Data centres
European projects, capacity and delivery teams.
Map viewGermany
Country coverage, not site locations. Small countries are available in the filter. Boundaries: Natural Earth, public domain.
Counts follow your search, region, stage and evidence filters. Select a country to filter the list.
8 projects in Germany8 with viability evidence
Campus substation; not converted into MW or treated as available IT load.
Campus substation; not converted into MW or treated as available IT load.
Capacity source200 MW import · Announced contracted grid connection
Operator’s August 2025 signed E.DIS connection announcement; supply targeted from 2027. Separate from published 200 MVA substation/design figure; no conversion or energisation assumption.
Published claim
Polarise Amberg AI Factory — Wertachtal
Former Wertachtal transmitter, Amberg, Unterallgäu, Bavaria·Germany
Developer Polarise
Polarise's updated initial campus plan announced on 18 August 2026. It is not verified IT load, utility import entitlement or commissioned capacity.
Polarise's updated initial campus plan announced on 18 August 2026. It is not verified IT load, utility import entitlement or commissioned capacity.
Capacity source30 MW unspecified · Original initial plan (superseded)
Original 10 March 2026 promoter plan, superseded by the later 65 MW initial plan; not import or operating IT load.
Published claim
120 MW unspecified · Ultimate scalable plan
Promoter's potential ultimate scale inclusive of the initial phase; not additional capacity or secured import.
Published claim
Google Hanau campus
Hanau-Wolfgang·Germany
Developer Google; original development by NDC-GARBE, now GARBE.DC
FRA17 design IT capacity across eight data halls; not a utility MVA figure or available headroom.
FRA17 design IT capacity across eight data halls; not a utility MVA figure or available headroom.
BER01 facility, current operator claim; not utility import entitlement. Earlier design source stated 8.2 MW IT.
BER01 facility, current operator claim; not utility import entitlement. Earlier design source stated 8.2 MW IT.
Capacity source8.2 MW IT · Earlier design claim
BER01 design reported by project manager in November 2023; current operator page states 9 MW IT. Reconciliation of the design change is not published.
Published claim
Overall FRA03 facility; phase 1 operating, phase 2 scheduled for 2026/27.
Overall FRA03 facility; phase 1 operating, phase 2 scheduled for 2026/27.
Proposed full FRA04 development; capacity depends on design.
Proposed full FRA04 development; capacity depends on design.
60 MW import · Acquisition-stage committed power
Operator-stated committed electrical supply when the site was acquired in January 2024; contract details, current energisation and available headroom unverified. Distinct from 40 MW IT design.
Published claim