Operating Marcoussis campus with separately evidenced expansion and occupied-building retrofit packages. Official environmental authorisation and phase-specific contractor/carrier evidence now supplement…
Read overviewData4 PAR01 — Marcoussis
Marcoussis / Nozay, France
Watch this site
Watch Data4 PAR01 — Marcoussis
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
10 cited sources · 8 utility and planning categories reviewed.
Review evidence and gapsReconcile the historic connection description with the executed current agreement, energised phases and reinforcement commissioning.
Open the full checkOverview
Operating Marcoussis campus with separately evidenced expansion and occupied-building retrofit packages. Official environmental authorisation and phase-specific contractor/carrier evidence now supplement operator specifications; current import rights and phase completion still require reconciliation.
- Developer / applicant
- Data4
- Owner
- Not verified
- Operator
- Data4
Planning and delivery status
Existing campus described as serving customers in the May 2025 operator announcement.
Stage source: 16 May 2025Project intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
France grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Campus-specific electrical/power capacity on operator page; not confirmed commissioned IT load.
Published claimProject source recordThe 2023 MRAe opinion describes two 90 kV underground feeds from Villejust and a historical 100 MW supply claim, while requiring the proposed 225 kV reinforcement to enter the project assessment. The current operator publishes 250 MW at campus scope. These dated statements do not prove present import rights or spare capacity.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
8 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceGéorisques identifies authorised operating establishment 0006522360 and lists an environmental authorisation dated 31 May 2024, following January 2024 advance-construction prescriptions. This verifies a regulatory record, not completion of every campus phase.
Sources & next check
Grid & import rights
Partial evidenceThe 2023 MRAe opinion describes two 90 kV underground feeds from Villejust and a historical 100 MW supply claim, while requiring the proposed 225 kV reinforcement to enter the project assessment. The current operator publishes 250 MW at campus scope. These dated statements do not prove present import rights or spare capacity.
Sources & next check
Fibre & dark fibre
Partial evidenceSipartech’s 10 September 2026 list identifies PAR1 buildings DC1–DC12, DC14 and DC17–DC24 as on-net. This is named building-level carrier evidence; no dark-fibre pairs, customer handoff or physically diverse ducts are verified. The broader operator claim of more than 70 carriers across its Paris campus does not allocate all carriers to this building.
Sources & next check
Land, footprint & access
Partial evidenceDATA4 publishes a 110 hectares campus-specific area and a street address. This supports the operating footprint but is not title or cadastral evidence.
Sources & next check
Flood, ground & environment
Partial evidenceThe 2023 MRAe review identified uncompleted ecological compensation from earlier clearance and requested a wetland diagnostic and stronger whole-campus impact assessment. Later authorisation is listed, but closure of those historic findings was not verified.
Sources & next check
Water, cooling & heat
Partial evidenceData4’s June 2025 release identifies a DC01 direct-liquid-cooling pilot with named CDU, equipment, load-bank and assessment partners. It describes a commissioning programme, not verified performance across every campus building.
Sources & next check
Demand & location fit
Partial evidenceThe operator cites proximity to the Paris-Saclay technology cluster and offers dedicated-building capacity. No named customer or contracted demand is disclosed for this campus record.
Sources & next check
Programme & delivery
Partial evidenceThe historic Zone 2 Nord dossier targeted completion by 2027. Cellpack’s DC23 reference instead describes a 2024–2026 package and planned 2026 completion. Neither forecast independently establishes handover.
Sources & next check
Not assessed
Evidence still needed
- Land-use zoning
The site boundary has not been matched to the current adopted zoning map and data-centre use policy.
- Ownership & development control
Legal title, land-owning entity, development-control route and restrictions need verification. A named developer does not establish availability.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Architect
DC19 architect named in Gesys project reference; not an appointment for all campus buildings.
Appointment sourceEngineering consultant
DC19 technical assistance, commissioning and execution management for technical trades; consultant records completion in January/March 2023.
Appointment sourceDC01 direct-liquid-cooling life-cycle assessment; not a campus-wide lead-design appointment.
Appointment sourceSpecialists & vendors
Design and construction of precast structures for DC21/DC23. The partner French construction group is unnamed; no campus-wide GC role inferred.
Appointment sourceDC23 medium- and low-voltage connection products, certification and installer training through Equans, with 2024–2026 project period.
Appointment sourceDC01 retrofit direct-liquid-cooling design collaboration; source does not establish a campus-wide electrical contract.
Appointment sourceDC01 direct-liquid-cooling CDU design/supply collaboration.
Appointment sourceDC01 direct-liquid-cooling equipment and operational system implementation.
Appointment sourceDC01 pilot hybrid air/liquid load banks used for infrastructure testing.
Appointment sourceDC01 cooling commissioning collaboration and third-party validation of test scripts described by Data4.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- Data4 Paris campus specificationsdata4group.com · Publication date unstated
- Data4 unveils PAR03 campus plansdata4group.com · 16 May 2025
- Géorisques: DATA 4 SERVICE establishment 0006522360 and authorisation registergeorisques.gouv.fr · Publication date unstated
- MRAe APJIF-2023-041: Marcoussis Zone 2 Nord environmental opinionmrae.developpement-durable.gouv.fr · 9 Aug 2023
- Sipartech: on-net locations, update 10 September 2026sipartech.com · 10 Sept 2026
- Generale Prefabbricati: Data4 DC21/DC23 precast structuresgeneraleprefabbricatispa.com · Publication date unstated
- Gesys: DC19 technical assistance, commissioning and architectgesys-ing.com · Publication date unstated
- BBC Cellpack: DC23 medium/low-voltage products through Equanscellpack.com · Publication date unstated
- Data4: DC01 direct-liquid-cooling implementation and named partnersdata4group.com · 2 Jun 2025
- Data4: occupied DC01 retrofit and further PAR02 intentiondata4group.com · 3 Feb 2025