Meta’s first Irish data-centre campus, distinct from neighbouring EngineNode. Named delivery appointments are recorded by package and phase. The developer’s 219 MW renewable-energy figure covers generation…
Read overviewMeta Clonee campus
Clonee, County Meath, Ireland
Watch this site
Watch Meta Clonee campus
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
10 cited sources · 6 utility and planning categories reviewed.
Review evidence and gapsMatch current supply agreements and asset boundaries to the two substations; obtain scoped import MVA/MW and rights-holder evidence.
Open the full checkOverview
Meta’s first Irish data-centre campus, distinct from neighbouring EngineNode. Named delivery appointments are recorded by package and phase. The developer’s 219 MW renewable-energy figure covers generation projects and is not campus IT load or contracted import; an older architect’s 108 MVA design statement is not treated as a current connection agreement.
- Developer / applicant
- Meta (Facebook)
- Owner
- Not verified
- Operator
- Meta
Planning and delivery status
Meta’s current Clonee information sheet identifies operational data-centre buildings and operational jobs. Historical contractor portfolios evidence completed early phases; the status of every later phase is not implied.
Stage source: Publication date unstatedProject intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
Historical 2018 Clonee campus demand and related extension infrastructure, retained separately from current import rights.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. Evidence reviewed 19 October 2026.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied import MVA is evidenced for this campus or phase?Offered
Not established from the public records reviewed.
What offered import MVA is evidenced for this campus or phase?Accepted / contracted
Not established from the public records reviewed.
What accepted import MVA is evidenced for this campus or phase?Energised
Not established from the public records reviewed.
What energised import MVA is evidenced for this campus or phase?Conflicts and scope comparisons
180 MW campus and 72 MW addition have different scopes
Keep whole-campus and addition values separate; neither is a current import-MVA entitlement.
Historical whole-campus maximum electrical demand
- An Bord Pleanála, now An Coimisiún PleanálaPublished 15 November 2018 · Accessed 19 October 2026 · Source quotation
MW facility demand, whole 2018 campus
Added development maximum electrical demand
- An Bord Pleanála, now An Coimisiún PleanálaPublished 15 November 2018 · Accessed 19 October 2026 · Source quotation
MW facility demand, added development only
Resolution
Rule and inputs
Compare values only after electrical basis, date and development boundary match.
- Whole-campus facility demand
- 180 MW
- Added-development facility demand
- 72 MW
Ireland grid context
Network publications frame the claim. They do not allocate capacity to this site.
CRU/2025236: Large Energy Users Connection Policy decisionCommission for Regulation of Utilities · Source checked
Connection policy for new data centre applications, including matching dispatchable generation or storage, additional renewable electricity and network location assessment. At least 80% of annual demand must be met by additional renewable electricity generated in the Republic of Ireland, with a six-year glide path from energisation. Requirements and transitional scope must be checked against the actual application date and connection position.
A policy requirement is not evidence that a particular site has complied or has connection rights. Onsite or proximate generation is permitted; onsite-only generation is not a universal requirement. Do not retrospectively apply the new application rules to an earlier agreement without checking transitional scope. No fixed publisher update cadence is stated; PowerPlotr proposes a weekly policy check.
Commission for Regulation of Utilities: CRU/2025236: Large Energy Users Connection Policy decisionPublished 12 December 2025 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotationData Centre Connection Offer Process and Policy, Version 3EirGrid · Source checked
Implements CRU/2025236. For new transmission data centres at or above 10 MVA, nominated dispatchable generation or storage must match MIC after applicable de-rating and be delivered before energisation or demand ramp-up. Nominated generation is separately connected and metered and participates in the SEM. The stated offer-processing periods are approximately 7.5 calendar months where nominated generation and renewables already have offers, or up to 18 months where associated generation has newly applied through ECP-GSS.
These are conditional application-to-offer periods, not construction or energisation durations, and are excluded from energisation calculations. A complete application, linked generation status and fees matter. An offer is not an accepted agreement. Earlier applications can remain under CRU/21/124. Publisher updates are event-driven; proposed review is weekly.
EirGrid: Data Centre Connection Offer Process and Policy, Version 3Published 20 May 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotationData Centre Technical AssessmentEirGrid · Source checked
Explains application-specific assessment of capacity, voltage, system stability, short-circuit effects and outages. Continuous demand above 50 MW is significant for the Irish 110 kV network and should focus on connection voltages above 110 kV. Dedicated loop-in connections are difficult to integrate and require wider system benefit.
General technical context cannot establish a connection point, headroom or capacity allocation for a particular site. Every proposal still requires operator assessment. Publisher cadence is event-driven; proposed review is monthly and after a related policy decision.
EirGrid: Data Centre Technical AssessmentPublished 20 May 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 30 daysRead the source quotationData Centre Constrained Area OverviewEirGrid · Source checked
Pages 11 to 12 identify high-level potential on the 220 kV network around Galway, Limerick and Cork, subject to individual assessment and policy compliance. The overview considers greater Dublin fully constrained for new data centre development. It advises a prudent mid-2030s assumption for new connections in the identified areas because of work and outage programmes.
Regional opportunity is not site-specific capacity or a contractual right. Mid-2030s is qualitative operator context, not a bounded energisation window or a promised 2035 date. Earlier applications and agreements require their own transitional-policy check. Detailed heat maps are planned through the 2027 Ten Year Transmission Forecast Statement. No recurring publisher cadence is specified; proposed review is monthly.
EirGrid: Data Centre Constrained Area OverviewPublished 20 May 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 30 daysRead the source quotationCRU2026145: Grid Code Modification MPID 345 and Compliance and Derogation FrameworkCommission for Regulation of Utilities · Source checked
Approves fault ride-through, rate of change of frequency and active power recovery requirements for existing and future transmission-connected demand facilities. The technical requirements include remaining connected within the specified voltage profile, withstanding plus or minus 1 Hz/s and recovering 90% of pre-fault active power within 500 milliseconds after fault clearance and voltage recovery to 0.9 per unit. Compliance is assessed at the point of connection.
The associated Grid Code amendment takes effect on 27 October 2026. This is a separate technical requirement from the December 2025 connection policy. Site compliance, an approved derogation and any demand utilisation restriction need direct evidence. Missing public compliance evidence means unverified, not automatically non-compliant. Publisher updates are event-driven; proposed review is weekly.
Commission for Regulation of Utilities: CRU2026145: Grid Code Modification MPID 345 and Compliance and Derogation FrameworkPublished 22 September 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotationMPID 345 CRU approval letter and effective dateCommission for Regulation of Utilities, hosted by EirGrid · Source checked
The CRU directs EirGrid to amend the Grid Code five weeks after the 22 September 2026 decision. EirGrid's Grid Code Modifications register labels this approval effective 27 October 2026. The letter applies the technical requirements to all transmission-connected demand facilities.
The effective date does not itself prove compliance or an energisation entitlement at any site. Review the decision, current Grid Code and any approved derogation together. Publisher cadence is event-driven; proposed review is weekly through implementation.
Commission for Regulation of Utilities, hosted by EirGrid: MPID 345 CRU approval letter and effective datePublished 22 September 2026 · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotationTransmission Development Plan 2024 and regulatory publications registerEirGrid · Source checked
The checked regulatory publication register lists Transmission Development Plan 2024, the 2024 Ten-Year Transmission Forecast Statement and current adequacy publications. This is the discovery and version-control entry for the earlier published development plan while the 2026 to 2035 draft is under CRU consultation.
A listed project is not evidence that it supplies a particular site, has all consents, or guarantees a delivery date. No reinforcement dependency has been assigned to a pilot merely from geographic proximity. The statutory development-plan cycle is two years; PowerPlotr proposes monthly checks for a new approved version or delivery update.
EirGrid: Transmission Development Plan 2024 and regulatory publications registerPublished Unknown · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 30 daysRead the source quotationAn Coimisiún Pleanála case search and strategic infrastructure casesAn Coimisiún Pleanála · Source checked
Official search for appeals, direct strategic infrastructure applications and related cases, including grid works. The current authority is An Coimisiún Pleanála, formerly An Bord Pleanála. Search by case reference, location, applicant and infrastructure to match a site with grid planning decisions and conditions. Proposed review is weekly and whenever a relevant case changes.
A grid planning application, pre-application consultation or permission does not establish an executed connection agreement, import capacity, route rights or energisation. Check the actual decision documents and exact development boundary. A target decision date is not the decision. The portal has no guaranteed fixed case-update interval.
An Coimisiún Pleanála: An Coimisiún Pleanála case search and strategic infrastructure casesPublished Unknown · Accessed 19 October 2026 · Last checked 19 October 2026 · Review every 7 daysRead the source quotationCountry coverage: Ireland pilot. View all country sources and refresh schedules.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
- Clonee extension grid infrastructure consent: earliest readiness
- Unknown
Input evidence
- Clonee extension grid infrastructure consentAn Coimisiún Pleanála · Published 6 December 2018 · Accessed 19 October 2026 · Source quotation
- Clonee extension grid infrastructure consent: latest readiness
- Unknown
Input evidence
- Clonee extension grid infrastructure consentAn Coimisiún Pleanála · Published 6 December 2018 · Accessed 19 October 2026 · Source quotation
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Clonee extension grid infrastructure consent: Conditional planning consent signed 2018-12-06. This is a planning decision only; electrical completion years and current programme are unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Clonee extension grid infrastructure consent is ready by the earliest case, which has no published readiness date: Conditional planning consent signed 2018-12-06. This is a planning decision only; electrical completion years and current programme are unknown.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Earliest readiness for Clonee extension grid infrastructure consent.
- A published upper readiness year for Clonee extension grid infrastructure consent.
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Establish that every necessary connection-work component is included in the published scope.
- Separate network and customer costs, upstream reinforcement, land, wayleaves, fees, taxes, securities, contingency and price base.
- Verify the approved and built station topology, transformer ratings and customer/network boundary.
- Resolve whether the approximate 2.5 kilometres describes each cable, their common corridor or aggregate cable length.
- Obtain a published Irish construction comparator for the same 220 kV AIS configuration and price base.
Alternatives and policy exposure
Behind-the-meter generation
- An Bord Pleanála, now An Coimisiún PleanálaPublished 15 November 2018 · Accessed 19 October 2026 · Source quotation
Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced for this connection?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What private wire is evidenced for this connection?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced for this connection?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the documented connection position comply with the policy applicable to its application date and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
61 questions to resolve
- What are the verified site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- Does the 2018 description of two cables at approximately 2.5 kilometres mean route length per circuit or aggregate cable length, and what was built?
The report gives an approximate 2.5-kilometre cable description but does not resolve the measurement basis for a complete current connection route.
- What applied import MVA is evidenced for this campus or phase?
Not established from the public records reviewed.
- What is the effective date of the applied import-capacity evidence?
Not established from the public records reviewed.
- Which buildings and phases does the applied import capacity cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered import MVA is evidenced for this campus or phase?
Not established from the public records reviewed.
- What is the effective date of the offered import-capacity evidence?
Not established from the public records reviewed.
- Which buildings and phases does the offered import capacity cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted import MVA is evidenced for this campus or phase?
Not established from the public records reviewed.
- What is the effective date of the accepted import-capacity evidence?
Not established from the public records reviewed.
- Which buildings and phases does the accepted import capacity cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised import MVA is evidenced for this campus or phase?
Not established from the public records reviewed.
- What is the effective date of the energised import-capacity evidence?
Not established from the public records reviewed.
- Which buildings and phases does the energised import capacity cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What phased import limits apply?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What generation or storage obligations apply to this agreement?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection milestones or longstop dates apply?
Not established from the public records reviewed.
- What IT load in MW is evidenced?
Not established from the public records reviewed.
- What electrical basis is stated for IT load in MW?
Not established from the public records reviewed.
- Which phase and campus boundary does IT load in MW cover?
Not established from the public records reviewed.
- What import capacity in MVA is evidenced?
Not established from the public records reviewed.
- What electrical basis is stated for import capacity in MVA?
Not established from the public records reviewed.
- Which phase and campus boundary does import capacity in MVA cover?
Not established from the public records reviewed.
- What dated and quoted source supports the input Whole-campus facility demand?
Each derivation input needs observed provenance.
- What dated and quoted source supports the input Added-development facility demand?
Each derivation input needs observed provenance.
- What operator-published connection-to-energisation duration applies to this dated capacity stage?
No applicable duration to energisation was established. An application-to-offer period is not a construction duration.
- Which upstream reinforcements are conditions of this demand connection, and what dated delivery programme applies?
Not established from the public records reviewed.
- What published earliest completion year applies to energisationInputs.gridWorksPlanning.value?
No bounded completion year is published.
- What published latest completion year applies to energisationInputs.gridWorksPlanning.value?
No bounded completion year is published.
- Which current policy requirements apply to this application and agreement, and when could they be satisfied?
Not established from the public records reviewed.
- What observed input establishes Complete current priced connection scope for capex.scopeCompleteness?
The derivation has an unknown input and cannot establish a precise value.
- What dated and quoted source supports the input Complete current priced connection scope?
Each derivation input needs observed provenance.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced for this connection?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What private wire is evidenced for this connection?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced for this connection?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the documented connection position comply with the policy applicable to its application date and agreement status?
Not established from the public records reviewed.
- Obtain current operator evidence of applied, offered, accepted and energised import MVA for the same campus boundary.
Research hand-off question.
- Confirm whether a later expansion or modification changes the policy regime applicable to the existing connection.
Research hand-off question.
- Confirm the voltage wording in the accommodation letter: the inspector records 200 kV in that passage, while the scheme is described as 220 kV elsewhere.
Research hand-off question.
- Identify current fault ride-through compliance evidence without assuming the 2018 planning permission demonstrates compliance.
Research hand-off question.
- Separate network and customer costs, upstream reinforcement, land, wayleaves, fees, taxes, securities, contingency and price base.
Connection-cost scope question.
- Verify the approved and built station topology, transformer ratings and customer/network boundary.
Connection-cost scope question.
- Resolve whether the approximate 2.5 kilometres describes each cable, their common corridor or aggregate cable length.
Connection-cost scope question.
- Obtain a published Irish construction comparator for the same 220 kV AIS configuration and price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Earliest readiness for Clonee extension grid infrastructure consent.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: A published upper readiness year for Clonee extension grid infrastructure consent.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
No project-specific capacity figure is published in this record.
The applicant describes on-site Bracetown and Clonee 220 kV AIS infrastructure, ESB/EirGrid assets and separate customer transformers. Normal supply is grid electricity; backup generation ratings and the existing architect design rating do not establish a contracted import allowance.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
6 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceEPA records Meath permissions RA/150605 and RA/180671, with appeal PL.245347 and substation cases PL17VA0018, ABP-301172-18 and ABP-301923-18. These are historical consent references for the operating campus; individual conditions and subsequent amendments remain unchecked.
Sources & next check
Grid & import rights
Partial evidenceThe applicant describes on-site Bracetown and Clonee 220 kV AIS infrastructure, ESB/EirGrid assets and separate customer transformers. Normal supply is grid electricity; backup generation ratings and the existing architect design rating do not establish a contracted import allowance.
Sources & next check
Ownership & development control
Partial evidenceEPA names Runways Information Services Limited, CRO 553841, as the installation applicant/operator at Slí Na Cháirde, Portan. This identifies a regulated legal entity, not registered land title.
Sources & next check
Land, footprint & access
Partial evidenceThe EPA inspector defines a 133.06 ha licence installation covering five buildings in Gunnocks, Portan, Loughsallagh and Clonee. This is gross installation extent, not vacant or developable land.
Sources & next check
Flood, ground & environment
Partial evidenceFinal licence P1192-01 was granted on 3 October 2023. Its cover states a Section 96 technical amendment dated 3 March 2026 must be read with it. Air, noise, stormwater and sewer controls apply, but the amendment and current compliance returns were not retrieved.
Sources & next check
Water, cooling & heat
Partial evidenceThe operational report distinguishes indirect-air cooling for CLN1/2/3 from Statepoint liquid cooling for CLN5/6, with wet/dry modes, mains-water supply and process drainage. It does not establish current spare water or wastewater capacity.
Sources & next check
Not assessed
Evidence still needed
- Land-use zoning
The site boundary has not been matched to the current adopted zoning map and data-centre use policy.
- Fibre & dark fibre
No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.
- Demand & location fit
Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.
- Programme & delivery
Permission expiry, commencement, energisation, enabling works, long-lead procurement and phase handovers need a reconciled programme.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Main contractor
Main contractor for Clonee phases 1–3, named as MACE International in studioNWA’s portfolio.
Appointment sourceArchitect
Contractor’s architect for CLN1, CLN2 and CLN3; portfolio records RIBA Stage 7 in 2017, 2018 and 2019.
Appointment sourceEngineering consultant
Contractor’s mechanical, electrical, civil and structural engineer for the Clonee phases described by studioNWA.
Appointment sourceStructural engineer for Clonee phases 5–6, identified as “Arups” in J Coffey’s phase-specific portfolio.
Appointment sourceEnvironmental operational report for Runways P1192-01 application, February 2023; no main-contractor appointment inferred.
Appointment sourceSpecialists & vendors
Fit-out of the 6,424 m² administration building linking the data-centre buildings, under Mace.
Appointment sourcePhase 3 earthworks, foundations, drainage, ducting, watermain, slabs, precast units, roads and landscaping; portfolio also confirms phases 1–2.
Appointment sourceMechanical contractor on the original Clonee build, explicitly named by its rooftop-support-system supplier; not extended to every later phase.
Appointment sourceSupplied rooftop support frames and bespoke maintenance-access platforms for fourteen air-handling units on the original Clonee build.
Appointment sourceSupplied Kampmann trench heating and Hudevad panel radiators for reception, atrium and stairwell areas, working with Dornan and Cundall.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- Meta: Clonee campus information sheetdatacenters.atmeta.com · Publication date unstated
- studioNWA: Facebook Clonee design and construction teamstudionwa.com · Publication date unstated
- Clancy: Facebook Clonee administration fit-outclancy.ie · Publication date unstated
- J Coffey: Clonee phase 3 packagejcoffey.com · Publication date unstated
- J Coffey: Clonee phases 5–6 and structural engineerjcoffey.com · Publication date unstated
- Flexi: Facebook Clonee AHU-support package and mechanical contractorflexisupportsystems.co.uk · Publication date unstated
- Keane Environmental: Facebook Clonee heating equipmentkeaneenvironmental.ie · Publication date unstated
- EPA: Runways Clonee P1192-01 inspector reportepawebapp.epa.ie · 24 Aug 2023
- EPA: P1192-01 final licence; cover notes Technical Amendment A of 3 March 2026leap.epa.ie · 3 Oct 2023
- AWN Consulting: Clonee operational report for Runways, EPA applicationepawebapp.epa.ie · 13 Feb 2023
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.