Operating Nebius-hosting campus with traced phase-one delivery and consultant team. Contractor 16.8 MW phase-one and consultant 54 MW two-building design scopes are separate from unverified utility import.
Read overviewArk Longcross Park
Chertsey, Surrey, United Kingdom
Watch this site
Watch Ark Longcross Park
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
7 cited sources · 7 utility and planning categories reviewed.
Review evidence and gapsRetrieve RU.13/0856 and RU.21/0780 signed decisions, approved Ark red lines and discharge records; check subsequent variations and distinguish the data-centre parcel from the wider Garden Village.
Open the full checkOverview
Operating Nebius-hosting campus with traced phase-one delivery and consultant team. Contractor 16.8 MW phase-one and consultant 54 MW two-building design scopes are separate from unverified utility import.
- Developer / applicant
- Ark Data Centres
- Owner
- Not verified
- Operator
- Ark Data Centres
Planning and delivery status
Ark’s February 2026 update describes delivery and commissioning of Nebius AI infrastructure at Longcross.
Stage source: 16 Feb 2026Project intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
United Kingdom grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Country coverage: prepared sources; site-level research not extended. View all country sources and refresh schedules.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Sweet Projects' phase-one case-study rating; MW basis is unspecified and not treated as IT power or utility import.
Published claimCapacity sourceStantec describes compute capacity across two centres; exact rating basis, current commissioned extent and utility import remain unverified.
Published claimCapacity sourceIT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
7 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceRunnymede's 2021 Longcross SLAA appendix links the wider Garden Village allocation to Policy SD9 and permission RU.13/0856, including 36,000 m² of sui-generis data-centre use. A July 2023 sequential test submitted by another applicant describes Longcross's RU.21/0780 reserved matters as approved/under construction. This is corroborating planning history, not the actual Ark decision notice or authority for all later expansion.
Sources & next check
Land-use zoning
Partial evidenceThe council's SLAA appendix identifies Policy SD9's wider Longcross Garden Village allocation, including a specific data-centre-use component. The whole allocation's mixed-use scope and area must not be applied to the Ark parcel or treated as current unrestricted development capacity.
Sources & next check
Land, footprint & access
Partial evidenceThe July 2023 sequential test treats the wider 17.7 ha Longcross Park comparator as sold to Ark, committed and unavailable for that applicant's alternatives assessment. This is not verified title or Ark's exact parcel area. Sweet Projects describes restricted phase-one logistics, off-site staff parking and road/service works. The operating development is not an off-market available land opportunity.
Sources & next check
Flood, ground & environment
Partial evidenceThe 2023 submitted sequential test records no Flood Zone 2/3 coverage for the wider Longcross Park comparator. Sweet Projects identifies noise-sensitive residential/commercial neighbours and constrained logistics. Neither source establishes building-level surface-water safety, contamination clearance or current acoustic compliance.
Sources & next check
Water, cooling & heat
DocumentedArk's February 2026 update describes the commissioned Nebius Blackwell deployment using an air-cooled configuration. Stantec's wider Longcross design account describes BladeRoom direct-air technology and broader air/liquid capability; that does not change the configuration of the named deployed customer or prove liquid cooling in every hall.
Sources & next check
Demand & location fit
DocumentedArk identifies delivery and commissioning of Nebius AI infrastructure at Longcross in February 2026. Nebius' June 2025 digest, published 8 July 2025, identifies its UK cloud deployment at Longcross for enterprise, research and public-sector uses. These are named customer/location evidence, but neither establishes occupied/contracted MW or spare capacity.
Sources & next check
Programme & delivery
DocumentedSweet Projects identifies itself as phase-one principal contractor for enabling, Stage 4/5 design, construction and associated energy-centre/services/road works, describing 2023–2025, 90 weeks and 16.8 MW with no clear rating basis. Stantec describes a two-centre 54 MW compute-capacity design scope and names Sweet and Hale Architects. These are different scopes; neither proves 54 MW commissioned or a utility import entitlement.
Sources & next check
Not assessed
Evidence still needed
- Grid & import rights
Site-specific import rights, available MVA, connection milestones and any transfer restrictions remain unverified.
- Fibre & dark fibre
No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.
- Ownership & development control
Legal title, land-owning entity, development-control route and restrictions need verification. A named developer does not establish availability.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Main contractor
Longcross phase-one principal contractor: enabling, Stage 4/5 design, construction, energy centre, ancillary services, gantry and roads; case study gives 2023–2025 and 90 weeks.
Appointment sourceArchitect
Architect named in Stantec's Longcross project team; exact building/phase appointment has not been separately established.
Appointment sourceEngineering consultant
Multidisciplinary design and construction support, including substructure optimisation and EV infrastructure; consultant page describes a two-centre design scope.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- Ark Longcross Park facilityark-d-c.com · Publication date unstated
- Ark 2026 update: Longcross Nebius deploymentark-d-c.com · 16 Feb 2026
- Sweet Projects: Longcross phase-one principal contractor and scopesweet-projects.com · Publication date unstated
- Stantec: Longcross design and construction support, team and campus scopestantec.com · Publication date unstated
- Runnymede: 2021 SLAA Longcross appendix and Policy SD9 development scoperunnymede.gov.uk · Publication date unstated
- Be First: July 2023 sequential test filed with Runnymede, Longcross comparator and RU.21/0780runnymede.gov.uk · Publication date unstated
- Nebius: June 2025 digest identifies Longcross UK cloud deploymentnebius.com · 8 Jul 2025
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.