Operator-announced SWE02 site-power headline; not published IT load, utility import limit or MVA.
Operator-announced SWE02 site-power headline; not published IT load, utility import limit or MVA.
Capacity source
European projects, capacity and delivery teams.
Country coverage, not site locations. Small countries are available in the filter. Boundaries: Natural Earth, public domain.
Counts follow your search, region, stage and evidence filters. Select a country to filter the list.
4 projects in Sweden4 with viability evidence
Operator-announced SWE02 site-power headline; not published IT load, utility import limit or MVA.
Capacity sourceAnnounced ultimate campus site-power target; not energised import capacity or IT MW.
Capacity source200 MW import · Municipality-reported phase-one connection agreement
E.ON Energidistribution–atNorth connection agreement reported 28 May 2026, subject to new station/line permissions and delivery. Not operational power or additional to the 300 MW target.
Published claim
Operator-stated site power capacity for SWE01. IT capacity and utility MVA are not separately given.
1.5 MW unspecified · Historical first phase opened March 2022
Veidekke’s dated opening report; not present total campus capacity.
Published claim
11 MW unspecified · Historical full-build design
Veidekke’s March 2022 three-phase design scope. Basis and reconciliation to current operator 12 MW facility figure remain unresolved.
Published claim