European projects, capacity and delivery teams.

Explore land research
Map viewUnited Kingdom

15 projects in United Kingdom15 with viability evidence

Thames Valley Park Data Centre

Earley, Reading·United Kingdom

Developer Mapeley / FH Trustees Limited and FH Trustees 2 Limited as applicants

In planningStage source 28 Sept 2026
Published capacity72 MW ITPublished claim
Proposed full-campus IT design capacity stated by the project team. The planning energy material separately describes approximately 110 MW peak facility demand; neither figure is commissioned load, secured grid import or available customer capacity.

Proposed full-campus IT design capacity stated by the project team. The planning energy material separately describes approximately 110 MW peak facility demand; neither figure is commissioned load, secured grid import or available customer capacity.

Capacity source

110 MW facility · Peak facility demand
Approximate completed-site peak demand reported from the submitted Energy Strategy, including cooling and electrical plant; not IT load or secured import.
Published claim

1.8 MW import · Existing site grid supply
Existing supply described for the administration building during the initial fuel-cell phase; not evidence of supply to the proposed data halls.
Published claim

60 MVA · Later SSEN connection
Applicant Utilities Statement scope reported as secured but dependent on transmission reinforcement and targeted from 2037. It does not cover the stated 110 MW facility peak and is not an achieved energisation.
Published claim

49.9 MW unspecified · Proposed on-site fuel-cell plant
Utilities Statement plant rating for proposed natural-gas solid-oxide fuel cells. The Energy Strategy separately gives about 42.5 MW initial effective supply; generation plant is not grid import capacity.
Published claim

10/10 evidence categories5 sources·5 team entries

Pure DC LON01B2 — Brent Cross expansion

Brent Cross, North London·United Kingdom

Developer Pure Data Centres Group

Under constructionStage source 3 Sept 2026
Published capacity70 MW unspecifiedPublished claim
Published B2 development capacity. The reviewed release does not distinguish IT load from facility demand; no import MVA is verified.

Published B2 development capacity. The reviewed release does not distinguish IT load from facility demand; no import MVA is verified.

6/10 evidence categories4 sources·2 team entries

DataVita DV1 — Fortis

Chapelhall, North Lanarkshire·United Kingdom

Developer DataVita

OperatingStage source 2 Sept 2026
Published capacity40 MW unspecifiedConflicting published claim
DV1 webpage overview power; conflicts with specification table.

DV1 webpage overview power; conflicts with specification table.

Capacity source

24 MW unspecified · Published power available
DV1 webpage technical specification; scope/date not reconciled with 40 MW overview.
Published claim

Published overview: DV1 webpage overview power; conflicts with specification table.

4/10 evidence categories5 sources·1 team entry

Green Mountain LON-East campus

Romford, London·United Kingdom

Developer Green Mountain

OperatingStage source 1 Sept 2026
Published capacity37 MW unspecifiedPublished claim
Secured/planned campus power capacity, including future development; not all live IT load.

Secured/planned campus power capacity, including future development; not all live IT load.

7/10 evidence categories5 sources·2 team entries

Kao Data Kenwood Point

Stockport, Greater Manchester·United Kingdom

Developer Kao Data

In planningStage source 1 Jul 2026
Published capacity40 MW unspecifiedPublished claim
Planned site capacity; 2024 approval announcement does not label the load basis.

Planned site capacity; 2024 approval announcement does not label the load basis.

4/10 evidence categories3 sources·2 team entries

Ark Longcross Park

Chertsey, Surrey·United Kingdom

Developer Ark Data Centres

OperatingStage source 16 Feb 2026
Published capacity16.8 MW unspecifiedPublished claim
Sweet Projects' phase-one case-study rating; MW basis is unspecified and not treated as IT power or utility import.

Sweet Projects' phase-one case-study rating; MW basis is unspecified and not treated as IT power or utility import.

Capacity source

54 MW unspecified · Two-centre consultant design scope
Stantec describes compute capacity across two centres; exact rating basis, current commissioned extent and utility import remain unverified.
Published claim

7/10 evidence categories7 sources·3 team entries

Kao Data KLON-03

Harlow·United Kingdom

Developer Kao Data

Under constructionStage source 18 Aug 2025
Published capacity17.6 MW ITPublished claim
KLON-03 planned hybrid-cooled IT capacity. Not secured utility MVA.

KLON-03 planned hybrid-cooled IT capacity. Not secured utility MVA.

8/10 evidence categories13 sources·4 team entries

GreenScale Derry — RRY10 campus (formerly Atlantic Hub)

Foyle Port Innovation Park, Maydown, Derry·United Kingdom

Developer GreenScale

Under constructionStage source 7 Aug 2025
Published capacity100 MW importPublished claim
Campus grid connections reported as secured by GreenScale; not commissioned IT load. Proposed expansion to 300+ MW is separate.

Campus grid connections reported as secured by GreenScale; not commissioned IT load. Proposed expansion to 300+ MW is separate.

5/10 evidence categories8 sources·5 team entries

CyrusOne LON6 — Iver Heath Data Park

Iver Heath·United Kingdom

Developer CyrusOne

In planningStage source 20 Jun 2025
Published capacity108 MW ITPublished claim
Current undated operator LON6 specification; planned capacity, not live or available capacity. The 2025 announcement and architect design still describe 90 MW IT; the change is not reconciled.

Current undated operator LON6 specification; planned capacity, not live or available capacity. The 2025 announcement and architect design still describe 90 MW IT; the change is not reconciled.

90 MW IT · Earlier announced design
June 2025 LON6 announcement and architect design; retained alongside the current 108 MW operator claim.
Published claim

160 MVA · Published incoming supply
Operator-published 132 kV active/active supply design. No utility agreement or transferable import rights independently verified; redundant feeds are not summed.
Published claim

8/10 evidence categories7 sources·9 team entries

VIRTUS LONDON2 — Hayes

Hayes, London·United Kingdom

Developer VIRTUS Data Centres

OperatingStage source 25 Apr 2024
Published capacity12.3 MW ITPublished claim
Current operator Hayes webpage rating. The specification PDF states 12.2 MW IT; the discrepancy is unresolved. Neither figure establishes spare capacity.

Current operator Hayes webpage rating. The specification PDF states 12.2 MW IT; the discrepancy is unresolved. Neither figure establishes spare capacity.

12.2 MW IT · Specification-sheet IT rating
LONDON2 PDF rating differs from the current webpage's 12.3 MW IT.
Published claim

20 MVA · Published incoming supply
Operator specification and September 2013 secured-supply announcement; not an independently inspected utility agreement or available expansion allocation.
Published claim

6/10 evidence categories6 sources·2 team entries

Vantage CWL1 — Newport / Cardiff campus

Newport, Cardiff Capital Region, South Wales·United Kingdom

Developer Vantage Data Centers

OperatingStage source 31 Jan 2024
Published capacity148 MW ITPublished claim
Full-campus design rating in the operator specification, consistent with January 2026 campus MW disclosure. Not commissioned, spare or transferable import capacity.

Full-campus design rating in the operator specification, consistent with January 2026 campus MW disclosure. Not commissioned, spare or transferable import capacity.

5/10 evidence categories4 sources·0 team entries

Kao Data KLON-02

Harlow·United Kingdom

Developer Kao Data

OperatingStage source 28 Nov 2023
Published capacity10 MW ITPublished claim
KLON-02 expandable design/2023 opening headline. Operator described 8.8 MW base expandable to 10 MW; current undated campus page still lists 8.8 MW. Neither is spare capacity or utility import.

KLON-02 expandable design/2023 opening headline. Operator described 8.8 MW base expandable to 10 MW; current undated campus page still lists 8.8 MW. Neither is spare capacity or utility import.

8.8 MW IT · Current campus-page building rating
KLON-02 operating rating on undated Harlow page; the 2023 design explanation identifies expansion to 10 MW.
Published claim

7/10 evidence categories13 sources·4 team entries

VIRTUS Stockley Park campus

Stockley Park, London·United Kingdom

Developer VIRTUS Data Centres

OperatingStage date not published
Published capacity112.5 MW ITPublished claim
Operator-published total campus IT load; not a statement of spare or occupied capacity.

Operator-published total campus IT load; not a statement of spare or occupied capacity.

27 MW IT · LONDON7 contractor design rating
Equans' LONDON7 design-and-build case study; historical phase-specific rating, not added to campus total.
Published claim

32.5 MW IT · LONDON7 current marketed rating
Current campus webpage's LONDON7 rating differs from Equans' 27 MW design scope; upgrade history not verified and not added to campus total.
Published claim

8/10 evidence categories6 sources·1 team entry
Project intelligence. Capacity claims do not establish available land or spare power.Suggest a project