Operating Koropi facility with 8 MW IT fully equipped design evidence and phase-specific construction records. The operator's current N+2 cooling field conflicts with the campus factsheet's N+1 description.
Read overviewDigital Realty ATH3
Koropi, Attica, Greece
Watch this site
Watch Digital Realty ATH3
Register interest in updates to planning status, grid position, capacity claims, delivery teams and policy exposure. Every Power Reality Check client receives 60 days of Site Watch on their assessed site when monitoring is available.
9 cited sources · 8 utility and planning categories reviewed.
Review evidence and gapsObtain commissioned load by phase and the utility contract; reconcile historical 6.8 MW unspecified design with the 8 MW IT fully equipped scope.
Open the full checkOverview
Operating Koropi facility with 8 MW IT fully equipped design evidence and phase-specific construction records. The operator's current N+2 cooling field conflicts with the campus factsheet's N+1 description.
- Developer / applicant
- Digital Realty
- Owner
- Digital Realty — project owner stated by DCarbon
- Operator
- Digital Realty
Planning and delivery status
METLEN confirmed final completion and handover on 12 August 2025. ELEMKA's 2021–2023 construction-package period and DCarbon's 2024 LEED Gold milestone describe earlier scopes; these dates are not interchangeable.
Stage source: 12 Aug 2025Project intelligence. This record does not establish that the land or facility is available to acquire.
POWER STUDY
Power
What the power evidence establishes
The site-specific connection scope has not been established for this record.
No same-scope, dated import-MVA rung has document-seen or better verification. Nearby infrastructure, IT MW and marketing claims cannot upgrade the class.
The class describes published documentary evidence at its stated date. It does not prove current contractual rights, transferability or an energisation date.
Class describes evidence maturity. Public records do not prove current contractual rights, transferable capacity or an energisation date. This record has not received a complete power study review.
Read the rules and verification levelsCapacity ladder and evidence
Each rung is a separate MVA claim for its stated site or phase. A missing rung is unknown.
Applied
Not established from the public records reviewed.
What applied mva is evidenced for the assessed site scope?Offered
Not established from the public records reviewed.
What offered mva is evidenced for the assessed site scope?Accepted / contracted
Not established from the public records reviewed.
What accepted or contracted mva is evidenced for the assessed site scope?Energised
Not established from the public records reviewed.
What energised mva is evidenced for the assessed site scope?Conflicts and scope comparisons
No conflicting pair is recorded. This does not establish that all public statements have been reconciled.
Greece grid context
Network publications frame the claim. They do not allocate capacity to this site.
No country context entries have been linked to this site. Applicable policy, capacity information and reinforcement dependencies need review.
Derived energisation window
The observed inputs do not establish a bounded delivery range. Open bounds stay unknown.
Rule
Use only a same-scope, dated, document-verified capacity rung and an applicable duration to energisation published by the observed site operator. The named process operator and a named source publisher must match that operator. Earliest year is the maximum of stage date plus minimum duration and each evidenced readiness constraint. Latest year is the maximum of stage date plus maximum duration and each published upper constraint only when every required input is bounded. An offer-processing duration is excluded. A missing required input leaves the affected bound unknown; no padding or contractual delivery promise is inferred.
No observed inputs establish this result.
Dependencies driving the range
- Connection-dependent reinforcement scope and completion dates: unknown.
- Grid-works planning status and programme: unknown.
- Applicable connection-policy conditions and programme: unknown.
What the earliest case requires
- Connection-dependent reinforcement scope and completion dates introduces no later constraint than the earliest case; this remains unverified.
- Grid-works planning status and programme introduces no later constraint than the earliest case; this remains unverified.
- Applicable connection-policy conditions and programme introduces no later constraint than the earliest case; this remains unverified.
Missing inputs leave the range open
- A dated, document-verified import-MVA rung for the assessed scope.
- An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
- Connection-dependent reinforcement scope and completion dates
- Grid-works planning status and programme
- Applicable connection-policy conditions and programme
Indicative HV and connection capex
Unknown
Rule and scope
Sum each published complete scope quantity multiplied by the matching published benchmark minimum and maximum. Configuration, voltage, route type, unit, country applicability, currency and explicit price base year must match. No assumed route length, transformer count, exchange rate, inflation, fee uplift or partial index is inserted. The result is an indicative benchmark band, not an operator quotation or contractual connection charge.
No observed inputs establish this result.
Scope questions
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
- Establish that every necessary connection-work component is included in the published scope.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Alternatives and policy exposure
Behind-the-meter generation
Not established from the public records reviewed.
What behind-the-meter generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require behind-the-meter generation?Battery storage
Not established from the public records reviewed.
What battery storage is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require battery storage?Private wire
Not established from the public records reviewed.
What a private wire is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require a private wire?Gas
Not established from the public records reviewed.
What gas supply or generation is evidenced, and at what scope?Planning / policy requirement
Not established from the public records reviewed.
Does the applicable planning or connection policy require gas supply or generation?Connection claim against current policy
Not established from the public records reviewed.
Does the published connection claim meet the policy applicable to its application date, location and agreement status?Open questions for a Reality Check
Generated from unknown fields, missing derivation inputs and unresolved evidence. The questions identify the documents or specialist checks needed next.
60 questions to resolve
- Which TSO or DSO is responsible for this demand connection?
Not established from the public records reviewed.
- What is the operator-confirmed connection substation or circuit?
Not established from the public records reviewed.
- What voltage level is specified for the demand connection?
Not established from the public records reviewed.
- What are the evidenced site and connection-point coordinates, and their calculated straight-line distance?
Not established from the public records reviewed.
- What grid route length is published, and for which circuit?
Not established from the public records reviewed.
- What applied mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the applied connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the applied connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.applied?
Verification has not been established.
- What offered mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the offered connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the offered connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.offered?
Verification has not been established.
- What accepted or contracted mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the accepted connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the accepted connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.accepted?
Verification has not been established.
- What energised mva is evidenced for the assessed site scope?
Not established from the public records reviewed.
- What is the effective date of the energised connection evidence?
Not established from the public records reviewed.
- Which buildings or phases does the energised connection evidence cover?
Not established from the public records reviewed.
- What evidence level can be supported for capacityLadder.energised?
Verification has not been established.
- What connection agreement type and current status are documented?
Not established from the public records reviewed.
- Does the agreement impose phased import-capacity limits?
Not established from the public records reviewed.
- What flexibility or curtailment obligations apply?
Not established from the public records reviewed.
- What on-site generation obligations apply?
Not established from the public records reviewed.
- What securities are required, posted and still valid?
Not established from the public records reviewed.
- What connection longstop or milestone dates apply?
Not established from the public records reviewed.
- What is the published IT load in MW?
Not established from the public records reviewed.
- On what electrical basis is the IT load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the IT load in MW cover?
Not established from the public records reviewed.
- What is the published facility load in MW?
Not established from the public records reviewed.
- On what electrical basis is the facility load in MW stated?
Not established from the public records reviewed.
- Which phase or campus does the facility load in MW cover?
Not established from the public records reviewed.
- What is the published import capacity in MVA?
Not established from the public records reviewed.
- On what electrical basis is the import capacity in MVA stated?
Not established from the public records reviewed.
- Which phase or campus does the import capacity in MVA cover?
Not established from the public records reviewed.
- What operator-published connection-to-energisation duration applies to this site and connection stage?
An application-to-offer processing target is not an energisation duration.
- Which reinforcements does the connection depend on, and what dates are published?
Not established from the public records reviewed.
- Which grid works require planning, and what is their current consent status and dated programme?
Not established from the public records reviewed.
- Which connection-policy conditions apply, and when could they be satisfied?
Not established from the public records reviewed.
- What complete connection scope is published: bays, stations, voltage, circuits, route lengths and underground or overhead configuration?
Not established from the public records reviewed.
- Is the published connection scope complete enough to match every component to a sourced benchmark?
Not established from the public records reviewed.
- What behind-the-meter generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require behind-the-meter generation?
Not established from the public records reviewed.
- What battery storage is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require battery storage?
Not established from the public records reviewed.
- What a private wire is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require a private wire?
Not established from the public records reviewed.
- What gas supply or generation is evidenced, and at what scope?
Not established from the public records reviewed.
- Does the applicable planning or connection policy require gas supply or generation?
Not established from the public records reviewed.
- Does the published connection claim meet the policy applicable to its application date, location and agreement status?
Not established from the public records reviewed.
- Which checked country-grid sources and location-specific constraints apply to this connection?
No country-context relationship has been established for this record.
- Identify network and customer works, upstream reinforcement, land and wayleaves, taxes, fees, securities, contingency and the price base.
Connection-cost scope question.
- Resolve the energisation input: A dated, document-verified import-MVA rung for the assessed scope.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: An applicable duration from the evidenced stage to energisation, published by and matched to the observed site operator, rather than an offer-processing target.
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Connection-dependent reinforcement scope and completion dates
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Grid-works planning status and programme
This missing input leaves an energisation bound unknown.
- Resolve the energisation input: Applicable connection-policy conditions and programme
This missing input leaves an energisation bound unknown.
- Obtain a published complete connection scope with voltage, configuration and measured quantities.
This scope or reference gap prevents a complete indicative connection capex band.
- Establish that every necessary connection-work component is included in the published scope.
This scope or reference gap prevents a complete indicative connection capex band.
Request an assessment of this record and the evidence needed next. Share only public information or documents you are authorised to provide.
Request a Reality CheckEarlier capacity notes and source context
ATH3 fully equipped IT design stated by ELEMKA; not metered load, contracted grid import, or proof that all IT capacity is occupied.
Published claimProject source recordThe 2021 annual report, p. 103, describes a 2 February 2022 appointment and 6.8 MW without an IT/import basis, with phase one then expected in December 2022. Not additive to or a conversion of ELEMKA's later 8 MW IT fully equipped design.
Published claimCapacity sourceELEMKA's dated construction notice explicitly states 8 MW IT when fully equipped. Digital Realty specifies 2N UPS. Neither quantifies live customer load, utility import or available IT headroom. The 2021 annual report gives a historical 6.8 MW figure without an IT/import basis; its phase-one programme must not be merged into the 8 MW IT fully equipped design.
IT load, facility demand, import capacity and equipment ratings retain their stated scope. A published figure does not establish spare or transferable supply.
Planning & utilities
8 of 10 categories contain evidence. Each status applies to its specific claim.
Grid & import rights
Partial evidenceELEMKA's dated construction notice explicitly states 8 MW IT when fully equipped. Digital Realty specifies 2N UPS. Neither quantifies live customer load, utility import or available IT headroom. The 2021 annual report gives a historical 6.8 MW figure without an IT/import basis; its phase-one programme must not be merged into the 8 MW IT fully equipped design.
Sources & next check
Fibre & dark fibre
Partial evidenceThe ATH1/2/3 campus factsheet describes diverse meet-me rooms and points of entry, 20-plus carriers, SEE-CIX and GR-IX and a Google Cloud PoP. Campus services are not proof of each ATH3 external route or contracted capacity.
Sources & next check
Ownership & development control
Partial evidenceDCarbon names Digital Realty as project owner; ELEMKA's earlier construction record names Lamda Hellix S.A. This is a corporate/project naming sequence, not a current registered property-title check.
Sources & next check
Land, footprint & access
Partial evidenceDigital Realty currently lists 8,600 m² building size; ELEMKA gives 7,517 m² internal construction area. The earlier annual report also used 8,600 m² for the then-described design. These source-specific design/area measures are not an independently verified final gross area or cadastral parcel size.
Sources & next check
Flood, ground & environment
Partial evidenceThe ministry-hosted March 2026 report for 2025 identifies ATH3 separately within Digital Realty's Koropi installation: five diesel sets, each 6.04 MW thermal input. It reports the operating-notification/standard-environmental-commitments route and use of the under-500-hours exemption. This is an operator compliance return, not a newly issued permit or electrical-capacity certificate.
Sources & next check
Water, cooling & heat
Partial evidenceDigital Realty's live ATH3 page states N+2 cooling, while the combined Athens factsheet describes N+1. The discrepancy cannot be resolved by assuming the campus and building scopes are identical.
Sources & next check
Demand & location fit
Partial evidenceAn active facility listing and METLEN's final handover support operational delivery, while the campus connectivity offer supports a market proposition. Neither states ATH3 occupancy or committed customer MW.
Sources & next check
Programme & delivery
Partial evidenceThe regulator-hosted return gives ATH3 generator start dates of 19–20 June and 25 September 2023. These are equipment milestones; METLEN's 12 August 2025 final handover and DCarbon's 2024 LEED milestone retain separate meanings.
Sources & next check
Not assessed
Evidence still needed
- Planning & decisions
A current planning decision, conditions and any appeal or court proceedings still need to be checked.
- Land-use zoning
The site boundary has not been matched to the current adopted zoning map and data-centre use policy.
Project team
Appointments are limited to the project, phase and scope supported by each source.
Main contractor
General contractor for ATH3 as expressly stated in the handover announcement.
Appointment sourceEngineering consultant
Sustainability consultancy, energy modelling and daylight analysis supporting ATH3 LEED Gold certification.
Appointment sourceSpecialists & vendors
ATH3 earthworks, concrete and MEP construction scope described under METLEN; published September 2021–July 2023 package period is separate from METLEN's August 2025 final handover.
Appointment sourceUnlisted roles have no project-specific appointment recorded.
Sources
Publication dates are shown where known. Review dates do not establish approval or commissioning.
- METLEN — ATH3 handover and general contractor rolemetlen.com · 12 Aug 2025
- DCarbon — ATH3 owner and sustainability servicesdcarbon.co · Publication date unstated
- Digital Realty — ATH3 specificationsdigitalrealty.com · Publication date unstated
- Digital Realty — ATH1/ATH2/ATH3 property factsheetgo2.digitalrealty.com · Publication date unstated
- ELEMKA — ATH3 Koropi construction scopeelemka.gr · Publication date unstated
- ELEMKA — ATH3 construction and fully equipped IT designelemka.gr · Publication date unstated
- MYTILINEOS — 2021 annual report, p. 103: historical ATH3 appointment/designelemka.gr · Publication date unstated
- Greek environment ministry — Digital Realty Hellas 2025 combustion-emissions report, March 2026ypen.gov.gr · Publication date unstated
- Greek environment ministry — medium-combustion-plant register and operator returnsypen.gov.gr · Publication date unstated
Original documents and maps retain their rights. Public access does not grant commercial redistribution rights.