Owner-led land and zoning signal. Kilkenny’s December 2025 report records Ballagh Holdings’ Mullinabro masterplan and data-centre utility assessments (KK-C330-65). Variation 6 was adopted on 23 March 2026.…
Read the full contextMullinabro lands — Ballagh Holdings
Mullinabro, Ferrybank / South Kilkenny, northern edge of Waterford urban area, Ireland
Watch this site
Watch Mullinabro lands — Ballagh Holdings
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
Public marketing found. 10 cited sources.
Review power evidenceMatch consultant-cited folios KK11641 and KK37926F to current title, the adopted zoning and campus boundary. Establish Ballagh’s exact legal identity and Echelon relationship, then obtain current operator…
Open the full actionOpen issues
Public owner-direct campus promotion prevents treating this as a new off-market discovery; statutory consultation alone is not marketing. Reconcile the 63.6 ha submission, 70.83 ha across two consultant-cited folios, 87.5 ha traffic-study area, 37 ha western feasibility scope and later 76.75 ha promotion. BETP permits data-centre uses in principle, but the exact adopted-zone overlay, project consent, land control, import capacity and usable footprint remain unresolved.
Overview
Owner-led land and zoning signal. Kilkenny’s December 2025 report records Ballagh Holdings’ Mullinabro masterplan and data-centre utility assessments (KK-C330-65). Variation 6 was adopted on 23 March 2026. This lead was identified following a user tip, then corroborated with public records.
Next action
Match consultant-cited folios KK11641 and KK37926F to current title, the adopted zoning and campus boundary. Establish Ballagh’s exact legal identity and Echelon relationship, then obtain current operator feasibility and application evidence before assigning MVA or preparing controlling terms. Check the separate Great Island–Belview development permission and delivery status; maritime consent alone does not authorise construction. No contact or purchase has been made.
Research only. Independent development control and an actionable off-market opportunity have not been established.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
Ireland grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Country coverage: Ireland pilot. View all country sources and refresh schedules.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier power notes and source context
CSEA’s desktop assessment identifies Waterford 110 kV and Cullenagh 220 kV, plus crossing overhead lines; it establishes no import MVA, demand offer or energisation date for this parcel. ESB’s December 2025 DNDP lists Mount Misery as 38 kV, superseding CSD’s conflicting 110 kV description. The actual Great Island–Belview maritime consent MAC240021, commencing 25 September 2025, was reviewed on 29 September 2026. It expressly excludes planning permission and requires further authorisations before works. This is regional context, not proof of a connection to Mullinabro, available import capacity or energisation.
Demand MVA not published. No site demand MVA or operator-confirmed headroom is published. ESB lists Mount Misery as 38 kV; the submission also names wider 110/220 kV infrastructure. Voltage, regional reinforcement and nearby generation do not establish parcel capacity.
Historic generation and industrial use do not establish transferable demand rights. Published capacities retain their original units and scope.
Opportunity Score · Withheld: assessment incomplete
A sourced scenario assessment has not passed every gate. Existing record evidence is retained; missing assessments are not scored as zero.
- Power (30%): Not assessed
No sourced scenario assessment recorded.
Source references: Not supplied - Land (20%): Not assessed
No sourced scenario assessment recorded.
Source references: Not supplied - Fibre (15%): Not assessed
No sourced scenario assessment recorded.
Source references: Not supplied - Planning (20%): Not assessed
No sourced scenario assessment recorded.
Source references: Not supplied - Demand (15%): Not assessed
No sourced scenario assessment recorded.
Source references: Not supplied
Source references are supplied by the analyst. IDs are not resolved or verified by this display; their evidence and relevance still require review.
Why the score is withheld
- power: assessment missing or invalid
- power: explanation and source IDs required
- land: assessment missing or invalid
- land: explanation and source IDs required
- fibre: assessment missing or invalid
- fibre: explanation and source IDs required
- planning: assessment missing or invalid
- planning: explanation and source IDs required
- demand: assessment missing or invalid
- demand: explanation and source IDs required
- control gate: unknown
- import gate: unknown
- planning gate: unknown
- marketing gate: blocked
- Power class D or unverified: score withheld
Land control, import rights, planning and marketing must each be at least partially evidenced for the scenario. A named owner, a planning record or nearby infrastructure does not by itself pass these gates.
Power class D: no score is issued. Only Category A, B or an evidenced strong C route can be assessed.
Public marketing is recorded. This is not an off-market opportunity.
Scenario fit is an analyst assessment, not a probability, qualification, investment recommendation or proof of financeability. Partial gates still require diligence.
Read the scoring methodLand control
- Identified owner / counterparty
- Legal landowner not verified
Ballagh Holdings Ltd, described in its September 2025 submission as a Limetree Global entity, asserts ownership. Public promotion was observed in the earlier review; the personal-profile source is withheld. This prevents an off-market claim but is not evidence of current title or a disposal mandate. Echelon’s August 2025 support letter indicates developer alignment; legal title, exclusivity and available independent development or operating control are not established. Personal ownership by the Geary brothers is not verified.
Planning & utilities
4 of 10 categories contain evidence. Status applies to the specific claim, not the whole site.
Land-use zoning
Partial evidenceKilkenny adopted the Ferrybank–Belview framework through Variation 6 on 23 March 2026. The June 2026 final BETP matrix permits Data Centre and Energy Park uses. The proposed Mullinabro site boundary has not been matched to the adopted map, so BETP status and permission for this parcel remain unverified.
Sources & next check
Fibre & dark fibre
Partial evidenceEnet lists Waterford as a MAN town and ESB Telecoms lists Gracedieu, Waterford co-location. These are regional leads only. The Mullinabro planning-policy submission discusses infrastructure suitability but no site fibre entry, contracted service or diverse route was verified.
Sources & next check
Ownership & development control
Partial evidenceBallagh Holdings asserts ownership in its submission. Echelon’s August 2025 support letter expresses development interest; it does not establish legal title, an exclusive option or a binding operating agreement.
Sources & next check
Land, footprint & access
Partial evidenceSubmission scopes conflict: JSA cites 63.6 ha; consultant folio areas KK11641 and KK37926F total 70.83 ha; the traffic study covers about 87.5 ha. CSEA’s western study is about 37 ha with 28 ha proposed building area. None is a reconciled net campus footprint.
Sources & next check
Not assessed
Evidence still needed
- Planning & decisions
A current planning decision, conditions and any appeal or court proceedings still need to be checked.
- Grid & import rights
Site-specific import rights, available MVA, connection milestones and any transfer restrictions remain unverified.
- Flood, ground & environment
Flood risk, ground conditions, contamination, ecology, heritage, noise and air-quality constraints have not been fully assessed here.
- Water, cooling & heat
Water availability and discharge, cooling technology, peak demand, heat reuse and utility agreements remain to be verified.
- Demand & location fit
Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.
- Programme & delivery
Permission expiry, commencement, energisation, enabling works, long-lead procurement and phase handovers need a reconciled programme.
Project team
Each appointment retains its evidenced planning, feasibility or construction scope.
Planning consultant
September 2025 planning and zoning submission; not evidence of project permission.
Architect
Draft masterplan included with the zoning submission; detailed data-centre design appointment not established.
Engineering consultant
Data-centre infrastructure and utility feasibility; not grid-operator approval.
Civil infrastructure assessment, May 2024; construction-stage appointment not established.
Utilities assessment through Frank Fox, May 2024. Its Mount Misery 110 kV statement conflicts with later ESB 38 kV evidence.
Roads and traffic assessment through Frank Fox, March 2024.
Property consultant
Land-use and market justification; no cost-consultant or construction appointment inferred.
Unlisted roles have no project-specific appointment recorded.
Sources
Publication dates remain as supplied in the source title or note. A review date does not establish a permission, transaction or connection date.
- Ballagh / John Spain Associates — September 2025 submission, CSEA feasibility and Echelon letterconsult.kilkenny.ie
- Kilkenny County Council — December 2025 chief executive report, submission KK-C330-65kilkennycoco.ie
- Kilkenny County Council — Variation 6 adopted 23 March 2026kilkennycoco.ie
- Kilkenny County Council — June 2026 adopted framework, zoning and infrastructurekilkennycoco.ie
- ESB Networks — DNDP Part 2, revised December 2025, p51: Mount Misery 38 kVmedia.esbnetworks.ie
- MARA — actual MAC240021 consent, 25 September 2025; expressly not development/planning permissionmaritimeregulator.ie
- MARA — July 2025 assessment MAC240021, p3: constrained 38 kV crossings and regional feeder proposalmaritimeregulator.ie
- Enet — Metropolitan Area Networks and access documentsenet.ie · Publication date unstated
- ESB Telecoms — fibre map and co-location sitesesb.ie · Publication date unstated
- Ferrybank–Belview adopted zoning map, Variation 6kilkennycoco.ie · Publication date unstated
Original documents and imagery retain their rights. Linking does not grant commercial redistribution rights.