Six data-centre buildings in a 39 ha campus within a wider 243 ha application. The form identifies Castlelost Flex Gen Limited and acquisition options on adjoining land; freehold ownership of the complete…
Read overviewRed Admiral — Rochfortbridge campus
Rochfortbridge, Co. Westmeath, Ireland
Watch this site
Watch Red Admiral — Rochfortbridge campus
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
8 cited sources · 5 utility and planning categories reviewed.
Review evidence and gapsMonitor campus appeal ACP501596 and separate GIS application ACP324417 independently. Verify final decisions, conditions and commencement; council support does not establish ACP permission or a grid import…
Open the full checkOverview
Six data-centre buildings in a 39 ha campus within a wider 243 ha application. The form identifies Castlelost Flex Gen Limited and acquisition options on adjoining land; freehold ownership of the complete campus is unverified. Proposed local generation/storage and proximity to Castlelost 220 kV do not establish contracted import capacity. The applicant’s June 2026 EIAR proposes fresh-air cooling with electric and absorption chillers in hot conditions, and a 40 m³/day maximum water-demand envelope. These are design assumptions, not verified utility or abstraction entitlements.
- Developer / applicant
- Red Admiral DC Limited / Lumcloon Energy
- Owner
- Not verified
- Operator
- Not verified
Planning and delivery status
Council application 2560344 remains under appeal in ACP501596, lodged 23 June 2026 and due 27 October 2026 at the 4 October review. Separate 220 kV GIS application ACP324417 was lodged 3 July 2026. Westmeath County Council recommended GIS approval on 18 September, subject to ACP environmental determinations and conditions; this is not ACP permission. Neither case displays a final ACP decision at review. Construction has not been verified.
Stage source: 23 Jun 2026Project intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
Ireland grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Country coverage: Ireland pilot. View all country sources and refresh schedules.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Full campus load scenario in June 2026 EIAR; not a contracted grid import or IT capacity. No independent connection-agreement verification.
Published claimProject source recordIT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
5 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceCouncil application 2560344 remains under appeal in ACP501596, lodged 23 June 2026 and due 27 October 2026 at the 4 October review. Separate 220 kV GIS application ACP324417 was lodged 3 July 2026. Westmeath County Council recommended GIS approval on 18 September, subject to ACP environmental determinations and conditions; this is not ACP permission. Neither case displays a final ACP decision at review. Construction has not been verified.
Sources & next check
Ownership & development control
Partial evidenceJuly 2026 SID form identifies Castlelost Flex Gen Limited, landowner consents and options on adjoining land. Full-campus freehold ownership and option completion are not verified.
Sources & next check
Land, footprint & access
DocumentedDeveloper describes six buildings inside a 39 ha data-centre campus, each 13,978 m² footprint and 28,561 m² gross floor area. The wider EIAR red line is 243 ha; that total is not net data-centre land.
Sources & next check
Flood, ground & environment
Partial evidenceThe Department’s 21 August 2026 observations identify six recorded monuments within the assessed development site and ACSU Ltd’s June 2026 archaeological assessment. They recommend advance archaeological testing and an agreed report before site preparation or groundworks, with preservation measures as required. The six-monument count relates to the assessed development site, not a verified count within the 39 ha data-centre campus. These are recommended conditions, not evidence of completed investigations or ACP permission.
Sources & next check
Water, cooling & heat
Partial evidenceApplicant’s consolidated EIAR NTS dated 26 June 2026 proposes fresh-air cooling and air-handling units, supplemented by electric and absorption chillers at high ambient temperatures, without evaporative cooling. It sets a maximum water-demand envelope of 40 m³/day: three proposed wells, with up to 10 m³/day from the public network following Uisce Éireann feasibility confirmation and approximately 30 m³/day groundwater abstraction. These are the wider campus/DER design assumptions, not verified operating consumption, an abstraction entitlement or a signed utility agreement.
Sources & next check
Not assessed
Evidence still needed
- Land-use zoning
The site boundary has not been matched to the current adopted zoning map and data-centre use policy.
- Grid & import rights
Site-specific import rights, available MVA, connection milestones and any transfer restrictions remain unverified.
- Fibre & dark fibre
No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.
- Demand & location fit
Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.
- Programme & delivery
Permission expiry, commencement, energisation, enabling works, long-lead procurement and phase handovers need a reconciled programme.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Specialists & vendors
Planning agent for ACP324417, identified in Westmeath County Council’s 18 September 2026 submission; also prepared the June 2026 consolidated EIAR. No construction contract implied.
Appointment sourcePrepared the archaeological impact assessment in the June 2026 EIAR, as identified by the Department of Housing, Local Government and Heritage on 21 August 2026.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- ACP — live Red Admiral appeal 501596pleanala.ie · Publication date unstated
- ACP — 220 kV GIS application 324417pleanala.ie · Publication date unstated
- Red Admiral — developer project overviewlumcloonenergy.com · Publication date unstated
- Red Admiral — consolidated June 2026 EIAR nontechnical summarypleanala.ie · 26 Jun 2026
- Red Admiral — July 2026 site legal-interest formpleanala.ie · 3 Jul 2026
- Westmeath County Council — Red Admiral GIS submission and recommendationpleanala.ie · 18 Sept 2026
- Department of Housing, Local Government and Heritage — archaeology observationspleanala.ie · 21 Aug 2026
- Red Admiral — response to prescribed-body submissionspleanala.ie · 18 Sept 2026
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.