Four-building PAR8–PAR11 campus with completed construction and current operating evidence. Team appointments distinguish PAR8 envelope/ground studies from PAR10/PAR11 fire protection.
Read overviewDigital Realty Paris Digital Park
La Courneuve, Paris, France
Watch this site
Watch Digital Realty Paris Digital Park
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
9 cited sources · 7 utility and planning categories reviewed.
Review evidence and gapsReconcile as-built connections and phase demand rights with the 76 MW IT design total.
Open the full checkOverview
Four-building PAR8–PAR11 campus with completed construction and current operating evidence. Team appointments distinguish PAR8 envelope/ground studies from PAR10/PAR11 fire protection.
- Developer / applicant
- Digital Realty
- Owner
- Not verified
- Operator
- Digital Realty
Planning and delivery status
Current undated PAR11 service listing and a May 2026 supplier account support campus operation following Mercury’s October 2025 handover. The 76 MW design total does not establish live or available capacity in every building.
Stage source: Publication date unstatedProject intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
France grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
Combined PAR8, PAR9, PAR10 and PAR11 campus design IT capacity; no available-capacity or MVA inference.
Published claimProject source recordThe historic design separated western-building Enedis connections from the RTE-fed eastern pair. This establishes a proposed network arrangement, not present contracted import.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
7 of 10 categories contain evidence. Each status applies to its specific claim.
Planning & decisions
Partial evidenceDRIEAT identifies the 24 September 2021 authorisation for INTERXION France’s four buildings PAR8–PAR11 at 2 avenue Marcel Cachin, AIOT 0006523747. Géorisques records authorised operation and a later inspection on 21 May 2026. This campus is distinct from PAR7 at rue du Rateau, AIOT 0006514850.
Sources & next check
Land-use zoning
Partial evidenceThe 2018 impact study locates the scheme in zone UE and identifies infrastructure servitudes. It predates the current planning framework.
Sources & next check
Grid & import rights
Partial evidenceThe historic design separated western-building Enedis connections from the RTE-fed eastern pair. This establishes a proposed network arrangement, not present contracted import.
Sources & next check
Land, footprint & access
Partial evidenceMercury identifies about 39,000 m² of technical space and a 7,500 m² public park. These are functional areas, not a verified developable land boundary.
Sources & next check
Flood, ground & environment
Partial evidenceThe 2018 study records contamination/remediation risks. The May 2025 DRIEAT inspection proposed corrective action on generator records, acoustic evidence, electrical isolation and emergency provisions. These were inspection findings, not proof of ongoing breach or a new refusal; closure remains unchecked.
Sources & next check
Water, cooling & heat
Partial evidenceThe 2025 inspection quotes the consent’s public-potable-water supply and monthly metering duties; it requested improved records of dry and adiabatic cooling operating hours. Contractor descriptions of hybrid/free cooling do not establish compliance or current water headroom.
Sources & next check
Programme & delivery
Partial evidenceDRIEAT found PAR8–PAR10 operating in May 2025 and records PAR10 delivery on 19 December 2024; its then-target for all four was 2027. Mercury’s 2020–2025 campus period and the 2026 PAR10/PAR11 fire-protection reference describe other milestones.
Sources & next check
Not assessed
Evidence still needed
- Fibre & dark fibre
No verified site entry, dark-fibre offer or physically diverse route assessment is recorded. Regional coverage alone is insufficient.
- Ownership & development control
Legal title, land-owning entity, development-control route and restrictions need verification. A named developer does not establish availability.
- Demand & location fit
Customer geography, latency, cloud or exchange nodes and a supported use case need project-specific evidence; national growth alone is insufficient.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Main contractor
Campus delivery including shell/core, architectural envelope, roof, MEP and architectural fit-out, modular plant and site infrastructure.
Appointment sourceArchitect
PAR8 architect identified in Arcora’s building-envelope reference.
Appointment sourceEngineering consultant
Full building-envelope engineering for PAR8; not the entire campus MEP scope.
Appointment source2018 PAR8 ground investigations and contaminated-land management plan.
Appointment sourcePAR8 G2-AVP geotechnical study dated 11 October 2018, identified in the impact study.
Appointment sourceSpecialists & vendors
Low-pressure water-mist fire-protection equipment for PAR10 and PAR11, supplied with Mercury.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- Mercury: PAR11 and Paris Digital Park handovermercuryeng.com · 21 Oct 2025
- Mercury: appointed campus expansion contractormercuryeng.com · 9 Apr 2024
- Mercury: Paris Digital Park portfoliomercuryeng.com · Publication date unstated
- Arcora: PAR8 envelope engineeringarcora.com · Publication date unstated
- VID FIREKILL: PAR10/PAR11 fire-protection deliveryvidfirekill.com · 15 May 2026
- Digital Realty: PAR11 facilitydigitalrealty.com · Publication date unstated
- La Courneuve: PAR8 environmental impact study, revision 1lacourneuve.fr · 26 Oct 2018
- DRIEAT: Paris Digital Park inspection of 23 May 2025, AIOT 0006523747georisques.gouv.fr · 23 May 2025
- Géorisques: INTERXION France, 2 avenue Marcel Cachin, establishment 0006523747georisques.gouv.fr · Publication date unstated
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.