Published capacity250 MW importPublished claimProposed grid-connection demand in the MRAe opinion; not secured import or IT load. The opinion identifies excess connection capacity beyond this project’s needs.
Proposed grid-connection demand in the MRAe opinion; not secured import or IT load. The opinion identifies excess connection capacity beyond this project’s needs.
75 MW IT · DC01 planned IT Planned building IT load; not live or secured import. Published claim
37.5 MW IT · DC02 planned IT Planned building IT load; not live or secured import. Published claim
15 MW IT · DC03 planned IT Planned building IT load; not live or secured import. Published claim
Published capacity150 MW ITPublished claimOperator headline campus design capacity. The same page separately describes two buildings at 74.4 MW IT each; this numerical difference is unresolved. Not verified commissioned IT or contracted grid import.
Operator headline campus design capacity. The same page separately describes two buildings at 74.4 MW IT each; this numerical difference is unresolved. Not verified commissioned IT or contracted grid import.
74.4 MW IT · Per-building design claim Operator states this separately for each of two buildings. Not summed, converted or reconciled with the 150 MW IT headline. Published claim