Recorded research reviews across data centres and land.

Demand & infrastructure signals
234 matching entries

A review is a research check, not a new project announcement. Open a record for its source evidence.

Green Mountain OSL-EnebakkOperating

Enebakk, Oslo region, Norway

Operating three-building campus with completed phases in 2020, 2022 and 2024. Capacity withheld: the same page quotes 75 MW IT, 93 MW maximum and 94 MW line-of-sight capacity.

Review context

Operating three-building campus with completed phases in 2020, 2022 and 2024. Capacity withheld: the same page quotes 75 MW IT, 93 MW maximum and 94 MW line-of-sight capacity.

Latest dated source: 24 Jun 2026. This is a source publication date, not the review or construction date.

Open full evidence
Green Mountain SVG-RennesøyOperating

Rennesøy, Stavanger region, Norway

Operating former NATO mountain-hall facility. Operator gives a maximum IT capacity of 25 MW; this is not available capacity.

Review context

Operating former NATO mountain-hall facility. Operator gives a maximum IT capacity of 25 MW; this is not available capacity.

Latest dated source: 31 Mar 2026. This is a source publication date, not the review or construction date.

Open full evidence
Green Mountain TEL-RjukanOperating

Rjukan, Telemark, Norway

Operating Rjukan campus. Hima heat recovery entered operation in autumn 2025; a June 2026 pollution permit is newly surfaced. The 50 MW figure is potential IT capacity, while the undated operator page separately describes supply-leg claims and upgrade plans.

Review context

Operating Rjukan campus. Hima heat recovery entered operation in autumn 2025; a June 2026 pollution permit is newly surfaced. The 50 MW figure is potential IT capacity, while the undated operator page separately describes supply-leg claims and upgrade plans.

Latest dated source: 10 Jun 2026. This is a source publication date, not the review or construction date.

Open full evidence
Greenergy Data Centers — 22 MW expansionUnder construction

Hüüru, Tallinn region, Estonia

Expansion of the operating Tallinn-region campus. The record tracks the new 22 MW package and avoids labelling its target completion as an achieved milestone.

Review context

Expansion of the operating Tallinn-region campus. The record tracks the new 22 MW package and avoids labelling its target completion as an achieved milestone.

Latest dated source: 31 Jul 2026. This is a source publication date, not the review or construction date.

Open full evidence
GreenScale Derry — RRY10 campus (formerly Atlantic Hub)Under construction

Foyle Port Innovation Park, Maydown, Derry, United Kingdom

DTCP-backed development acquired through Atlantic Hub in 2024. GreenScale reports 119,000 m² acquired near Foyle Port; the registered land-owning SPV remains unverified. RRY11 is the initial phase, included here rather than counted again.

Review context

DTCP-backed development acquired through Atlantic Hub in 2024. GreenScale reports 119,000 m² acquired near Foyle Port; the registered land-owning SPV remains unverified. RRY11 is the initial phase, included here rather than counted again.

Latest dated source: 10 Apr 2026. This is a source publication date, not the review or construction date.

Open full evidence
Kevlinx BRU01Operating

Neder-Over-Heembeek, Brussels, Belgium

Operating first phases on citydev’s Galilei land under a long-term lease. Technical delivery now has a site-specific Elia route, cooling supplier and carrier relationship.

Review context

Operating first phases on citydev’s Galilei land under a long-term lease. Technical delivery now has a site-specific Elia route, cooling supplier and carrier relationship.

Latest dated source: 27 Mar 2026. This is a source publication date, not the review or construction date.

Open full evidence
LCL Brussels-North campus — DiegemOperating

Diegem, Brussels, Belgium

Existing Diegem campus expanded with its fifth facility, BN5. No whole-campus MW figure is asserted.

Review context

Existing Diegem campus expanded with its fifth facility, BN5. No whole-campus MW figure is asserted.

Latest dated source: 26 Mar 2026. This is a source publication date, not the review or construction date.

Open full evidence
maincubes BER01 — Go West campusOperating

Berlin, Germany

Operating GoWest data centre. Current operator claim is 9 MW IT; SMV published 8.2 MW IT at design stage. Lupp, SMV and ROM have distinct delivery appointments. The surrounding GoWest plan IX-55-3 was adopted in 2026; utility import rights and building-specific permit conditions remain unverified.

Review context

Operating GoWest data centre. Current operator claim is 9 MW IT; SMV published 8.2 MW IT at design stage. Lupp, SMV and ROM have distinct delivery appointments. The surrounding GoWest plan IX-55-3 was adopted in 2026; utility import rights and building-specific permit conditions remain unverified.

Latest dated source: 8 May 2026. This is a source publication date, not the review or construction date.

Open full evidence
maincubes BER02 / mainHub — Nauen campusUnder construction

Nauen, Berlin region, Germany

Campus with an effective data-centre zoning plan and substation/cable works underway. Published 200 MW contracted-connection claim and 200 MVA substation rating are retained separately; IT design range remains 144–186 MW.

Review context

Campus with an effective data-centre zoning plan and substation/cable works underway. Published 200 MW contracted-connection claim and 200 MVA substation rating are retained separately; IT design range remains 144–186 MW.

Latest dated source: 25 Mar 2026. This is a source publication date, not the review or construction date.

Open full evidence
Melita MadlienaOperating

Madliena, Swieqi, Malta

Historical operating facility newly captured at Triq il-Madliena. ERA ties the site to a granted combustion-plant permit; import MW/MVA remain unpublished.

Review context

Historical operating facility newly captured at Triq il-Madliena. ERA ties the site to a granted combustion-plant permit; import MW/MVA remain unpublished.

Latest dated source: Publication date not recorded. This is a source publication date, not the review or construction date.

Open full evidence
MERLIN Edged Bilbao-Arasur — BIL03 first buildingOperating

Rivabellosa, Álava, Spain

Operating first building at Arasur. Earlier 24 MW announcements are superseded here by Edged’s specific 2026 first-building figure.

Review context

Operating first building at Arasur. Earlier 24 MW announcements are superseded here by Edged’s specific 2026 first-building figure.

Latest dated source: 3 Apr 2026. This is a source publication date, not the review or construction date.

Open full evidence
MERLIN Edged Lisbon — VFX first development phaseUnder construction

Vila Franca de Xira, Lisbon region, Portugal

Under-construction Lisbon phase. Campus marketing totals and solar generation are not treated as this phase’s commissioned load.

Review context

Under-construction Lisbon phase. Campus marketing totals and solar generation are not treated as this phase’s commissioned load.

Latest dated source: 28 Jul 2026. This is a source publication date, not the review or construction date.

Open full evidence
Meta Clonee campusOperating

Clonee, County Meath, Ireland

Meta’s first Irish data-centre campus, distinct from neighbouring EngineNode. Named delivery appointments are recorded by package and phase. The developer’s 219 MW renewable-energy figure covers generation projects and is not campus IT load or contracted import; an older architect’s 108 MVA design statement is not treated as a current connection agreement.

Review context

Meta’s first Irish data-centre campus, distinct from neighbouring EngineNode. Named delivery appointments are recorded by package and phase. The developer’s 219 MW renewable-energy figure covers generation projects and is not campus IT load or contracted import; an older architect’s 108 MVA design statement is not treated as a current connection agreement.

Latest dated source: 3 Oct 2023. This is a source publication date, not the review or construction date.

Open full evidence
NorthC Eindhoven 2 — High Tech GatewayOperating

Eindhoven, Netherlands

De Schakel 35 facility, distinct from NorthC Eindhoven 1 at High Tech Campus.

Review context

De Schakel 35 facility, distinct from NorthC Eindhoven 1 at High Tech Campus.

Latest dated source: 12 May 2025. This is a source publication date, not the review or construction date.

Open full evidence
NXDATA-3 / BUH3Under construction

Tunari, Ilfov, Romania

Purpose-built north-Bucharest facility under development, with no published general contractor verified.

Review context

Purpose-built north-Bucharest facility under development, with no published general contractor verified.

Latest dated source: 25 Mar 2024. This is a source publication date, not the review or construction date.

Open full evidence
SIEN REAL Piaseczno — EnergetycznaIn planning

Piaseczno, Warsaw metropolitan area, Poland

Newly surfaced historical project for four three-storey data-centre and e-commerce-service buildings on 11 specified plots at Energetyczna Street. The authority decision records a proposed 110 kV supply design and standby plant, but neither is evidence of import capacity or transferable connection rights. Applicant identity is documented; owner, operator, building permission, import MW/MVA and delivery team remain unverified.

Review context

Newly surfaced historical project for four three-storey data-centre and e-commerce-service buildings on 11 specified plots at Energetyczna Street. The authority decision records a proposed 110 kV supply design and standby plant, but neither is evidence of import capacity or transferable connection rights. Applicant identity is documented; owner, operator, building permission, import MW/MVA and delivery team remain unverified.

Latest dated source: 19 Aug 2026. This is a source publication date, not the review or construction date.

Open full evidence
Alcalá Data Center — ADC1 & ADC2Operating

Alcalá de Henares, Madrid, Spain

Operating ADC1/ADC2 campus. Phase-specific 22.3 MW IT remains separate from ENGIE's unreconciled 35 MW campus description, the 100 MW expansion ambition and the Cisneros substation application.

Review context

Operating ADC1/ADC2 campus. Phase-specific 22.3 MW IT remains separate from ENGIE's unreconciled 35 MW campus description, the 100 MW expansion ambition and the Cisneros substation application.

Latest dated source: 17 Feb 2026. This is a source publication date, not the review or construction date.

Open full evidence
Andorra Telecom Data Centre — La MassanaOperating

La Massana, Andorra

Current business colocation offering in La Massana. Operator specifies redundant fibre up to 10 Gbps, UPS/generator resilience and in-row cooling; numerical IT power and property title remain unverified.

Review context

Current business colocation offering in La Massana. Operator specifies redundant fibre up to 10 Gbps, UPS/generator resilience and in-row cooling; numerical IT power and property title remain unverified.

Latest dated source: Publication date not recorded. This is a source publication date, not the review or construction date.

Open full evidence
Ark Longcross ParkOperating

Chertsey, Surrey, United Kingdom

Operating Nebius-hosting campus with traced phase-one delivery and consultant team. Contractor 16.8 MW phase-one and consultant 54 MW two-building design scopes are separate from unverified utility import.

Review context

Operating Nebius-hosting campus with traced phase-one delivery and consultant team. Contractor 16.8 MW phase-one and consultant 54 MW two-building design scopes are separate from unverified utility import.

Latest dated source: 16 Feb 2026. This is a source publication date, not the review or construction date.

Open full evidence
Arnes Data Centre MariborOperating

Maribor, Studenci, Slovenia

Newly surfaced historical research infrastructure on the DEM estate. Public research campus, not available off-market land.

Review context

Newly surfaced historical research infrastructure on the DEM estate. Public research campus, not available off-market land.

Latest dated source: 29 May 2025. This is a source publication date, not the review or construction date.

Open full evidence
Aruba Global Cloud Data Center — IT3Operating

Ponte San Pietro, Bergamo, Italy

Operating former Legler textile campus including DC-A/B/C. Municipal records add parcel-use, river-edge flood constraints and historic soil-investigation conditions; those historic concerns are not evidence of a current breach.

Review context

Operating former Legler textile campus including DC-A/B/C. Municipal records add parcel-use, river-edge flood constraints and historic soil-investigation conditions; those historic concerns are not evidence of a current breach.

Latest dated source: 6 Dec 2022. This is a source publication date, not the review or construction date.

Open full evidence
AtlasEdge Lisbon campus — LIS001 and planned expansionOperating

Carnaxide, Oeiras, Portugal

Operating LIS001 at Estrada Outurela 117a with planned adjoining expansion. Operator-stated 5.1 MW and 10 MVA have distinct scopes. This is an existing operator-controlled campus, not an available off-market land opportunity.

Review context

Operating LIS001 at Estrada Outurela 117a with planned adjoining expansion. Operator-stated 5.1 MW and 10 MVA have distinct scopes. This is an existing operator-controlled campus, not an available off-market land opportunity.

Latest dated source: 28 Oct 2025. This is a source publication date, not the review or construction date.

Open full evidence
Atman WAW-3 — first buildingOperating

Duchnice, Warsaw region, Poland

First phase of Atman's Warsaw-area campus. Public evidence links the developer, operator and first-building contractor; specialist consultants remain unidentified.

Review context

First phase of Atman's Warsaw-area campus. Public evidence links the developer, operator and first-building contractor; specialist consultants remain unidentified.

Latest dated source: 18 Sept 2025. This is a source publication date, not the review or construction date.

Open full evidence
atNorth FIN01 — Helsinki metro siteOperating

Helsinki, Finland

Operating Helsinki metro facility. The missing numeric field is restored to the operator’s 1.6 MW headline without assigning an IT or import basis.

Review context

Operating Helsinki metro facility. The missing numeric field is restored to the operator’s 1.6 MW headline without assigning an IT or import basis.

Latest dated source: Publication date not recorded. This is a source publication date, not the review or construction date.

Open full evidence
atNorth FIN04 campusUnder construction

Myllykoski / Kouvola, Finland

Phased FIN04 development with distinct municipal permits and power routes. The campus figure must not be assigned to individual buildings; original land acquisition, later planning areas and advertised campus area differ in scope.

Review context

Phased FIN04 development with distinct municipal permits and power routes. The campus figure must not be assigned to individual buildings; original land acquisition, later planning areas and advertised campus area differ in scope.

Latest dated source: 28 Aug 2026. This is a source publication date, not the review or construction date.

Open full evidence
atNorth ICE01 — ReykjavikOperating

Hafnarfjörður / Reykjavík metro, Iceland

Operating ICE01 at Steinhella 10, Hafnarfjörður. Historical municipal files add plot-allocation and as-built approval evidence; current title, demand rights and physically diverse fibre routes remain unverified.

Review context

Operating ICE01 at Steinhella 10, Hafnarfjörður. Historical municipal files add plot-allocation and as-built approval evidence; current title, demand rights and physically diverse fibre routes remain unverified.

Latest dated source: 8 Mar 2017. This is a source publication date, not the review or construction date.

Open full evidence
atNorth ICE02 — KeflavikOperating

Keflavik, Iceland

Operating Keflavik campus with phased expansion. The operator states 83 MW campus power without defining IT or import scope. Mannverk documents expansion delivery; the new capacity display remains an attributed campus claim, not verified import rights.

Review context

Operating Keflavik campus with phased expansion. The operator states 83 MW campus power without defining IT or import scope. Mannverk documents expansion delivery; the new capacity display remains an attributed campus claim, not verified import rights.

Latest dated source: 14 Dec 2023. This is a source publication date, not the review or construction date.

Open full evidence
atNorth ICE03 AkureyriOperating

Akureyri, Iceland

Operating Akureyri campus with expansion. Utility PPA, backup-power permit and local heat agreement now provide evidence beyond the operator headline; none equates the advertised 50 MW to energised demand rights.

Review context

Operating Akureyri campus with expansion. Utility PPA, backup-power permit and local heat agreement now provide evidence beyond the operator headline; none equates the advertised 50 MW to energised demand rights.

Latest dated source: 2 Sept 2025. This is a source publication date, not the review or construction date.

Open full evidence
atNorth NOR01 HaugalandIn planning

Haugaland / Tysvær, Norway

Planned 36-hectare site with municipal land-purchase confirmation and seller-reported Fagne contribution agreement. Rezoning, infrastructure completion and investment decision remain development dependencies.

Review context

Planned 36-hectare site with municipal land-purchase confirmation and seller-reported Fagne contribution agreement. Rezoning, infrastructure completion and investment decision remain development dependencies.

Latest dated source: 3 Jun 2026. This is a source publication date, not the review or construction date.

Open full evidence
atNorth SWE01 StockholmOperating

Kista / Stockholm, Sweden

Operating Kista facility on Varmvattnet 5 within Stockholm Exergi’s ground lease, under an Exergi–atNorth agreement. Historical contractor phase figures differ from the operator’s current 12 MW headline.

Review context

Operating Kista facility on Varmvattnet 5 within Stockholm Exergi’s ground lease, under an Exergi–atNorth agreement. Historical contractor phase figures differ from the operator’s current 12 MW headline.

Latest dated source: 14 Oct 2025. This is a source publication date, not the review or construction date.

Open full evidence

This feed combines the latest recorded project and land reviews with saved legacy record notes. It is not a complete field-by-field change history.