Bounded, developer-led reuse proposal at the former Wertachtal transmitter. Public evidence supports a pre-planning concept and historical consortium control of the broader conversion area, but not a completed…
Read overviewPolarise Amberg AI Factory — Wertachtal
Former Wertachtal transmitter, Amberg, Unterallgäu, Bavaria, Germany
Watch this site
Watch Polarise Amberg AI Factory — Wertachtal
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
6 cited sources · 5 utility and planning categories reviewed.
Review evidence and gapsIdentify the DSO and exact connection node/voltage, then obtain the application, connection offer/agreement, staged firm/flexible import and energisation terms. Keep generation, BESS, equipment, historical…
Open the full checkOverview
Bounded, developer-led reuse proposal at the former Wertachtal transmitter. Public evidence supports a pre-planning concept and historical consortium control of the broader conversion area, but not a completed Polarise acquisition, exact parcel title, planning application, grid import right, physical fibre route or named customer. The 69.5/70 MWp solar park, planned wind and BESS are generation/storage context and do not establish continuous data-centre import. This is market intelligence, not off-market land.
- Developer / applicant
- Polarise
- Owner
- Stadtwerke Bad Vilbel and Bürgerstiftung Bad Vilbel (historical conversion-area consortium and proposed seller; exact current data-centre parcel title and transfer unverified)
- Operator
- Polarise (intended)
Planning and delivery status
Pre-planning, not a submitted or permitted data centre. On 13 March 2026 the mayor described only an oral request and said implementation/urban-development agreements must precede a land-use-plan amendment and project-specific development plan. The current municipal planning page does not list a Wertachtal data-centre procedure. Mid-2027 remains a promoter target, not a permission, construction start or energisation date.
Stage source: 13 Mar 2026Project intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
Germany grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Polarise's updated initial campus plan announced on 18 August 2026. It is not verified IT load, utility import entitlement or commissioned capacity.
Published claimCapacity sourceOriginal 10 March 2026 promoter plan, superseded by the later 65 MW initial plan; not import or operating IT load.
Published claimCapacity sourcePromoter's potential ultimate scale inclusive of the initial phase; not additional capacity or secured import.
Published claimCapacity sourcePolarise's current initial 65 MW and ultimate 120 MW figures have unspecified electrical scope. The 69.5/70 MWp existing solar park, proposed additional photovoltaic capacity, planned wind, BESS and CHP are generation/storage context only. No site-specific DSO connection offer, import right, node, voltage, route or firm/flexible terms were found in this review.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
5 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceThe mayor reported an oral request on 13 March 2026 and said implementation/urban-development agreements must precede a land-use-plan amendment and project-specific development plan. No Wertachtal data-centre procedure appears on the municipality's current published planning page; this does not prove that no unpublished or later step exists.
Sources & next check
Grid & import rights
UnverifiedPolarise's current initial 65 MW and ultimate 120 MW figures have unspecified electrical scope. The 69.5/70 MWp existing solar park, proposed additional photovoltaic capacity, planned wind, BESS and CHP are generation/storage context only. No site-specific DSO connection offer, import right, node, voltage, route or firm/flexible terms were found in this review.
Sources & next check
Ownership & development control
Partial evidenceStadtwerke Bad Vilbel records a joint 2017 acquisition of the broader Wertachtal conversion area with Bürgerstiftung Bad Vilbel. Its 2026/27 business plan describes the site and sales of land not needed for the energy project. Polarise says it plans to acquire the former transmitter building and adjacent land; closing and exact parcel title have not been verified.
Sources & next check
Demand & location fit
Partial evidencePolarise is the named intended AI-cloud operator/developer, and its platform financing announcement cites sovereign-AI demand. No named Amberg customer, signed site allocation, GPU deployment or leased load is public.
Sources & next check
Programme & delivery
Partial evidencePolarise targets mid-2027 and has announced platform debt financing up to an undisclosed substantial double-digit euro amount. Neither establishes project finance, land closing, permission, construction, energisation or commissioning, and the authority evidence still shows pre-planning.
Sources & next check
Not assessed
Evidence still needed
- Land-use zoning
The site boundary has not been matched to the current adopted zoning map and data-centre use policy.
- Fibre & dark fibre
No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.
- Land, footprint & access
Gross and net developable area, boundaries, access rights, easements, setbacks and expansion space need site-specific evidence.
- Flood, ground & environment
Flood risk, ground conditions, contamination, ecology, heritage, noise and air-quality constraints have not been fully assessed here.
- Water, cooling & heat
Water availability and discharge, cooling technology, peak demand, heat reuse and utility agreements remain to be verified.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Specialists & vendors
Energy and site partner named by Polarise for the pre-planning concept; not a campus-wide MEP, utility or construction appointment.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- Polarise: Amberg proposal and planned acquisitionpolarise.eu · 10 Mar 2026
- Polarise: financing and updated 65 MW initial planpolarise.eu · 18 Aug 2026
- Gemeinde Amberg: current published land-use planning proceduresgemeinde-amberg.de · Publication date unstated
- Kreisbote: mayor describes oral request and required planning sequencekreisbote.de · 13 Mar 2026
- Stadtwerke Bad Vilbel: Wertachtal conversion-area acquisition chronologysw-bv.de · Publication date unstated
- Stadtwerke Bad Vilbel: 2026/27 business plan — Wertachtal land and generationrim.ekom21.de · 3 Nov 2025
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.