Operating

Digital Realty ATH3

Koropi, Attica, Greece

Reviewed 28 Sept 20269 sources
Watch this site

Watch Digital Realty ATH3

Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.

Fields marked * are required.

Checking enquiry availability…

Request details

Register your interest in monitoring this record. Alerts are not active yet. Site Watch will cost €150 per site per month excluding VAT after any included trial.

Optional. Public information only. Do not include confidential or non-public information.

Project brief

Operating Koropi facility with 8 MW IT fully equipped design evidence and phase-specific construction records. The operator's current N+2 cooling field conflicts with the campus factsheet's N+1 description.

Read overview
Next check

Obtain commissioned load by phase and the utility contract; reconcile historical 6.8 MW unspecified design with the 8 MW IT fully equipped scope.

Open the full check

Overview

Operating Koropi facility with 8 MW IT fully equipped design evidence and phase-specific construction records. The operator's current N+2 cooling field conflicts with the campus factsheet's N+1 description.

Developer / applicant
Digital Realty
Owner
Digital Realty — project owner stated by DCarbon
Operator
Digital Realty

Planning and delivery status

METLEN confirmed final completion and handover on 12 August 2025. ELEMKA's 2021–2023 construction-package period and DCarbon's 2024 LEED Gold milestone describe earlier scopes; these dates are not interchangeable.

Stage source: 12 Aug 2025

Project intelligence. This record does not establish that the land or facility is available to acquire.

POWER STUDY

Power

What the power evidence establishes

The site-specific connection scope has not been established for this record.

Power classDNo qualifying rung

No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.

The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.

Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.

Read the rules and verification levels
01

Capacity ladder and evidence

Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.

01

Applied

Unknown

Not established from the public records reviewed.

What applied mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the applied connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the applied connection evidence cover?
Verification
Unknown
02

Offered

Unknown

Not established from the public records reviewed.

What offered mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the offered connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the offered connection evidence cover?
Verification
Unknown
03

Accepted / contracted

Unknown

Not established from the public records reviewed.

What accepted or contracted mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the accepted connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the accepted connection evidence cover?
Verification
Unknown
04

Energised

Unknown

Not established from the public records reviewed.

What energised mva is evidenced for the assessed site scope?
Event date
Unknown

Not established from the public records reviewed.

What is the effective date of the energised connection evidence?
Capacity boundary
Unknown

Not established from the public records reviewed.

Which buildings or phases does the energised connection evidence cover?
Verification
Unknown
Connection point and load boundaries
Network operator
Unknown

Not established from the public records reviewed.

Which TSO or DSO is responsible for this demand connection?
Connection point
Unknown

Not established from the public records reviewed.

What is the operator-confirmed connection substation or circuit?
Voltage
Unknown

Not established from the public records reviewed.

What voltage level is specified for the demand connection?
Straight-line distance
Unknown

Not established from the public records reviewed.

What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Published route length
Unknown

Not established from the public records reviewed.

What grid route length is published, and for which circuit?

IT load

Unknown

Not established from the public records reviewed.

What is the published IT load in MW?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the IT load in MW stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the IT load in MW cover?

Facility load

Unknown

Not established from the public records reviewed.

What is the published facility load in MW?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the facility load in MW stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the facility load in MW cover?

Import capacity

Unknown

Not established from the public records reviewed.

What is the published import capacity in MVA?
Basis
Unknown

Not established from the public records reviewed.

On what electrical basis is the import capacity in MVA stated?
Site / phase boundary
Unknown

Not established from the public records reviewed.

Which phase or campus does the import capacity in MVA cover?

These are different electrical quantities. No power factor, PUE or available import is assumed from an IT-load statement.

Connection agreement and conditions
Agreement type
Unknown

Not established from the public records reviewed.

What connection agreement type and current status are documented?
Phased capacity
Unknown

Not established from the public records reviewed.

Does the agreement impose phased import-capacity limits?
Flexibility obligations
Unknown

Not established from the public records reviewed.

What flexibility or curtailment obligations apply?
On-site generation obligations
Unknown

Not established from the public records reviewed.

What on-site generation obligations apply?
Securities posted
Unknown

Not established from the public records reviewed.

What securities are required, posted and still valid?
Longstop dates
Unknown

Not established from the public records reviewed.

What connection longstop or milestone dates apply?
02

Conflicts and scope comparisons

No conflicting pair is recorded. This does not establish that all public statements have been reconciled.

03

Greece grid context

Network publications frame the claim. They do not allocate capacity to this site.

No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.

04

Derived energisation window

Earliest plausible yearUnknown
Latest plausible yearUnknown

The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.

Rule

Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.

No observed inputs establish this result.

Dependencies driving the range

  • Connection-dependent reinforcement scope and completion dates: unknown.
  • Grid-works planning status and programme: unknown.
  • Applicable connection-policy conditions and programme: unknown.

What the earliest case requires

  • Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
  • Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
  • Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.

Missing inputs leave the range open

  • A dated, document-verified import-MVA rung for the assessed scope.
  • An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
  • Connection-dependent reinforcement scope and completion dates
  • Grid-works planning status and programme
  • Applicable connection-policy conditions and programme
05

Indicative HV and connection capex

Unknown

Rule and scope

Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.

No observed inputs establish this result.

Published connection works scope
Unknown

Not established from the public records reviewed.

What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Scope completeness
Unknown

Not established from the public records reviewed.

Is the published connection scope complete enough to match every component to a sourced benchmark?

Scope questions

  • Obtain a published complete connection scope with voltage, configuration and measured quantities.
  • Establish that every necessary connection-work component is included in the published scope.
  • Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
06

Alternatives and policy exposure

Behind-the-meter generation

Unknown

Not established from the public records reviewed.

What behind-the-meter generation is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require behind-the-meter generation?

Battery storage

Unknown

Not established from the public records reviewed.

What battery storage is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require battery storage?

Private wire

Unknown

Not established from the public records reviewed.

What a private wire is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require a private wire?

Gas

Unknown

Not established from the public records reviewed.

What gas supply or generation is evidenced, and at what scope?
Planning / policy requirement
Unknown

Not established from the public records reviewed.

Does the applicable planning or connection policy require gas supply or generation?

Connection claim against current policy

Unknown

Not established from the public records reviewed.

Does the published connection claim meet the policy applicable to its application date, location and agreement status?
07

Open questions for a Reality Check

Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.

60 questions to resolve
  1. Which TSO or DSO is responsible for this demand connection?

    Not established from the public records reviewed.

  2. What is the operator-confirmed connection substation or circuit?

    Not established from the public records reviewed.

  3. What voltage level is specified for the demand connection?

    Not established from the public records reviewed.

  4. What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?

    Not established from the public records reviewed.

  5. What grid route length is published, and for which circuit?

    Not established from the public records reviewed.

  6. What applied mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  7. What is the effective date of the applied connection evidence?

    Not established from the public records reviewed.

  8. Which buildings or phases does the applied connection evidence cover?

    Not established from the public records reviewed.

  9. What evidence level can be supported for capacityLadder.applied?

    Verification has not been established.

  10. What offered mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  11. What is the effective date of the offered connection evidence?

    Not established from the public records reviewed.

  12. Which buildings or phases does the offered connection evidence cover?

    Not established from the public records reviewed.

  13. What evidence level can be supported for capacityLadder.offered?

    Verification has not been established.

  14. What accepted or contracted mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  15. What is the effective date of the accepted connection evidence?

    Not established from the public records reviewed.

  16. Which buildings or phases does the accepted connection evidence cover?

    Not established from the public records reviewed.

  17. What evidence level can be supported for capacityLadder.accepted?

    Verification has not been established.

  18. What energised mva is evidenced for the assessed site scope?

    Not established from the public records reviewed.

  19. What is the effective date of the energised connection evidence?

    Not established from the public records reviewed.

  20. Which buildings or phases does the energised connection evidence cover?

    Not established from the public records reviewed.

  21. What evidence level can be supported for capacityLadder.energised?

    Verification has not been established.

  22. What connection agreement type and current status are documented?

    Not established from the public records reviewed.

  23. Does the agreement impose phased import-capacity limits?

    Not established from the public records reviewed.

  24. What flexibility or curtailment obligations apply?

    Not established from the public records reviewed.

  25. What on-site generation obligations apply?

    Not established from the public records reviewed.

  26. What securities are required, posted and still valid?

    Not established from the public records reviewed.

  27. What connection longstop or milestone dates apply?

    Not established from the public records reviewed.

  28. What is the published IT load in MW?

    Not established from the public records reviewed.

  29. On what electrical basis is the IT load in MW stated?

    Not established from the public records reviewed.

  30. Which phase or campus does the IT load in MW cover?

    Not established from the public records reviewed.

  31. What is the published facility load in MW?

    Not established from the public records reviewed.

  32. On what electrical basis is the facility load in MW stated?

    Not established from the public records reviewed.

  33. Which phase or campus does the facility load in MW cover?

    Not established from the public records reviewed.

  34. What is the published import capacity in MVA?

    Not established from the public records reviewed.

  35. On what electrical basis is the import capacity in MVA stated?

    Not established from the public records reviewed.

  36. Which phase or campus does the import capacity in MVA cover?

    Not established from the public records reviewed.

  37. What operator-published connection-to-energisation duration applies to this site and connection stage?

    An application-to-offer processing target is not an energisation duration.

  38. Which reinforcements does the connection depend on, and what dates are published?

    Not established from the public records reviewed.

  39. Which grid works require planning, and what is their current consent status and dated programme?

    Not established from the public records reviewed.

  40. Which connection-policy conditions apply, and when could they be satisfied?

    Not established from the public records reviewed.

  41. What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?

    Not established from the public records reviewed.

  42. Is the published connection scope complete enough to match every component to a sourced benchmark?

    Not established from the public records reviewed.

  43. What behind-the-meter generation is evidenced, and at what scope?

    Not established from the public records reviewed.

  44. Does the applicable planning or connection policy require behind-the-meter generation?

    Not established from the public records reviewed.

  45. What battery storage is evidenced, and at what scope?

    Not established from the public records reviewed.

  46. Does the applicable planning or connection policy require battery storage?

    Not established from the public records reviewed.

  47. What a private wire is evidenced, and at what scope?

    Not established from the public records reviewed.

  48. Does the applicable planning or connection policy require a private wire?

    Not established from the public records reviewed.

  49. What gas supply or generation is evidenced, and at what scope?

    Not established from the public records reviewed.

  50. Does the applicable planning or connection policy require gas supply or generation?

    Not established from the public records reviewed.

  51. Does the published connection claim meet the policy applicable to its application date, location and agreement status?

    Not established from the public records reviewed.

  52. Which checked country-grid sources and location-specific constraints apply to this connection?

    No country-context relationship has been established for this record.

  53. Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.

    Connection-cost scope question.

  54. Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.

    This missing input leaves an energisation bound unknown.

  55. Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.

    This missing input leaves an energisation bound unknown.

  56. Resolve the energisation input: Connection-dependent reinforcement scope and completion dates

    This missing input leaves an energisation bound unknown.

  57. Resolve the energisation input: Grid-works planning status and programme

    This missing input leaves an energisation bound unknown.

  58. Resolve the energisation input: Applicable connection-policy conditions and programme

    This missing input leaves an energisation bound unknown.

  59. Obtain a published complete connection scope with voltage, configuration and measured quantities.

    This scope or reference gap prevents a complete indicative connection capex band.

  60. Establish that every necessary connection-work component is included in the published scope.

    This scope or reference gap prevents a complete indicative connection capex band.

Use these questions to scope a Power Reality Check.

Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.

Request a Reality Check
Earlier capacity notes and source context
8 MW ITProject capacity

ATH3 fully equipped IT design stated by ELEMKA; not metered load, contracted grid import, or proof that all IT capacity is occupied.

Published claimProject source record
6.8 MW unspecifiedHistorical annual-report design figure

The 2021 annual report, p. 103, describes a 2 February 2022 appointment and 6.8 MW without an IT/import basis, with phase one then expected in December 2022. Not additive to or a conversion of ELEMKA's later 8 MW IT fully equipped design.

Published claimCapacity source
Import rights and connection evidence

ELEMKA's dated construction notice explicitly states 8 MW IT when fully equipped. Digital Realty specifies 2N UPS. Neither quantifies live customer load, utility import or available IT headroom. The 2021 annual report gives a historical 6.8 MW figure without an IT/import basis; its phase-one programme must not be merged into the 8 MW IT fully equipped design.

IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.

Planning & utilities

8 of 10 categories contain evidence. Each status applies to its specific claim.

Grid & import rights

Partial evidence

ELEMKA's dated construction notice explicitly states 8 MW IT when fully equipped. Digital Realty specifies 2N UPS. Neither quantifies live customer load, utility import or available IT headroom. The 2021 annual report gives a historical 6.8 MW figure without an IT/import basis; its phase-one programme must not be merged into the 8 MW IT fully equipped design.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Obtain commissioned load by phase and the utility contract; reconcile historical 6.8 MW unspecified design with the 8 MW IT fully equipped scope.

Fibre & dark fibre

Partial evidence

The ATH1/2/3 campus factsheet describes diverse meet-me rooms and points of entry, 20-plus carriers, SEE-CIX and GR-IX and a Google Cloud PoP. Campus services are not proof of each ATH3 external route or contracted capacity.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Confirm ATH3-specific cross-connect availability, physical external route diversity and rights.

Ownership & development control

Partial evidence

DCarbon names Digital Realty as project owner; ELEMKA's earlier construction record names Lamda Hellix S.A. This is a corporate/project naming sequence, not a current registered property-title check.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Resolve current legal landholder and tenure against registry evidence without equating operator branding with title.

Land, footprint & access

Partial evidence

Digital Realty currently lists 8,600 m² building size; ELEMKA gives 7,517 m² internal construction area. The earlier annual report also used 8,600 m² for the then-described design. These source-specific design/area measures are not an independently verified final gross area or cadastral parcel size.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Reconcile gross and internal areas with as-built plans and cadastral parcel/access records.

Flood, ground & environment

Partial evidence

The ministry-hosted March 2026 report for 2025 identifies ATH3 separately within Digital Realty's Koropi installation: five diesel sets, each 6.04 MW thermal input. It reports the operating-notification/standard-environmental-commitments route and use of the under-500-hours exemption. This is an operator compliance return, not a newly issued permit or electrical-capacity certificate.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Retrieve the operating notification and applicable environmental commitments, then verify generator hours and emissions returns against their conditions.

Water, cooling & heat

Partial evidence

Digital Realty's live ATH3 page states N+2 cooling, while the combined Athens factsheet describes N+1. The discrepancy cannot be resolved by assuming the campus and building scopes are identical.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Obtain the current ATH3 cooling schedule and explain the N+1/N+2 scope and date difference.

Demand & location fit

Partial evidence

An active facility listing and METLEN's final handover support operational delivery, while the campus connectivity offer supports a market proposition. Neither states ATH3 occupancy or committed customer MW.

Sources & next check
Evidence reviewed 27 Sept 2026

Next check

Seek dated building-specific fitted-out, leased and available capacity.

Programme & delivery

Partial evidence

The regulator-hosted return gives ATH3 generator start dates of 19–20 June and 25 September 2023. These are equipment milestones; METLEN's 12 August 2025 final handover and DCarbon's 2024 LEED milestone retain separate meanings.

Sources & next check
Evidence reviewed 28 Sept 2026

Next check

Reconcile generator commissioning, first customer operation and final handover without using thermal plant dates as the campus opening date.

Not assessed

Planning & decisionsLand-use zoning
Evidence still needed
  • Planning & decisions

    A current planning decision, conditions and any appeal or court proceedings still need to be checked.

  • Land-use zoning

    The site boundary has not been matched to the current adopted zoning map and data-centre use policy.

Project team

Appointments are limited to the project, phase and scope supported by each source.

Main contractor

Engineering consultant

Specialists & vendors

ATH3 earthworks, concrete and MEP construction scope described under METLEN; published September 2021–July 2023 package period is separate from METLEN's August 2025 final handover.

Appointment source

Unlisted roles have no project-specific appointment recorded.

Sources

Publication dates are shown where known. Review dates do not establish approval or commissioning.

  1. METLEN — ATH3 handover and general contractor rolemetlen.com · 12 Aug 2025
  2. DCarbon — ATH3 owner and sustainability servicesdcarbon.co · Publication date unstated
  3. Digital Realty — ATH3 specificationsdigitalrealty.com · Publication date unstated
  4. Digital Realty — ATH1/ATH2/ATH3 property factsheetgo2.digitalrealty.com · Publication date unstated
  5. ELEMKA — ATH3 Koropi construction scopeelemka.gr · Publication date unstated
  6. ELEMKA — ATH3 construction and fully equipped IT designelemka.gr · Publication date unstated
  7. MYTILINEOS — 2021 annual report, p. 103: historical ATH3 appointment/designelemka.gr · Publication date unstated
  8. Greek environment ministry — Digital Realty Hellas 2025 combustion-emissions report, March 2026ypen.gov.gr · Publication date unstated
  9. Greek environment ministry — medium-combustion-plant register and operator returnsypen.gov.gr · Publication date unstated

Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.