Operating former Legler textile campus including DC-A/B/C. Municipal records add parcel-use, river-edge flood constraints and historic soil-investigation conditions; those historic concerns are not evidence of…
Read overviewAruba Global Cloud Data Center — IT3
Ponte San Pietro, Bergamo, Italy
Watch this site
Watch Aruba Global Cloud Data Center — IT3
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
6 cited sources · 10 utility and planning categories reviewed.
Review evidence and gapsObtain current grid contracts, commissioned IT capacity and building allocation; retain photovoltaic output separately.
Open the full checkOverview
Operating former Legler textile campus including DC-A/B/C. Municipal records add parcel-use, river-edge flood constraints and historic soil-investigation conditions; those historic concerns are not evidence of a current breach.
- Developer / applicant
- Aruba
- Owner
- Aruba — operator states company ownership; 2019 municipal/ARPA record identifies Aruba S.p.A. at the former Legler site. Current cadastral title not checked.
- Operator
- Aruba
Planning and delivery status
The active operator listing describes 45 MW achievable IT capacity and 60 MW total power; neither is proof of spare grid import. Historical planning and environmental records describe the former Legler redevelopment and require current-condition follow-up.
Stage source: Publication date unstatedProject intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
Italy grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Achievable full-campus IT power, not proof that all capacity is fitted out or occupied.
Published claimProject source recordAruba markets 45 MW achievable IT capacity and 60 MW total power for IT3. These are different electrical scopes and do not establish a current secured, spare or transferable grid import right.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
10 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceThe municipal PGT scoping report, section 7.5.1, records a former Legler redevelopment variation approved by council decision 22 of 9 July 2019, following decision 20 of 20 April 2016. It describes a technology/production campus in three intervention units.
Sources & next check
Land-use zoning
Partial evidenceThe 2019 ARPA record identifies ATS2 mixed production, tertiary and service uses and industrial acoustic class V. The municipal account includes industrial heritage, riverside green continuity and public access/setback obligations.
Sources & next check
Grid & import rights
Partial evidenceAruba markets 45 MW achievable IT capacity and 60 MW total power for IT3. These are different electrical scopes and do not establish a current secured, spare or transferable grid import right.
Sources & next check
Fibre & dark fibre
Partial evidenceAruba describes two opposite-side main distribution areas and dual transmission to MIX. This supports campus topology and interconnection provision; carrier presence does not prove physically independent external ducts.
Sources & next check
Ownership & development control
Partial evidenceARPA's historical municipal-file response identifies Aruba S.p.A. at the former Legler property, supplementing Aruba's company-ownership statement. Neither is a current cadastral title extract.
Sources & next check
Land, footprint & access
Partial evidenceThe operator states 200,000 m² gross campus area. Municipal records describe redevelopment units and retained industrial heritage along the Brembo river; this is not unrestricted developable land.
Sources & next check
Flood, ground & environment
Partial evidenceThe 2019 ARPA review records river-edge PAI/PGRA flood overlaps and geological classes 2/3/4. Soil results met industrial thresholds but exceeded some residential/green-space thresholds; ARPA questioned sample locations and noted groundwater was not investigated in the submitted report. These are historical review findings, not proof of a current breach.
Sources & next check
Water, cooling & heat
DocumentedAruba specifies a groundwater primary circuit, 2N heat-exchanger secondary arrangement and emergency air/water chillers. This is a defined cooling configuration, without independently verified abstraction entitlement or measured water performance.
Sources & next check
Demand & location fit
Partial evidenceAruba's current listing markets an operating multi-building cloud and colocation campus. The 45 MW achievable figure is not an occupancy or contracted-demand measure.
Sources & next check
Programme & delivery
DocumentedBaraclit's dated December 2022 case identifies DC-C construction and photovoltaic design/installation on three buildings and the auditorium. This supports that package, not a general-contractor appointment across every campus phase.
Sources & next check
Project team
Appointments are limited to the project, phase and scope supported by each source.
Specialists & vendors
Constructed DC-C and designed/installed photovoltaic systems on three buildings and the auditorium. Scope does not establish general contractor for the entire campus.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- Aruba — IT3 Bergamo campus and achievable capacitydatacenter.it · Publication date unstated
- Aruba — ownership of Italian data-centre networkaruba.it · Publication date unstated
- Baraclit — construction of Aruba DC-C and photovoltaic packagebaraclit.it · 6 Dec 2022
- Aruba — IT3 campus technical specificationsdatacenter.it · Publication date unstated
- Municipality — ARPA response on former Legler site, receipt 7 March 2019comune.pontesanpietro.bg.it · 7 Mar 2019
- Municipality — PGT scoping report, section 7.5.1comune.pontesanpietro.bg.it · Publication date unstated
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.
