configuration?
No eligible reference
Complete new 220 kV or 275 kV GIS substation220 / 275 kVUnknown: The EU GIS comparison is grouped by bays, without a voltage-specific matched Irish band.
Scope questions
  • What GIS busbar design, bays, transformer scope and import arrangement are required?
  • Which published cost source matches voltage, geography, scope and price base?
No eligible reference
Complete switching station110 / 220 kVUnknown: No matched complete Irish public construction band verified.
Scope questions
  • What voltage, circuit topology, bay count, civils and protection scope apply?
  • Are published total costs separated from unrelated reinforcement?
No eligible reference
Reference scope, exclusions and price basis
EU comparator: 110 to 150 kV, 1 circuit overhead routeContext only · EUR · Price base unknown

570,000 to 910,000 EUR per km · 110 to 150 kV, 1 circuit · 110 / 132 / 150 kV · overhead

ACER Table I.1, page 43. Published 25th to 75th percentiles, 6 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 110 to 150 kV, 2 circuits overhead routeContext only · EUR · Price base unknown

300,000 to 390,000 EUR per km · 110 to 150 kV, 2 circuits · 110 / 132 / 150 kV · overhead

ACER Table I.1, page 43. Published 25th to 75th percentiles, 8 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 220 kV, 1 circuit overhead routeContext only · EUR · Price base unknown

320,000 to 510,000 EUR per km · 220 kV, 1 circuit · 220 kV · overhead

ACER Table I.1, page 43. Published 25th to 75th percentiles, 15 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 220 kV, 2 circuits overhead routeContext only · EUR · Price base unknown

440,000 to 740,000 EUR per km · 220 kV, 2 circuits · 220 kV · overhead

ACER Table I.1, page 43. Published 25th to 75th percentiles, 25 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 110 to 150 kV, 1 circuit underground routeContext only · EUR · Price base unknown

560,000 to 1,590,000 EUR per km · 110 to 150 kV, 1 circuit · 110 / 132 / 150 kV · underground

ACER Table I.1, page 43. Published 25th to 75th percentiles, 20 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 110 to 150 kV, 2 circuits underground routeContext only · EUR · Price base unknown

1,330,000 to 3,580,000 EUR per km · 110 to 150 kV, 2 circuits · 110 / 132 / 150 kV · underground

ACER Table I.1, page 43. Published 25th to 75th percentiles, 7 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 220 kV, 1 circuit underground routeContext only · EUR · Price base unknown

1,030,000 to 2,400,000 EUR per km · 220 kV, 1 circuit · 220 kV · underground

ACER Table I.1, page 43. Published 25th to 75th percentiles, 20 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: 220 kV, 2 circuits underground routeContext only · EUR · Price base unknown

2,990,000 to 4,690,000 EUR per km · 220 kV, 2 circuits · 220 kV · underground

ACER Table I.1, page 43. Published 25th to 75th percentiles, 9 assets; EU sample, not an Irish construction index.

Fees: inclusion unknown.

Exclusions
  • Historical commissioned routes exceeding 5 kilometres; application to shorter connections is unverified.
  • Single monetary base year not explicitly established. No escalation, currency conversion or country adjustment applied.
  • Fees, customer allocation and project-specific scope are unverified. No complete site estimate may use this reference.
EU comparator: new GIS station with 0 to 5 bays, voltage unspecifiedContext only · EUR · Price base unknown

5,480,000 to 15,110,000 EUR per item · New GIS station, 0 to 5 bays, all reported voltage classes · kV · station

ACER Table I.2, page 44. Published 25th to 75th percentiles, 13 assets.

Fees: inclusion unknown.

Exclusions
  • Voltage-specific and Irish applicability unverified. This is not a 220 kV or 275 kV station band.
  • Single monetary base year not explicitly established.
  • Transformer scope and fees unverified. No complete site estimate may use this reference.
EU comparator: new GIS station with 6 to 9 bays, voltage unspecifiedContext only · EUR · Price base unknown

8,540,000 to 12,600,000 EUR per item · New GIS station, 6 to 9 bays, all reported voltage classes · kV · station

ACER Table I.2, page 44. Published 25th to 75th percentiles, 24 assets.

Fees: inclusion unknown.

Exclusions
  • Voltage-specific and Irish applicability unverified. This is not a 220 kV or 275 kV station band.
  • Single monetary base year not explicitly established.
  • Transformer scope and fees unverified. No complete site estimate may use this reference.
110 kV AIS line bay electrical componentContext only · EUR · 2026 price base

763,440 to 763,440 EUR per item · New AIS line bay in existing 110 kV single busbar outdoor station · 110 kV · bay

Item 35, pages 30 to 31. Electrical component including design and commissioning. Excluding VAT.

Fees: not included.

Exclusions
  • Generator standard charge, not a complete demand connection construction price.
  • Civils and remote-end works excluded; existing space, services and protection assumed adequate.
  • Shared customer contribution, land, access and site-specific reinforcement unknown.
110 kV underground cable electrical component for one kilometreContext only · EUR · 2026 price base

398,640 to 398,640 EUR per km · 630 square millimetre aluminium XLPE, single circuit, exactly one kilometre · 110 kV · underground

Item 8, pages 12 to 13. Generator cable charge for one kilometre only. Excluding VAT.

Fees: not included.

Exclusions
  • For more than one kilometre, ESB Networks states specific tender and pass-through charging apply.
  • Excavation, ducting, reinstatement and other civil works excluded.
  • Not an all-in construction cost or a scalable multi-kilometre rate.
110/38 kV, 31.5 MVA transformer electrical packageContext only · EUR · 2026 price base

1,504,210 to 1,504,210 EUR per item · Outdoor 110/38 kV, one 31.5 MVA transformer and 38 kV bay and two-bay busbar extension · 110 kV · station

Item 19, page 16. Electrical transformer package including design and commissioning. Excluding VAT.

Fees: not included.

Exclusions
  • Generator standard charge; not a complete new 110 kV substation cost.
  • Civil works excluded. Incoming connection, land, remote works and project allocation remain unknown.
110/38 kV, 63 MVA transformer electrical packageContext only · EUR · 2026 price base

1,826,850 to 1,826,850 EUR per item · Outdoor 110/38 kV, one 63 MVA transformer and 38 kV bay and two-bay busbar extension · 110 kV · station

Item 18, page 15. Electrical transformer package including design and commissioning. Excluding VAT.

Fees: not included.

Exclusions
  • Generator standard charge; not a complete new 110 kV substation cost.
  • Civil works excluded. Incoming connection, land, remote works and project allocation remain unknown.
06

Alternatives and policy exposure

Behind-the-meter generation

Observed
The proposed substation scope includes a backup generator; this does not establish primary behind-the-meter supply or a compliant dispatchable capacity allocation.
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require behind-the-meter generation?

Battery storage

Unknown

Not established from the public records reviewed.

What battery storage is evidenced for this connection?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require battery storage?

Private wire

Unknown

Not established from the public records reviewed.

What private wire is evidenced for this connection?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require private wire?

Gas

Unknown

Not established from the public records reviewed.

What gas supply or generation is evidenced for this connection?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require gas supply or generation?

Connection claim against current policy

Unknown

Not established from the public records reviewed.

Does the documented connection position comply with the policy applicable to its application date and agreement status?
07

Open questions for a Reality Check

Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.

61 questions to resolve
  1. What are the verified site and connection-point coordinates, and their calculated straight-line distance?

    Not established from the public records reviewed.

  2. Does the 2018 description of two cables at approximately 2.5 kilometres mean route length per circuit or aggregate cable length, and what was built?

    The report gives an approximate 2.5-kilometre cable description but does not resolve the measurement basis for a complete current connection route.

  3. What applied import MVA is evidenced for this campus or phase?

    Not established from the public records reviewed.

  4. What is the effective date of the applied import-capacity evidence?

    Not established from the public records reviewed.

  5. Which buildings and phases does the applied import capacity cover?

    Not established from the public records reviewed.

  6. What evidence level can be supported for capacityLadder.applied?

    Verification has not been established.

  7. What offered import MVA is evidenced for this campus or phase?

    Not established from the public records reviewed.

  8. What is the effective date of the offered import-capacity evidence?

    Not established from the public records reviewed.

  9. Which buildings and phases does the offered import capacity cover?

    Not established from the public records reviewed.

  10. What evidence level can be supported for capacityLadder.offered?

    Verification has not been established.

  11. What accepted import MVA is evidenced for this campus or phase?

    Not established from the public records reviewed.

  12. What is the effective date of the accepted import-capacity evidence?

    Not established from the public records reviewed.

  13. Which buildings and phases does the accepted import capacity cover?

    Not established from the public records reviewed.

  14. What evidence level can be supported for capacityLadder.accepted?

    Verification has not been established.

  15. What energised import MVA is evidenced for this campus or phase?

    Not established from the public records reviewed.

  16. What is the effective date of the energised import-capacity evidence?

    Not established from the public records reviewed.

  17. Which buildings and phases does the energised import capacity cover?

    Not established from the public records reviewed.

  18. What evidence level can be supported for capacityLadder.energised?

    Verification has not been established.

  19. What phased import limits apply?

    Not established from the public records reviewed.

  20. What flexibility or curtailment obligations apply?

    Not established from the public records reviewed.

  21. What generation or storage obligations apply to this agreement?

    Not established from the public records reviewed.

  22. What securities are required, posted and still valid?

    Not established from the public records reviewed.

  23. What connection milestones or longstop dates apply?

    Not established from the public records reviewed.

  24. What IT load in MW is evidenced?

    Not established from the public records reviewed.

  25. What electrical basis is stated for IT load in MW?

    Not established from the public records reviewed.

  26. Which phase and campus boundary does IT load in MW cover?

    Not established from the public records reviewed.

  27. What import capacity in MVA is evidenced?

    Not established from the public records reviewed.

  28. What electrical basis is stated for import capacity in MVA?

    Not established from the public records reviewed.

  29. Which phase and campus boundary does import capacity in MVA cover?

    Not established from the public records reviewed.

  30. What dated and quoted source supports the input Whole-campus facility demand?

    Each derivation input needs observed provenance.

  31. What dated and quoted source supports the input Added-development facility demand?

    Each derivation input needs observed provenance.

  32. What operator-published connection-to-energisation duration applies to this dated capacity stage?

    No applicable duration to energisation was established. An application-to-offer period is not a construction duration.

  33. Which upstream reinforcements are conditions of this demand connection, and what dated delivery programme applies?

    Not established from the public records reviewed.

  34. What published earliest completion year applies to energisationInputs.gridWorksPlanning.value?

    No bounded completion year is published.

  35. What published latest completion year applies to energisationInputs.gridWorksPlanning.value?

    No bounded completion year is published.

  36. Which current policy requirements apply to this application and agreement, and when could they be satisfied?

    Not established from the public records reviewed.

  37. What observed input establishes Complete current priced connection scope for capex.scopeCompleteness?

    The derivation has an unknown input and cannot establish a precise value.

  38. What dated and quoted source supports the input Complete current priced connection scope?

    Each derivation input needs observed provenance.

  39. Does the applicable planning or connection policy require behind-the-meter generation?

    Not established from the public records reviewed.

  40. What battery storage is evidenced for this connection?

    Not established from the public records reviewed.

  41. Does the applicable planning or connection policy require battery storage?

    Not established from the public records reviewed.

  42. What private wire is evidenced for this connection?

    Not established from the public records reviewed.

  43. Does the applicable planning or connection policy require private wire?

    Not established from the public records reviewed.

  44. What gas supply or generation is evidenced for this connection?

    Not established from the public records reviewed.

  45. Does the applicable planning or connection policy require gas supply or generation?

    Not established from the public records reviewed.

  46. Does the documented connection position comply with the policy applicable to its application date and agreement status?

    Not established from the public records reviewed.

  47. Obtain current operator evidence of applied, offered, accepted and energised import MVA for the same campus boundary.

    Research hand-off question.

  48. Confirm whether a later expansion or modification changes the policy regime applicable to the existing connection.

    Research hand-off question.

  49. Confirm the voltage wording in the accommodation letter: the inspector records 200 kV in that passage, while the scheme is described as 220 kV elsewhere.

    Research hand-off question.

  50. Identify current fault ride-through compliance evidence without assuming the 2018 planning permission demonstrates compliance.

    Research hand-off question.

  51. Separate network and customer costs, upstream reinforcement, land, wayleaves, fees, taxes, securities, contingency and price base.

    Connection-cost scope question.

  52. Verify the approved and built station topology, transformer ratings and customer/network boundary.

    Connection-cost scope question.

  53. Resolve whether the approximate 2.5 kilometres describes each cable, their common corridor or aggregate cable length.

    Connection-cost scope question.

  54. Obtain a published Irish construction comparator for the same 220 kV AIS configuration and price base.

    Connection-cost scope question.

  55. Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.

    This missing input leaves an energisation bound unknown.

  56. Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.

    This missing input leaves an energisation bound unknown.

  57. Resolve the energisation input: Connection-dependent reinforcement scope and completion dates

    This missing input leaves an energisation bound unknown.

  58. Resolve the energisation input: Earliest readiness for Clonee extension grid infrastructure consent.

    This missing input leaves an energisation bound unknown.

  59. Resolve the energisation input: A published upper readiness year for Clonee extension grid infrastructure consent.

    This missing input leaves an energisation bound unknown.

  60. Resolve the energisation input: Applicable connection-policy conditions and programme

    This missing input leaves an energisation bound unknown.

  61. Establish that every necessary connection-work component is included in the published scope.

    This scope or reference gap prevents a complete indicative connection capex band.

Use these questions to scope a Power Reality Check.

Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.

Request a Reality Check
Earlier capacity notes and source context

No project-specific capacity figure is published in this record.

Import rights and connection evidence

The applicant describes on-site Bracetown and Clonee 220 kV AIS infrastructure, ESB/EirGrid assets and separate customer transformers. Normal supply is grid electricity; backup generation ratings and the existing architect design rating do not establish a contracted import allowance.

IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.

Planning & utilities

6 of 10 categories contain evidence. Each status applies to its specific claim.

Planning & decisions

Partial evidence

EPA records Meath permissions RA/150605 and RA/180671, with appeal PL.245347 and substation cases PL17VA0018, ABP-301172-18 and ABP-301923-18. These are historical consent references for the operating campus; individual conditions and subsequent amendments remain unchecked.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Retrieve the council/ACP orders and map each permission to CLN1/2/3/5/6 and associated substations.

Grid & import rights

Partial evidence

The applicant describes on-site Bracetown and Clonee 220 kV AIS infrastructure, ESB/EirGrid assets and separate customer transformers. Normal supply is grid electricity; backup generation ratings and the existing architect design rating do not establish a contracted import allowance.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Match current supply agreements and asset boundaries to the two substations; obtain scoped import MVA/MW and rights-holder evidence.

Ownership & development control

Partial evidence

EPA names Runways Information Services Limited, CRO 553841, as the installation applicant/operator at Slí Na Cháirde, Portan. This identifies a regulated legal entity, not registered land title.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Reconcile the licence-holder with current property title and any group/lease interests.

Land, footprint & access

Partial evidence

The EPA inspector defines a 133.06 ha licence installation covering five buildings in Gunnocks, Portan, Loughsallagh and Clonee. This is gross installation extent, not vacant or developable land.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Retrieve the current licence boundary and cadastral titles; distinguish retained operational areas and access easements.

Flood, ground & environment

Partial evidence

Final licence P1192-01 was granted on 3 October 2023. Its cover states a Section 96 technical amendment dated 3 March 2026 must be read with it. Air, noise, stormwater and sewer controls apply, but the amendment and current compliance returns were not retrieved.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Retrieve Technical Amendment A and latest monitoring/compliance records before presenting a complete current condition set.

Water, cooling & heat

Partial evidence

The operational report distinguishes indirect-air cooling for CLN1/2/3 from Statepoint liquid cooling for CLN5/6, with wet/dry modes, mains-water supply and process drainage. It does not establish current spare water or wastewater capacity.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Check current water agreement, metered demand, sewer restrictions and licence-amendment conditions by building.

Not assessed

Land-use zoningFibre & dark fibreDemand & location fitProgramme & delivery
Evidence still needed
  • Land-use zoning

    The site boundary has not been matched to the current adopted zoning map and data-centre use policy.

  • Fibre & dark fibre

    No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.

  • Demand & location fit

    Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.

  • Programme & delivery

    Permission expiry, commencement, energisation, enabling works, long-lead procurement and phase handovers need a reconciled programme.

Project team

Appointments are limited to the project, phase and scope supported by each source.

Main contractor

Architect

Engineering consultant

AWN ConsultingOther projects

Environmental operational report for Runways P1192-01 application, February 2023; no main-contractor appointment inferred.

Appointment source

Specialists & vendors

J Coffey ConstructionOther projects

Phase 3 earthworks, foundations, drainage, ducting, watermain, slabs, precast units, roads and landscaping; portfolio also confirms phases 1–2.

Appointment source
Dornan EngineeringOther projects

Mechanical contractor on the original Clonee build, explicitly named by its rooftop-support-system supplier; not extended to every later phase.

Appointment source
Flexi Support Systems / DiversiTechOther projects

Supplied rooftop support frames and bespoke maintenance-access platforms for fourteen air-handling units on the original Clonee build.

Appointment source
Keane EnvironmentalOther projects

Supplied Kampmann trench heating and Hudevad panel radiators for reception, atrium and stairwell areas, working with Dornan and Cundall.

Appointment source

Unlisted roles have no project-specific appointment recorded.

Sources

Publication dates are shown where known. Review dates do not establish approval or commissioning.

  1. Meta: Clonee campus information sheetdatacenters.atmeta.com · Publication date unstated
  2. studioNWA: Facebook Clonee design and construction teamstudionwa.com · Publication date unstated
  3. Clancy: Facebook Clonee administration fit-outclancy.ie · Publication date unstated
  4. J Coffey: Clonee phase 3 packagejcoffey.com · Publication date unstated
  5. J Coffey: Clonee phases 5–6 and structural engineerjcoffey.com · Publication date unstated
  6. Flexi: Facebook Clonee AHU-support package and mechanical contractorflexisupportsystems.co.uk · Publication date unstated
  7. Keane Environmental: Facebook Clonee heating equipmentkeaneenvironmental.ie · Publication date unstated
  8. EPA: Runways Clonee P1192-01 inspector reportepawebapp.epa.ie · 24 Aug 2023
  9. EPA: P1192-01 final licence; cover notes Technical Amendment A of 3 March 2026leap.epa.ie · 3 Oct 2023