Data centres
European projects, capacity and delivery teams.
Map viewFinland
Country coverage, not site locations. Small countries are available in the filter. Boundaries: Natural Earth, public domain.
Counts follow your search, region, stage and evidence filters. Select a country to filter the list.
6 projects in Finland6 with viability evidence
Planned total FIN04 campus capacity in the July YIT announcement; not the capacity of either individual YIT contract.
Planned total FIN04 campus capacity in the July YIT announcement; not the capacity of either individual YIT contract.
Nebius Pajarila — Lappeenranta campus
Kettukuja, Pajarila, Lappeenranta, South Karelia·Finland
Developer Nebius; Polarnode (development and enabling works)
Approximate ultimate campus rating; electrical basis and commissioned extent not established. Not first-phase import, IT load or available customer capacity.
Approximate ultimate campus rating; electrical basis and commissioned extent not established. Not first-phase import, IT load or available customer capacity.
Capacity sourceGlesys Pori / The Rock
Ulvila / Pori, Kivipellontie·Finland
Developer Ficolo (original conversion); Glesys (current operator)
Operator-stated total site capacity; no explicit IT/import scope or available allocation.
Operator-stated total site capacity; no explicit IT/import scope or available allocation.
Capacity sourceCurrent operator headline power capacity; IT, facility-demand and contracted-import bases are not distinguished. No spare or transferable allocation established.
Current operator headline power capacity; IT, facility-demand and contracted-import bases are not distinguished. No spare or transferable allocation established.
Capacity sourcePower access agreed with Caruna Espoo Oy; separate from 40 MW campus headline, not unallocated headroom.
Power access agreed with Caruna Espoo Oy; separate from 40 MW campus headline, not unallocated headroom.
Capacity source45 MW import · Operator-reported power-access agreement
Operator reports 45 MW access agreed with Caruna. Caruna says use of the expanded connection depends on additional transmission-grid capacity; current energised import and spare capacity are not established.
Published claim
45 MW facility · Skanska planned whole-facility gross capacity
Whole-facility gross capacity after expansion, as described by Skanska on 4 May 2026. Separate scope from agreed access; do not add these figures or infer IT MW.
Published claim